GBSQSS recommendations for offshore transmission networks - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

GBSQSS recommendations for offshore transmission networks

Description:

Contents. Background. Methodology. Scope of offshore transmission. Cost benefit analysis ... HV assets. LV assets. 100MW wind farm. Single offshore platform ... – PowerPoint PPT presentation

Number of Views:62
Avg rating:3.0/5.0
Slides: 21
Provided by: jonathan210
Category:

less

Transcript and Presenter's Notes

Title: GBSQSS recommendations for offshore transmission networks


1
GBSQSS recommendations foroffshore transmission
networks
  • GBSQSS Sub Group
  • OTEG 29 September 2006

2
Contents
  • Background
  • Methodology
  • Scope of offshore transmission
  • Cost benefit analysis
  • Offshore transmission voltage requirements
  • Recommendations
  • Further work

3
Background
  • Ofgem scoping document published in April 2006
  • OTEG established
  • GBSQSS sub-group of OTEG set up to review
    existing GBSQSS and test relevance to offshore
    transmission networks
  • This presentation sets our GBSQSS sub-group
    assessment of the GBSQSS and its recommendations
  • 15 meetings considering output of 20000 studies

4
Methodology
  • Consider GBSQSS and identify areas that require
    review
  • Cost benefit analysis - in line with existing
    GBSQSS and ER P2/6
  • Formulation of working assumptions
  • Consideration of assets likely to have an impact
    on outcome of cost benefit analysis
  • Creation of network models for assessment
  • Population of network models with real data
  • Carry out analysis and present back to sub-group
    at each meeting
  • Test key input variables for the value at which
    the conclusion changes

5
Scope of offshore transmission
Shore
Generator
Onshore system (Transmission or Distribution)
Offshore Transmission system
Offshore Grid Entry Point (offshore platform)
Onshore Grid Entry Point or User System Entry
Point
Generator
Offshore TO
Onshore TO /DNO
6
Scope of offshore transmission
Central high voltage offshore platform
Low voltage assets
High voltage assets
Offshore transmission network
Wind farm
Offshore platform transformer circuits
Preferred option
7
Offshore transmission voltage requirements
  • Assessment of existing arrangements
  • At onshore connection point of offshore
    transmission network to onshore electricity
    network
  • At offshore connection point of generator to
    offshore transmission network
  • Outline possible options
  • Consideration of voltage limits at connection of
    offshore network to onshore network
  • Consideration of voltage limits at offshore
    platform
  • Comparison of options and provide recommendations

8
Offshore transmission voltage requirements
Onshore substation
Offshore substation
Shore
Offshore wind farm
A
B
Onshore Grid or User System
Generator has to meet Grid Code requirements.
Existing onshore GB SQSS voltage requirements
apply.
  • Recommended that Grid Code, CC.6.3.2(b)
    CC.6.3.2(c) and CC.6.3.8(c) apply at
    onshore/offshore interface
  • Reactive power capability
  • Voltage control

New voltage limits set for offshore platform
Offshore SQSS recommendations
9
Cost benefit analysis
  • Network models
  • Single / shared AC connections
  • Single / shared DC connections
  • Wind farms considered
  • Up to 1500MW
  • Up to 100km from shoreline
  • Sensitivity assessment of input parameters to
    test robustness of recommendation

10
Recommendation Offshore platform
  • For a single wind farm connection
  • Platform capacity should be planned to accept the
    full output of the wind farm with no equipment
    loadings exceeding their pre-fault rating.
  • For AC connections for wind farms with an export
    capacity of 120MW or greater, following the
    outage (planned or unplanned) of a single
    offshore transmission transformer circuit there
    should be, at a minimum, 50 of installed
    platform transformer capacity remaining.
  • For HVDC connections for outages (planned or
    unplanned) of a single offshore platform DC
    converter module, the loss of power infeed shall
    not exceed existing onshore Normal Infeed Loss
    Risk of 1000MW (limited at present by available
    technology, hence reliability and cost data for
    larger modules not available for further
    assessment).

11
Recommendation Offshore platform
  • For a multiple wind farm connections
  • Transformer capacity should be planned to accept
    90 of the cumulative installed capacity of the
    wind farms connected, with no equipment loadings
    exceeding their pre-fault rating.
  • For AC connections for wind farms with an export
    capacity of 120MW or greater, following the
    outage (planned or unplanned) of a single
    offshore transmission transformer circuit there
    should be, at a minimum, 50 of installed
    platform transformer capacity remaining.
  • For HVDC connections for outages (planned or
    unplanned) of a single offshore platform DC
    converter module, the loss of power infeed shall
    not exceed existing onshore Normal Infeed Loss
    Risk of 1000MW (limited at present by available
    technology, hence reliability and cost data for
    larger modules not available for further
    assessment).

12
Recommendation AC platform
Single wind farm connection
100MW wind farm
LV assets
For wind farms with an export capacity of 120MW
or greater, following the outage (planned or
unplanned) of a single offshore transmission
transformer circuit, there should be, at a
minimum, 50 of installed transformer capacity
remaining.
Platform should be designed such that the High
Voltage and Low Voltage terminals of the platform
transformer circuits are interconnected to allow
for full flexibility of use of all assets housed
upon it.
1 x 100MW rated unit
HV assets
Offshore transmission cable network
Single offshore platform
Substation configurations for illustration only
13
Recommendation AC platform
Single wind farm connection
500MW wind farm
For wind farms with an export capacity of 120MW
or greater, following the outage (planned or
unplanned) of a single offshore transmission
transformer circuit there should be, at a
minimum, 50 of installed transformer capacity
remaining.
LV assets
Platform should be designed such that the High
Voltage and Low Voltage terminals of the platform
transformer circuits are interconnected to allow
for full flexibility of use of all assets housed
upon it.
2 x 250MW rated units
HV assets
Offshore transmission cable network
Single offshore platform
Substation configurations for illustration only
14
Recommendation AC platform
Multiple wind farm connection
Transmission transformer capacity should be
planned to accept 90 of the cumulative installed
capacity of the wind farms connected, with no
equipment loadings exceeding their pre-fault
rating. For wind farms with a cumulative
installed capacity of 120MW or greater, following
the outage (planned or unplanned) of a single
offshore transmission transformer circuit there
should be, at a minimum, 50 of installed
transformer capacity remaining. Note value of
90 could be reduced at marginal point of
investment.
50MW
50MW
Offshore transmission circuit
1 x 90MW rated units
Offshore transmission circuit
Shoreline
Onshore grid entry point
Substation configurations for illustration only
15
Recommendation AC platform
Multiple wind farm connection
Transmission transformer capacity should be
planned to accept 90 of the cumulative installed
capacity of the wind farms connected, with no
equipment loadings exceeding their pre-fault
rating. For wind farms with a cumulative
installed capacity of above 120MW, following the
outage (planned or unplanned) of a single
offshore transmission transformer circuit there
should be, at a minimum, 50 of installed
transformer capacity remaining. Note 90 value
could be reduced at marginal point of investment.
500MW
500MW
Offshore transmission circuit
2 x 450MW rated units
Offshore transmission circuit
Shoreline
Substation configurations for illustration only
Onshore grid entry point
16
Recommendation Network capacity
  • For a single wind farm connection
  • Transmission cable circuit capacity should be
    planned to accept the full output of the wind
    farm with no equipment loadings exceeding the
    pre-fault rating.
  • For multiple wind farm connections
  • Transmission cable circuit capacity should be
    planned to accept 90 of the cumulative
    installed capacity of the wind farms connected to
    it, with no equipment loadings exceeding their
    pre-fault rating
  • Where cost of additional assets is marginal then
    values less then 90 can be justified
  • Following the outage of a single offshore
    transmission cable circuit, the reduction in
    cable circuit capacity should not exceed 1500MW
    i.e. can allow up to 1500MW to be connected to a
    single transmission cable circuit.
  • 1500MW reflects the limit in scope of the
    analysis. A value greater than this could be
    feasible following further economic assessment.

17
Recommendation Network capacity
Single wind farm connection
Offshore platform
500MW
Following the outage of a single offshore
transmission circuit, the reduction in circuit
capacity should not exceed 1500MW i.e. can allow
up to 1500MW to be connected to a single
transmission circuit. Note 1500MW reflects the
limit in scope of the analysis. A value greater
than this could be feasible following further
economic assessment.
The transmission circuit capacity should be
planned to accept the full output of the wind
farm with no equipment loadings exceeding the
pre-fault rating
Single 500MW circuit
Onshore grid
18
Recommendation Network capacity
Multiple wind farm connection
500MW
500MW
Following the outage of a single offshore
transmission circuit, the reduction in circuit
capacity should not exceed 1500MW i.e. can allow
up to 1500MW to be connected to a single
transmission circuit. Note 1500MW reflects the
limit in scope of the analysis. A value greater
than this could be feasible following further
economic assessment.
Local offshore platform
The circuit capacity should be planned to accept
90 output of the wind farms connected to it,
with no equipment loadings exceeding their
pre-fault rating. Note 90 value could be
reduced at marginal point of investment.
Master offshore platform
Single 900MW rated circuit
Shoreline
Onshore grid entry point
19
Summary
  • Onshore GBSQSS not applicable offshore
  • AC and DC could be different
  • Recommendations cover
  • Offshore platform
  • Offshore network capacity
  • Voltage requirements
  • GBSQSS sets minimum standard generators can opt
    for more as onshore

20
Issues for OTEG consideration
  • DNO sandwich
  • Grid Code review
  • Access rights, compensation arrangements and
    transmission charging require review
  • Assessment of demand connected to offshore
    transmission networks
  • The consideration of generating plant with a
    higher annual capacity factor (e.g. offshore
    CCGT, tidal etc) should be considered
  • Voltage requirements offshore
Write a Comment
User Comments (0)
About PowerShow.com