Title: Relevant Cash Flows and Other Topics in Capital Budgeting
1Relevant Cash Flows and Other Topics in Capital
Budgeting
- Timothy R. Mayes, Ph.D.
- FIN 3300 Chapter 10
2Project Cash Flows
- When deciding whether or not to make an
investment, we must first estimate the cash flows
that the investment will provide - Generally, these cash flows can be categorized as
follows - The initial outlay (IO)
- The annual after-tax cash flows (ATCF)
- The terminal cash flow (TCF)
3Relevant Cash Flows
- Determining the relevant cash flows can sometimes
be difficult, here are some guidelines - Cash flows must be
- Incremental (i.e., in addition to what you
already have) - After-tax
- Ignore those cash flows that are
- Sunk costs (monies already spent, and not
recoverable) - Additional financing costs (e.g., extra interest
expense)
4The Initial Outlay
- The initial outlay is the total up-front cost of
the investment - The initial outlay can consist of many
components, among these are - The cost of the investment
- Shipping and setup costs
- Training costs
- Any increase in net working capital
- When we are making a replacement decision, we
also need to subtract the after-tax salvage value
of the old machine (or land, building, etc.)
5The Annual After-tax Cash Flows
- The annual after-tax cash flows (ATCF) are the
incremental after-tax cash flows that the
investment will provide - Generally, these cash flows fall into four
categories - Incremental savings (positive cash flow) or
expenses (negative cash flow) - Incremental income (positive cash flow)
- The tax savings due to depreciation
- Lost cash flows (negative cash flow) from the
existing project. This is an opportunity cost.
6The Terminal Cash Flow
- The terminal cash flow consists of those cash
flows that are unique to the last year of the
life of the project - There may be a number of components of the TCF,
but three common categories are - Estimated salvage value
- Shut-down costs
- Recovery of the increase in net working capital
7Problems in Capital Budgeting
- Thus far we have been analyzing relatively simple
capital budgeting problems. The methodolgy that
we have used is fairly robust, but there are some
difficulties. In particular we will now look at
problems with - Unequal lives
- Inflation
- Differential risk
8The Unequal Lives Problem
- Any time that mutually exclusive projects are
being examined, it is vital that we make apples
to apples comparisons. A perfect example is two
projects with unequal lives. - Suppose, for example, that we are trying to
decide between projects A and B and that they are
mutually exclusive. They have the following cash
flows, and the cost of capital is 10
9The Unequal Lives Problem (cont.)
- If we calculate the NPVs of both projects, we
find - NPVA 413.22
- NPVB 568.27
- From these calculations it appears that project B
is the better project. However, we are making a
potentially serious mistake. - Obviously, because we are willing to invest in B
we have a 5-year investment horizon. So, we must
ask if we accepted project A, what would we do
with our money for the remaining 3 years? Only
then can a valid comparison be made.
10The Unequal Lives Problem (cont.)
- There are two ways to correctly deal with the
unequal lives problem - The replacement chain approach
- The equivalent annual annuity approach
11The Replacement Chain Approach
- The replacement chain approach assumes that a
project will be repeated as many times as
necessary to fit into the investment horizon. In
this example, we need to repeat project A just
once so that it has a 4-year life (the same a B).
After replication, the cash flows for A are
12The Rep. Chain Approach (Cont.)
- Note that the net cash flow in year 2 is now
-4,000 because we must pay for project A a
second time. - Now, recalculating the NPV for project A reveals
that the correct NPV for the entire 4-year
horizon is actually 754.73 which exceeds the NPV
of project B. - Therefore, when the problem is correctly
analyzed, we find that it is actually project A
which should be accepted, not B.
13The EAA Approach
- The equivalent annual annuity approach is
identical to the replacement chain approach in
its results, but it is much simpler to perform - First, we calculate the NPVs for both projects
assuming that they are NOT replicated. Then, we
convert these NPVs into equivalent annuity
payments that they could provide over the life of
the project.
14The EAA Approach (Cont.)
- Using the formula for the present value of an
ordinary annuity, we simply solve for the annuity
payment
- Solving for the payment for project A, we find
that its EAA is 238.09. - Using the same methodology for project B we find
that its EAA is 179.27. - Since the EAA for A is higher than the EAA for B,
we should accept project A.
15Dealing with Inflation
- Inflation must be accounted for in capital
budgeting if we are to make correct decisions. - Generally, we should inflate the cash flow
estimates by the expected rate of inflation since
the discount rate that we are using already
incorporates expected inflation. If we do not do
this, then the estimated NPV will be lower than
the correct NPV. This could cause us to reject a
project that (because it appears to have a
negative NPV) when, in fact, we should accept it.
16Incorporating Risk Estimates
- Recall from our discussions in Chapters 1 and 5
that we assume that investors are risk averse.
This means that they will require higher rates of
return on higher risk investments. - This means that the WACC is not the appropriate
discount rate for projects that are riskier or
less risky than the average for the firm.
Instead, we need to increase the discount rate
for riskier projects and decrease it for less
risky projects. This is known as the
risk-adjusted discount rate (RADR).
17Incorporating Risk Estimates
- There are, of course, several other techniques
for incorporating risk into our decision making.
However, they are beyond the scope of this
course. - Just for completeness, here are a few
- Certainty equivalents
- Scenario analysis
- Sensitivity analysis
- Monte-Carlo Simulation