Title: Production and Operations Management: Manufacturing and Services
1CHASE AQUILANO JACOBS
Operations Management
For Competitive Advantage
Chapter 15
Material Requirements Planning
2Chapter 14Materials Requirements Planning
- Material Requirements Planning (MRP)
- Components of an MRP System
- Time Fences
- MRP Logic and Product Structure Trees
- MRP Example
- MRP II
- Lot Sizing in MRP Programs
3Material Requirements PlanningDefined
- Materials requirements planning (MRP)
- Is the logic for determining the number of parts,
components, and materials needed to produce a
productthe quantity problem. - It provides time scheduling information
specifying when each of the components, parts,
materials should be ordered or producedwhen
problem. - Dependent demand drives MRP.
- MRP is a software system.
4Benefits of Material Requirements Planning
- Improved facility utilization
- Faster response to market
- Increased customer service
- Better inventory planning
- Reduced setup costs
5Components of Material Requirements Planning
- Master production schedule (MPS)
- Bill of materials (BOM)
- Inventory records file (IRF)
- Primary output reports
66
Material planning (MRP)
From Exhibit 14.6
- The McGraw-Hill Companies, Inc., 2001
7Master Production Schedule (MPS)
- Time-phased plan specifying how many and when the
firm plans to build each end item.
MPS (Specific End Items)
8Master production Schedule (MPS)
- The key input driver for MRP
- Tells MRP what to schedule, how many, and when
they are needed - It is time-phased requirement system
- Usually end items and special order components
- Aggregation of
- Customer firmed orders
- Forecast demands and safety stocks
- Service parts and seasonal adjustment, etc.
9Time Fences
- Purpose
- To maintain reasonably controlled flow through
the production system. - What they are
- Periods of time within which the customer can
make changes to the order (MPS).
10Types of Time Fences
- Frozen
- No schedule changes allowed within this window.
- Moderately Firm
- Specific changes allowed within product groups as
long as parts are available. - Flexible
- Significant variation allowed as long as overall
capacity requirements remain at the same levels.
11Example of Time Fences
Exhibit 14.5
12Bill of Materials (BOM) FileA Complete Product
Description
- Identifies components, parts, materials, and
subassemblies in the product - Shows production sequence for the product
- More of a recipe for making the product
- Modular BOM
- Buildable items that are storable as
subassemblies - Planning BOM
- Fractional options. Fraction of the part
contained in the completed unit
13Bill of Materials Structure
A
1. Christmas tree structure
B(1)
C(1)
D(1)
E(4)
F(2)
G(4)
H(4)
2. Indented structure Part Description Quantity
Source A Car 1 Assembled B
Engine 1 Manufactured D
Block 1 Manufactured E
Valves 4 Purchased C
Body 1 Manufactured F
Doors 2 Manufactured G
Tires 4 Purchased H
Shocks 4 Purchased
14Inventory Records File
- Each inventory item carried as a separate file
- See, for example, Exhibit 16.15
- Status according to time buckets for all items
- On-hand quantities
- Scheduled receipt of order
- Lead times for all orders
- Lot size requirements
- Pegging
- Identify each parent item that created demand
15Primary MRP Reports
- Planned orders to be released at a future time.
- Order release notices to execute the planned
orders. - Changes in due dates of open orders due to
rescheduling. - Cancellations or suspensions of open orders due
to cancellation or suspension of orders on the
master production schedule. - Inventory status data.
16Secondary MRP Reports
- Planning reports, for example, forecasting
inventory requirements over a period of time. - Performance reports used to determine agreement
between actual and programmed usage and costs. - Exception reports used to point out serious
discrepancies, such as late or overdue orders.
17Updating The MRP System
- Regenerative method
- Limited replanning frequency, weekly or longer
- MPS submission triggers replanning
- Every end-item in the MPS is exploded
- Voluminous output is generated
- High data processing efficiency--batch
- Net change method
- High frequency of replanning
- But affected parts of MPS are exploded
- Limited number of outputs result
18Net Change System
- Activity driven
- Net change schedules
- Potential for system nervousness
19The Material Requirements Planning System
- Based on a master production schedule, a material
requirements planning system - Creates schedules identifying the specific parts
and materials required to produce end items. - Determines exact unit numbers needed.
- Determines the dates when orders for those
materials should be released, based on lead
times.
20Example of MRP Logic and Product Structure Tree
(BOM)
Given the product structure tree for A and the
lead time and demand information below, provide a
materials requirements plan that defines the
number of units of each component and when they
will be needed.
Lead Times A 1 day B 2 days C 1 day D 3
days E 4 days F 1 day
Product Structure Tree (BOM) for Assembly A
Demand Day 10 50 A Day 8 20 B (Spares) Day 6
15 D (Spares)
21First, the number of units of A are scheduled
backwards to allow for their lead time. So, in
the materials requirement plan below, we have to
place an order for 50 units of A in the 9th
week to receive them in the 10th week.
LT 1 day
22Next, we need to start scheduling the components
that make up A. In the case of component B
we need 4 Bs for each A. Since we need 50 As,
that means 200 Bs. And again, we back the
schedule up for the necessary 2 days of lead time.
23Finally, repeating the process for all
components, we have the final materials
requirements plan
23
- The McGraw-Hill Companies, Inc., 2001
24MRP Scheduling Terminology
- Gross Requirements
- Gross demand as taken from the MPS
- On-hand
- Available physical inventory
- Net requirements
- Net demand after inventories are consumed
- Planned order receipt
- Time outstanding orders are expected
- Planned order release
- When to place orders so they come in when needed
25An MRP Example 1
Level
0
A
(1)
- Straight one-to-one correspondence
- No multiple parents
- One component one parent
- Consider the three level part explosion diagram
above. The items do not have multiple parents and
only 1 unit of each item goes into the
corresponding parent. Suppose that the gross
requirements for product A for periods 3, 4, 5,
6, 8, and 10 are 25, 5, 35, 7, 10, and 21,
respectively. Suppose also that it takes 2
periods from the period an order was placed to
the time it was actually received in inventory,
and that the amount of item A on hand was 20 30
for item B, and 2 for item C. Develop the
complete MRP explosion requirements needed to
determine the net requirements for item C. The
scheduled receipt for product A, the end item, is
25 in period 4.
1
B
(1)
2
C
(1)
26(No Transcript)
27MRP Example 2
Requirements include 95 units (80 firm orders and
15 forecast) of X in week 10 plus the following
spares
28 29(No Transcript)
30Closed Loop MRP
Production Planning Master Production
Scheduling Material Requirements
Planning Capacity Requirements Planning
31Manufacturing Resource Planning (MRP II)
- Goal Plan and monitor all resources of a
manufacturing firm (closed loop) - manufacturing
- marketing
- finance
- engineering
- Simulate the manufacturing system
32Lot Sizing in MRP Programs
- Economic order quantity (EOQ)
- Lot-for-lot (L4L)
- Period order quantity (POQ)
- Part period balancing (PPB)
- Least total cost (LTC)
- Least unit cost (LUC)
- Silver-Meal heuristics (SM)
- Wagner-Wittin (WW)
33Lot-Sizing Example EOQ Method
- The net requirements for a product is as given in
the table. If C10/unit, S47/order, H.5 of
cost, find the total cost to meet order demand
requirements using the EOQ method. - Weekly Net Requirements
- 1 2 3 4 5 6 7 8
- 50 60 70 60 95 75 60 55
- Solution
TC10(525)(.05)(1563)2(47)5,422.15
34Lot-Sizing Example LFL Method
- The net requirements for a product is as given in
the table. If C10/unit, S47/order, H.5 of
cost, find the total cost to meet order demand
requirements using the LFL method. - Weekly Net Requirements
- 1 2 3 4 5 6 7 8
- 50 60 70 60 95 75 60 55
- Solution
TC10(525)(.05)(0)8(47)5,626
35Lot-Sizing Example POQ Method
- The net requirements for a product is as given in
the table. If C10/unit, S47/order, H.5 of
cost, find the total cost to meet order demand
requirements using the POQ method. - Weekly Net Requirements
- 1 2 3 4 5 6 7 8
- 50 60 70 60 95 75 60 55
- Solution
TC10(525)(.05)(1190)2(47)5,404