Title: SLURRY SEAL PROJECTS
1SLURRY SEAL PROJECTS
- By Richard Sampson
-
- Dustin Lang
2WHAT IS A SLURRY SEAL?
- A Slurry Seal is a cold mixed asphalt. It
consists of a graded aggregate, a binder, fines
and additives. It is a hard wearing surfacing for
pavement preservation.
3WHAT IS A SLURRY SEAL MADE CONSIST OF
- Mixture of
- Asphalt Emulsion (Approx. 14 by total aggregate)
- Water (Approx. 12 by total aggregate)
- Aggregate (Type I, II or III)
- Cement
- Additives
4MAXIMUM ALLOWABLE THICKNESS OF SLURRY IS 1 ½
TIMES MAXIMUM ROCK SIZE
5SLURRY SEAL LIFE EXPECTANCY
7 YEARS LIFE SPAN AND LONGER WHEN USED FOR A
TRUE PREVENTIVE MAINTENANCE PROCEDURE
6SLURRY SEAL IS USED FOR
- Seal sound, oxidized pavements
- Restore surface texture by providing a
skid-resistant wearing surface - Improve waterproofing characteristics
- Correct raveling
- Provide a new surface where weight restrictions
preclude the use of heavier overlays - Alternative to a seal coat
7SLURRY SEAL SHOULD NOT BE USED TO
- Correct surface profile
- Fill potholes
- Alleviate cracking except for short-term weather
protection - Used on primarily new pavement
8PROPERTIES - SLURRY SEAL
- Surface treatment of equal thickness
- Thickness is equal to the largest stone of the
component aggregate - May be conventional or polymer modified aggregate
- Can be slow or quick setting
- Usually Cationic in nature
9PROPERTIES-SLURRY SEAL
- 6. Slow set breaks by evaporation
- Quick set breaks emulsions maintain a degree of
chemical break - Both systems are dependant on environmental
conditions - Quick set cures within an hour
- Slow set cures within a couple of hours
10(No Transcript)
11RATE OF APPLICATION
Above Data taken from International Slurry
Surfacing Assn. 2007 Workshop and Valley Slurry
Seal website.
12SLURRY SEAL VS. SEAL COAT
- Vehicle damage less likely
- Wider temperature placement range
- Fewer personnel required for inspection
- Less materials testing
- Traffic speeds can be raised much sooner
- Life of a slurry seal
- Requires less equipment
- Requires a consistent plain from outside edge to
inside edge - Project can be completed in a shorter duration
- Greater possibility for vehicle damage
- Faster initial seal operation
- Requires more equipment for placement
- Traffic speeds reduced for longer period
- Life of a seal coat
- Placement unaffected by sloughs
- Seal coats lose chip
- Less expensive than slurry seal
13DIFFERENCES BETWEEN SLURRY SEAL AND MICROSURFACE
- SLURRY SEAL
- Mixture of emulsified asphalt, fine
aggreagate,mineral filler, and water - Best preventive maintenance for surfaces
- Seals surface, stops pavement raveling,
smoothes and waterproofs - Provides non-skid surface
- Cannot stack material
- Non-structural
- MICROSURFACE
- Polymer asphalt emulsion, selected Fine Grade
Aggregate, mineral filler, water - Can be placed at a thickness of up to 1.5
(multiple layering is possible) - Used for rut filling
- Provides non-skid surface
- Structural overlay
142006 SLURRY SEAL VS. SEALCOATCOSTS
- GRAND FORKS SEALCOAT PROJ. PRICES
- Average price HFMS-2 . . . . . . . . . . .
1.03 Gal - Average Price CL 43 . . . . . . . . . . . .
.22.85 Ton - Price CRS-2P. . . . . . . . . . . . . . . . . .
. 1.40 Gal - Price CL 41 . . . . . . . . . . . . . . . . . . .
. 30.00 Ton - GRAND FORKS SLURRY SEAL PROJ. PRICES
- Asphalt Emulsion for Slurry Seal . 1.30
Gal - Agg. For Slurry Seal-Type II . . . . . . . 67.00
Ton
15SLURRY SEAL VS. SEAL COATCOST COMPARISON PER
MILE
- GRAND FORKS SEAL COAT PROJ. PRICES
- Average price HFMS-2 . . . . . . . . . . . . .
5,801 - Average Price CL 43 . . . . . . . . . . . . . . .
4,022 - 9,823
- Price CRS-2P . . . . . . . . . . . . . . . . . .
. . . 7,885 - Price CL 41 . . . . . . . . . . . . . . . . . . .
. 5,280 -
13,165 - GRAND FORKS SLURRY SEAL PROJ. PRICES
- Agg. For Slurry Seal-Type II . . . . . . . . .
9,827 - Asphalt Emulsion for Slurry Seal . . . . .
6,333 - 16,160
- Quantities computed using 24 widths and no
shoulders
16SLURRY SEAL COVERED UNDER SPECIAL
PROVISIONSP471(02)
17SPECIAL PROVISION
- Borrowed heavily from Nevada
- Issues addressed in SP Materials, Engineering,
Equipment, Weather Limitations, Traffic Control,
Surface Preparation, Application, Measurement
18SPECIAL PROVISION-AASHTO SPECIFICATION COVERAGE
- Additives
- 1. ISSA TB-139
- Emulsified Asphalt
- 1. AASHTO T59
- 2. AASHTO T49
- Aggregates
- 1. AASHTO T11 T27
- 2. AASHTO T2
- Deleterious Substances
- 1. AASHTO 176
- Soundness
- 1. AASHTO T104
- Hardness
- 1. AASHTO T96
- Moisture on weight of aggregate
- 1. AASHTO T19
19REQUIRED TESTS AND MIX DESIGN SPECIFICATIONS AS
PER SP 471(02)
The mixing test and set-time should be performed
at the highest temperatures expected during
construction.
20COMPONENT MATERIALS-SP 471(02)
21EMULSIONS
- CSS-1h
- CQS-1h ? emulsion used
- QS-1h
- SS-1h
- EMULSION SPECIFICATIONS ARE FORMULATED FOR
CAPITIBILITY WITH THE AGGREGATE AND MEET MIX
DESIGN PARAMETERS
22SPECIAL PROVISION-AGGREGATES
- Aggregate will be accepted at the job location or
stockpile based on the passing average of 5
gradation tests - Deleterious substances
- Soundness
- Hardness
23AGGREGATES CHARACTORISTICS
- Geology-Compatibility, adhesion, and cohesiveness
are affected - Shape-Slurry aggregates must have fractured faces
in order to form the required interlocking matrix
(rounded aggregates result in poor mix strength) - TextureRough surfaces bonds better with
emulsions
24AGGREGATES CHARACTORISTICS-CONTINUED
- Age Reactivity-Aggregates the are crushed
recently have a higher surface charge than
weathered aggregates - Clean Materials-Clay, dust, and silt can cause
poor cohesion
25REASONS FOR FAILURE
- General wear
- Surface oxidation
- Abrasion under traffic
- Surface deflection
- Cracked surfaces
- Base or subgrade failure
- Delamination
26TEST SAMPLE DEPICTIING TOO MUCH MINERAL ADDITIVE
Segregation of aggregates Excessive moisture
around edges of sample Sample will be very slow
setting and may have to be removed from roadway
- Segregation of aggregates
27EXAMPLE OF AN ACCEPTABLE SLURRY SAMPLE
- Uniform aggregate throughout sample
- Minimal water puddling outside of sample
28RESULT OF TOO MUCH MINERAL ADDITIVE
29SLURRY CONTAINING EXCESSIVE WATER
30SLURRY WITH NOT ENOUGH MINERAL ADDITIVE
Note slurry is so stiff it holds in a
pile
31USING A CANVAS DRAG BEHIND REAR POLY SCREED
32PROJECTSSNH-6-081(063)163 U.S. 81 FROM MANVEL
TO LEVANTSNH-6-081(062)175U.S. 81 FROM ARDOCH
TO MINTO
33PROJECTS SCOPE OF WORK
- Slurry Seal both lanes
- using Type II aggregate for slurry and CQS-1H
oil - Slurry Seal U.S. 81 Manvel Intersection
- Prior to Slurry Seal, tack lanes using CSS1H
- Seal shoulders with CSS1H
- Seal and apply Class 44 Blotter to approaches
- Pre-install Plastic pavement marking Message for
2 R/R crossings Stop bar at Manvel Intersection - Epoxy Permanent Pavement Marking
34MIX DESIGN
- BEFORE WORK BEGINS
- A contractor submitted mix design covering
the specific material to be used on the project - A qualified laboratory shall present certified
test results for the contractors approval. - No substitution of materials will be permitted
unless first tested and approved by the
laboratory preparing the mix design.
35N.D.D.O.T. SLURRY SEAL SPECIAL PROVISION
471(02)GRADATION REQUIREMENTS
Aggregate is accepted at job location or
stockpile. The stockpile shall be accepted based
on 5 gradation tests according to AASHTO-T2 After
the mix design gradation is submitted, each sieve
shall not very by more than the stockpile
tolerance and still remain within the gradation
band.
36ACTUAL TARGET TEST RESULTS
Targets taken from lab results
37ROADWAY PREPARATION
38ROADWAY PREPARATION REPAIR CRACKS BEFORE
SEALING
- All cracks should be sealed and sealant allowed
to cure - Most cracks will reappear
39POOR CRACK REPAIR
- Cracks and subgrade problems should be properly
repaired and ample time to cure prior to
placement of slurry seal
40ROADWAY PREPARATION
Cracks 1/4 or greater should be filled with
crack sealing material and be allowed to cure
prior to slurry placement Crack sealant that has
not cured or that has been tacked may stick to
tires on the slurry paver
41ROADWAY PREPARATION
Slurry Seals are not designed to fix this
42ROADWAY PREPARATION-MUST BE MADE WITH TIME FOR
CURE BEFORE SEALING
Rutting must be repaired prior to slurry
seal. Pavement leaching oil will cause the slurry
seal to lift.
43ROADWAY PREPARATION
- Remove all organic materials from roadway
- Grind any existing plastic pavement marking to be
slurry sealed over - Repair roadway asphalt problems due to subgrade
- Seal all cracks and allow for cure time
- Asphalt patches with excessive oil can bleed
threw slurry - High pressure wash or grind oil spots
- Ensure construction equipment does not have oil
or hydraulic leaks - Broom ahead of slurry sealing
- Mark and cover all manholes, gate valve covers,
curb inlets as needed - Mark stop bars and messages to be reinstalled
44CALIBRATION
- Calibration of the aggregate using
- loader scale
- Receive a copy of
- the CALIBRATION
- SUMMARY
- If same materials are being used for multiple
jobs, new calibration is not necessary - ISSA requires minimum of recalibration every 6
months - Special provision allows engineer to request
calibration at anytime
45Cement and aggregate meter
46CONTROL LINE
- Must fit the roadway especially when roads have a
secondary or barely meet plan width
47SKID RUNNING ON CENTER EDGE
48ROADWAY PREPARATION
- Special Provision-Tack Coat, if required shall be
applied with 3 parts water with a distributor at
a rate of 0.10 0.15 gallons per square yard.
This equals to .025 - .0375 gallons of tack only
per yard. - U.S. 81 worked best with minimum coverage
49WEATHER CONCERNS
- Medium to heavy rain can wash slurry seal oil
from roadway - Can cause aggregate separation
- May require total removal of damaged slurry seal
- Takes a minimum of an hour (plus) to be cured
adequately
50TACK COAT
51PREFORMED PATTERNED PAVEMENT MARKING-MESSAGE
- Not recommended
- Spreader bar skids will cut into message if run
over - Stickiness of the tack coat can lift the
temporary paper liner covering message, allowing
slurry to cover and stain message
52OPERATIONS
53OPERATIONS
54SELF CONTAINED SLURRY SEAL/MICROSURFACING MACHINE
55SELF CONTAINED SLURRY SEAL/MICROSURFACING MACHINE
56SLURRY DRAGGING SHOULD NOT BE LONGER THAN 6
Hand work Dirty Screed
57EXCESSIVE SLURRY DRAGGING
58CONTROL LINE
Missed matching slurry at centerline due to bad
control line Good centerline control will
prevent such problems to include consistent
slurry seal lane widths and a cosmetically
pleasing job.
59PERIODIC MAINTENANCE/CLEANING IS NECESSARY
THROUGHOUT DAY
60 Slurry sealing requires constant adjustments.
61SLURRY SEAL PLACEMENT PROBLEMS
If the outside skid gets too close to the
rounded edge of existing pavement, the slurry box
may slide and cause the box to vibrate or jump.
This can cause a washboarding effect on the
slurry surfacing.
62EDGE LINE
A good control line will aide in a smooth and
straight edge line.
Notice slurry material is leaking between the
primary screed allowing the slurry to cover
beyond the skids
63HEADERS
64HEADERS
When cleaning in front of the header, make sure
emulsion is not washed off of the placed slurry
seal
65CLEANING SPREADER AT HEADER
66TAKING OFF FROM A HEADER
67COMING OFF A BRIDGE DECK
Use of roofing paper and duct tape to cover edge
of bridge deck
68TRAFFIC CONTROL
Usually, within an hour, the slurry can carry
traffic but not excessive twisting/turning of
heavy equipment
69EPOXY PAVEMENT MARKING
Moisture in slurry can continue to leach long
after placement, causing damage to permanent
pavement marking. A minimum of four weeks
between slurry placement and permanent pavement
marking placement is recommended. Epoxy pavement
marking was placed about 3 weeks after completion
of slurry seal.
70MORE EPOXY PAVEMENT MARKING DAMAGE
71CONSTANT CLEANING AND MAINTENANCE IS THE KEY TO A
QUALITY JOB
72TACKED SURFACE NEST TO SLURRY SEALED SURFACE
Notice relatively straight centerline
73EXAMPLE OF QUALITY LAYDOWN
74ADDITIONAL INFORMATION-ITEMS TO MONITOR
- Ensure calibration is completed before placement
of slurry seal or calibration data is provided
from previous project (using same materials) - Ensure inappropriate materials do not contaminate
slurry from digging too low in stockpile - Monitor stockpile segregation
- Is moisture in stockpile consistent (a new mix
design may be necessary if moisture changes
dramatically
75ADDITIONAL INFORMATION-ITEM TO MONITOR
- Recommend, as a minimum, calculating aggregate
cut off at end of each day (the difference
between the slurry machines dial reading
calculation and total tonnage hauled by totaling
tickets for comparison) - Monitor air and surface temperatures for limits
as specified in the special provision - Monitor weather
- Monitor roadway ahead for last minute
contamination - Take periodic depth checks of placed slurry seal
make sure to stay within thickness spec. - Check yield on a regular basis
- Monitor slurry for minimal drag marks, should to
exceed 6 - Ensure the centerline overlap does not create a
safety hazard due to buildup of slurry on edge
76ADDITIONAL INFORMATION-ITEMS TO MONITOR
- Adjust squeegee (secondary strike-off) angle for
best or preferred surface texture - Ensure traffic control is maintained and minimal
delays to the public - Monitor construction equipment for leaking fluids
- Acquire samples of materials, as required
- Watch for slurry not overlapping at centerline
- Periodic measurement of slurry seal widths
77ADDITIONAL INFORMATION-ITEMS TO MONITOR
- Watch for washboard effect in the placed slurry
seal - Keep material haulers from driving on fresh tack
- Watch for leaking equipment
- Over filled cracks can create problems-skids can
hook material and drag it. Small pieces can than
cause dragging problems when placing the slurry
78EXAMPLE OF EXCEL SPREADSHEET YIELD CHECK
Green are required inputs and yellow shows
desired information
79TICKET WEIGHT COMPARED TO PLAN YIELD CHECK USING
EXCEL SPREADSHEET
80PLAN SLURRY SEAL-MANVEL INTERSECTION
81SLURRY SEAL PLACEMENT DAY 1-MANVEL INTERSECTION
Slurry seal is basically placed in straight
lines, overlapping. It is difficult to turn the
slurry seal machine sharp enough to turn most
intersections
82SLURRY SEAL PLACEMENT DAY 2-MANVEL INTERSECTION
83USE OF SPOTTING TABS
- Spotting tabs, if used for centerline control,
can create a void as the tab is knocked down by
the slurry box - The tab can be torn away by the slurry box skid
or the squeegees - Are used for marking utility holes, stop bars,
inlets, etc.
84EXAMPLE OF FIELD EXPEDIANT SLURRY SEAL FOOT WEAR
85USEFUL WEBSITES
- Valley Slurry Seal Co
- http//www.slurry.com/equip_microsurfacing.shtml
- International Slurry Surfacing Association
- http//www.slurry.org/
- MNDOT
- http//www.mnltap.umn.edu/pdf/asphalt.pdf
- Intermountain Slurry
- http//www.intermountainslurry.com/services_UT.ht
m