Title: Reading Permit Files
1Reading Permit Files
- Enforcing Environmental Law
- January 2002
2State Pollutant Discharge Elimination System
3(No Transcript)
4Hydrologic Unit Codes (HUC)http//www.dec.state.n
y.us/website/dow/uwa/p4120104.gif
5(No Transcript)
6What is the legal effect of exceeding an action
level?
7When youve done BAT--BMP may be the next
step (unless theres ALARA, or LAER)
8Concentration (ug/L) x Flow (L/hr) x Time (hrs)
Mass Load (weight)
Process waste
Joined by storm drains
9(No Transcript)
10(No Transcript)
11(No Transcript)
12(No Transcript)
13(No Transcript)
14(No Transcript)
15(No Transcript)
16(No Transcript)
17(No Transcript)
18(No Transcript)
19(No Transcript)
20(No Transcript)
21(No Transcript)
22.5 permitted 8.9 measured
The RBCs have lost their growth of bacteria--I
believe due to the higher water temp--we are
doing a 6 hr. composite each work day with an
engineering firm to analyze the data to help
solve our problem.
232.0 permitted 10.6 measured
110.6 on ammonia was due to drawing supernate (?)
into plant at a high rate --illegible flow
regulated back into the plant with better results
24The 2.3 DO had to be operator error as the next
worst value was a 6.7 6.8 all the rest were
above 7.0
25Should the Friends of Murder Creek bring a
citizen suit against the Akron sewer plant?