Title: Enabling Activities: Technology Needs Assessments
1Enabling ActivitiesTechnology Needs Assessments
- GEF Familiarization Seminar
- April 28-30, 2009
2COP Decision on TNAs
- By decision 2/CP.4 (November 1998), the COP
decided that the GEF should provide funding to
developing country Parties to, enable themto
identify and submit to the COP their prioritized
technology needs especially as concerns key
technology needed in particular sectors of their
national economies conducive to addressing CC and
minimizing its adverse effect.
- According to the framework, the purpose of TNAs
is to assist in identifying and analyzing
priority technology needs, which can form the
basis for a portfolio of EST projects and
programs which can facilitate the transfer of,
and access to, the ESTs and know-how in the
implementation of Article 4, paragraph 5, of the
Convention.
3GEF Funding for TNAs
- GEF provided funding for more than 90 non-Annex I
Parties to conduct TNAs through its interim
financing for capacity building in priority areas
- enabling activities phase II (also known as
top-ups). - UNDP assisted 78 countries between 2000 and 2003
- Reports available for 66 countries
- UNEP assisted 14 countries
- Reports available for 12 countries
4Countries with TNA Reports Available
5Stakeholder Involvement in the TNA Process
Source Synthesis report on technology needs
identified by Parties not included in Annex I to
the Convention, FCCC/SBSTA/2006/INF.1, 21 April
2006.
6Key Sectors Covered by TNA Reports
Source Synthesis report on technology needs
identified by Parties not included in Annex I to
the Convention, FCCC/SBSTA/2006/INF.1, 21 April
2006.
7Gaps in TNA Reports
- Selection of sectors were not always clearly
justified. - Not all TNA reports were elaborated on the basis
for the choice of technologies. - Methodology of assessment was not always
described but common steps in TNA reports. - Stakeholders roles and specific contributions
and future involvement were not explained. - Barriers and capacity building needs were not
identified by all countries. - Follow-up activities usually were not addressed.
8Constraints with Previous TNAs
- No reporting requirements
- Convention did not require Parties to report on
the findings of their TNAs. - Complexity of TNA work
- Identification of technology needs was innovative
and a complex task. - Capacity constraints
- Many countries had limited technical capacity to
carry out their TNA work. - Availability of technical guidance
- TNA handbook was late for many countries and
reporting guidelines were lacking. - Capacity building focus of top-up projects
- Top-ups placed a strong emphasis on capacity
building implementation was process-oriented
which was not always conducive to substantive
outputs.
9From Bali to Poznan
- COP13 requested the GEF to elaborate a strategic
program on technology transfer. - A progress report was submitted by GEF to SBI 28
in June 2008. - Extensive consultation with Parities and other
stakeholders ensued. - GEF Council approved the revised strategic
program in November 2008. - COP14 endorsed the GEF strategic program and
renamed it the Poznan strategic program on tech
transfer.
10Poznan Strategic Program on Technology Transfer
- Consists of three funding windows
- Technology needs assessments (9m)
- Technology transfer pilot projects (40m)
- Dissemination of technologies and practices (1m)
- Timeframe for implementation
- Remainder of GEF-4 (FY2006-10)
11Pushing the TNA Process Further
- Developing barrier removal tools technical,
policy, financial, awareness, etc. - Developing Technology Action Plans (TAPs) in the
countries that identify short- and long-term
measures - Establishing links (internal and external with
relevant agencies) for implementing TAPs - Developing technology transfer projects in
participating countries
12Progress of Implementation
- Dec 2008 COP 14, Poznan Strategic Program on TT
- Jan 2009 Stakeholder consultation meeting to
formulate a strategy and work plan for
implementation - Feb 2009 UNEP drafted a project concept for a
global TNA project for GEF funding (SCCF). - Informal consultation at EGTT meeting in Bonn
- March 2009 UNEP finalized the global TNA project
concept and submitted to the GEF Secretariat. - Project concept was cleared by the GEF CEO.
- April 2009 Approved by the LDCF/SCCF Council
13The New TNA Project
- The goal is to assist countries to go beyond
identifying technology needs and develop National
Technology Action Plans for prioritized
mitigation and adaptation technologies that are
consistent with national development objectives. - Up to 45 developing countries will be supported
during GEF-4. - Revised TNA Handbook methodologies will be used.
- Project concept is available at the GEF website
http//www.thegef.org/uploadedfiles/PIF20Global2
03907.doc.
14Participation of Countries
- Selection of countries will take into
consideration elements including - Size of the country/economy
- Mitigation potential
- Adaptation needs
- National interest and enabling environment
- Expression of interest by countries
- Past efforts
- Institutional capacities
- Initial countries will be chosen with a goal of
regional diversity to field test the revised TNA
handbook. - More countries will join based on expression of
interest and other considerations.
15TNA Implementation at the Country Level
- Participating country prepare a national work
plan for conducting its TNA based upon a
simplified format, but will include - timelines, benchmarks, indicators to show how
each output at the national level supports the
overall TNA process. - Countries will receive grant financing for
in-country activities. - Qualified regional centers will be used to
provide much of the technical guidance and
support. - Mechanisms that promote exchange of experience
and information between countries will be
established.
16Toward Copenhagen and GEF-5
- Progress and results of implementing this new
around of TNAs will be presented in Copenhagen in
December 2009. - During GEF-5 (FY2010-13), the GEF will continue
to support as a first priority enabling
activities.
17Contact Information
- Zhihong Zhang, Ph.D.
- Coordinator, Climate Change Mitigation
- Global Environment Facility
- Email zzhang2_at_thegef.org
- Tel. (202) 473-9852
- Website www.TheGEF.org