FIRE Design: FY03 PFC Tasks - PowerPoint PPT Presentation

About This Presentation
Title:

FIRE Design: FY03 PFC Tasks

Description:

Rebuild OPERA model of vessel and PFCs including copper (input from design at Boeing) ... Use Opera to determine the effect of the copper shell on magnetic ... – PowerPoint PPT presentation

Number of Views:74
Avg rating:3.0/5.0
Slides: 14
Provided by: fire8
Learn more at: https://fire.pppl.gov
Category:
Tags: fire | pfc | design | fy03 | opera | tasks

less

Transcript and Presenter's Notes

Title: FIRE Design: FY03 PFC Tasks


1
FIRE Design FY03 PFC Tasks
NSO PAC Meeting San Diego, February 27-28, 2003
  • Mike Ulrickson (FIRE Divertor Design Team)
  • presented by
  • Richard Nygren (new member, NSO PAC)
  • Sandia National Laboratories

Sandia is a multiprogram laboratory operated by
Sandia Corporation, a Lockheed Martin
Company,for the United States Department of
Energy under contract DE-AC04-94AL85000.
2
Introduction
  • Best guess for readiness for PVR is late
    August or early September 2003.
  • Continuing resolution in FY03 has constrained the
    initial schedule.
  • In the following slides
  • green text indicates completed tasks,
  • blue text indicates tasks in progress,
  • black text indicates planned tasks that can be
    done with the FY03 budget.

3
Plasma Equilibrium
green (completed)
  • Define baseline plasma shape for 2.14 m.
  • Use TSC to compute vertical and radial disruption
    cases.
  • Define the range of ?, li, ?, and Paux that
    should be accommodated and provide magnetic data.

black text (can be done with FY03 )
4
Edge modeling
  • Use UEDGE to reestablish edge plasma conditions
    with the proper fusion power and heating
  • Determine heat flux profiles
  • Determine boundaries for partial detachment

blue (in progress) black text (can be done with
FY03 )
Note for high density plasma in ARIES-RS/CLIFF
for APEX, Rognlien found steady state solution
for strongly radiating regions near X-point.
5
Disruption Forces
  • Rebuild OPERA model of vessel and PFCs including
    copper (input from design at Boeing)
  • Use TSC data as input to Opera to find eddy
    currents and forces
  • Use Opera to determine the effect of the copper
    shell on magnetic diagnostics
  • Run a vertical disruption case to compare to
    vertical disruption on 2.0 m machine and use
    results to scale radial disruption forces to 2.14
    m

6
Design
  • Revise baseline divertor design (input to Opera)
  • Revise the divertor hardware to accommodate the
    new plasmas and check shape variations
  • Compute stresses in the revised design for both
    thermal and disruption loads (input from Opera)
  • Revise design as needed to accommodate stresses

green (completed) black text (can be done with
FY03 )
7
Heat flux testing
  • Investigate new concept for W rod attachment to
    improve reliability
  • (PFC base program but input from FIRE design)
  • New design completed
  • Negotiating with vendor for production

green (completed) black text (can be done with
FY03 )
8
W-rod Armor
  • Mockups have survived high heat flux tests to
    24MW/m2 and thermal cycling for 500 cycles.
  • We recommend two design improvements.
  • - Creep resistant Cu alloy as the rod bed.
  • - Positive mechanical lock of rod to bed
    (grooved rod tip). Vendor bids have been
    received.

PW-8 rods reached 3300oC at 24MW/m2. Some
erosion of rods occurred but no cracking or
melting. PW-8 was then subjected to thermal
fatigue cycles After 370 cycles (10s-ON10s-OFF)
at 20MW/m2, one rod began to melt. The affected
area grew to 9 rods we terminated testing at 500
cycles.
9
ELMs on FIRE
ELMS are not a problem if no surface melting
occurs. We must reduce the magnitude of ELMS.
  • Assumptions for ELM energy deposited on FIRE
    divertor plates.
  • Either (a) 2 or (b) 5 of stored energy is lost.
  • Footprint for deposition is either (a) same as
    normal operation or (b) up to three times larger
  • Duration of ELM is 0.1
  • Most of the 2 cases and a few 5 cases are
    acceptable.
  • Limit for 0.1ms ELM is 0.3 MJ/m2 (partially
    detached, 12 MW/m2)
  • Limit for 1.0ms ELM is 1.0 MJ/m2 (partially
    detached, 12 MW/m2)

10
ELMs Melting LIMIT
Melting will not occur when the deposited energy
density is less than the value at the
intersection of (a) T-rise curve and (b)
TLIMIT,normalHF.
T-rise (1ms ELM) 5 (loss Estored) 6MW/m2
qnormal
Energy Density 1.25MJ/m2 to avoid melting.
11
PFC Task Progress
12
Reporting
  • Provide data needed for Physics Validation Review
  • Revise divertor section of engineering report to
    include new design

13
Summary
  • A redesign of the PFC components can be completed
    in time for the PVR, but the effort must start
    immediately.
  • Funding is not adequate for iterating the
    divertor design.
  • We can only scale the design to the new size and
    analyze the forces
  • Local areas of excessive stress are likely to
    exist on the supports or vacuum vessel
Write a Comment
User Comments (0)
About PowerShow.com