Title: FIRE Design: FY03 PFC Tasks
1FIRE Design FY03 PFC Tasks
NSO PAC Meeting San Diego, February 27-28, 2003
- Mike Ulrickson (FIRE Divertor Design Team)
- presented by
- Richard Nygren (new member, NSO PAC)
- Sandia National Laboratories
Sandia is a multiprogram laboratory operated by
Sandia Corporation, a Lockheed Martin
Company,for the United States Department of
Energy under contract DE-AC04-94AL85000.
2Introduction
- Best guess for readiness for PVR is late
August or early September 2003. - Continuing resolution in FY03 has constrained the
initial schedule. - In the following slides
- green text indicates completed tasks,
- blue text indicates tasks in progress,
- black text indicates planned tasks that can be
done with the FY03 budget.
3Plasma Equilibrium
green (completed)
- Define baseline plasma shape for 2.14 m.
- Use TSC to compute vertical and radial disruption
cases. - Define the range of ?, li, ?, and Paux that
should be accommodated and provide magnetic data.
black text (can be done with FY03 )
4Edge modeling
- Use UEDGE to reestablish edge plasma conditions
with the proper fusion power and heating - Determine heat flux profiles
- Determine boundaries for partial detachment
blue (in progress) black text (can be done with
FY03 )
Note for high density plasma in ARIES-RS/CLIFF
for APEX, Rognlien found steady state solution
for strongly radiating regions near X-point.
5Disruption Forces
- Rebuild OPERA model of vessel and PFCs including
copper (input from design at Boeing) - Use TSC data as input to Opera to find eddy
currents and forces - Use Opera to determine the effect of the copper
shell on magnetic diagnostics - Run a vertical disruption case to compare to
vertical disruption on 2.0 m machine and use
results to scale radial disruption forces to 2.14
m
6Design
- Revise baseline divertor design (input to Opera)
- Revise the divertor hardware to accommodate the
new plasmas and check shape variations - Compute stresses in the revised design for both
thermal and disruption loads (input from Opera) - Revise design as needed to accommodate stresses
green (completed) black text (can be done with
FY03 )
7Heat flux testing
- Investigate new concept for W rod attachment to
improve reliability - (PFC base program but input from FIRE design)
- New design completed
- Negotiating with vendor for production
green (completed) black text (can be done with
FY03 )
8W-rod Armor
- Mockups have survived high heat flux tests to
24MW/m2 and thermal cycling for 500 cycles. - We recommend two design improvements.
- - Creep resistant Cu alloy as the rod bed.
- - Positive mechanical lock of rod to bed
(grooved rod tip). Vendor bids have been
received.
PW-8 rods reached 3300oC at 24MW/m2. Some
erosion of rods occurred but no cracking or
melting. PW-8 was then subjected to thermal
fatigue cycles After 370 cycles (10s-ON10s-OFF)
at 20MW/m2, one rod began to melt. The affected
area grew to 9 rods we terminated testing at 500
cycles.
9ELMs on FIRE
ELMS are not a problem if no surface melting
occurs. We must reduce the magnitude of ELMS.
- Assumptions for ELM energy deposited on FIRE
divertor plates. - Either (a) 2 or (b) 5 of stored energy is lost.
- Footprint for deposition is either (a) same as
normal operation or (b) up to three times larger - Duration of ELM is 0.1
- Most of the 2 cases and a few 5 cases are
acceptable. - Limit for 0.1ms ELM is 0.3 MJ/m2 (partially
detached, 12 MW/m2) - Limit for 1.0ms ELM is 1.0 MJ/m2 (partially
detached, 12 MW/m2)
10ELMs Melting LIMIT
Melting will not occur when the deposited energy
density is less than the value at the
intersection of (a) T-rise curve and (b)
TLIMIT,normalHF.
T-rise (1ms ELM) 5 (loss Estored) 6MW/m2
qnormal
Energy Density 1.25MJ/m2 to avoid melting.
11PFC Task Progress
12Reporting
- Provide data needed for Physics Validation Review
- Revise divertor section of engineering report to
include new design
13Summary
- A redesign of the PFC components can be completed
in time for the PVR, but the effort must start
immediately. - Funding is not adequate for iterating the
divertor design. - We can only scale the design to the new size and
analyze the forces - Local areas of excessive stress are likely to
exist on the supports or vacuum vessel