Title: U.S. Army Corps of Engineers
1- U.S. Army Corps of Engineers
- Monthly Project Review w/ USAG
- 21 November 2006
2- Agenda
- Project Reviews
- EUL
- CUP
- Hotel-Conf Ctr/Gateway
- Design Projects
- USAMRIID
- Steam Sterilization Plant
- SATCOM
- RAA/DA
- Construction Projects
- Remote Truck Inspection
- Main Gate
- JMLC
- Fire Station
- UEPH
- General Discussion Items
3- PROJECT Enhanced Use Lease For Central Utility
Plant (CUP) -
- SCOPE/DESCRIPTION Phase 1 will provide highly
reliable conditioned electricity, steam, chilled
water, and emergency standby electrical
generation to multiple off-taker facilities owned
by the Army, Department of Homeland Security, and
the National Institutes of Health. Specifically
three NIBC tenants to include approximately 16MW
of diesel-fueled back-up emergency power, 173,000
pounds per hour of steam capacity, 3,500 tons per
hour of chilled water capacity, and the optional
capability to improve power quality and
reliability by passing Fort Detrick-purchased
electricity through a power conditioning system.
The Phase 2 CUP expansion is intended to include
full-scale co-generation and will be constructed
as the NIBC and other commercial energy markets
grow. - CONTRACT DATA
- Developer Chevron
-
- SCHEDULE
- Lease Signed April 1, 2006
- Loan Closed August 3, 2006 (financing for
project) - Ground Breaking October 2006
- Commercial Operation 1st quarter 2008
- CHEVRON CAPITAL COST
- 100 Million
-
- ISSUES
4- PROJECT Enhanced Use Lease For Gateway Center
-
- SCOPE/DESCRIPTION Hotel and conference center
mixed use office, laboratory and retail space.
Retail space is MWR and AAAFES operated.
Possible other retail users with their approval.
Land rent will be taken in in-kind services to
offset OM costs at Fort Detrick. Approximately
20 acres will comprise the hotel and conference
center and 4 acres will comprise the remainder. - CONTRACT DATA
- Developer To be selected
-
- SCHEDULE
- Industry Forum January 2007
- Source Selection February 2007
- Developer Selected March 2007
- Lease Signed November 2007
-
- ISSUES
- The market study is being revised.
5Fort Detrick Integrated Program Office
Projects (Design)
USAMRIID Recapitalization Stage I FY 07 DODM PN
058395 550 M S2 design under review
USAMRIID Sterilization Plant (SSP) FY 06 DODM PN
059215 21.2 M S7 design under review over budget
Satellite Communications Facility (SATCOM) FY 10
MCA PN 058625 14 M Congressional Design Concept
submittal 07 Feb 07
DEF Satellite Communications Facility (SATCON) FY
10 MCA PN 057579 24 M Design on hold
Research Support Ops Center (RESOC) FY 13 MCA PN
055840 27 M Design on hold
Research Acq Bldg (RAA/DA) LR MCA PN
055839 12.4 M Potential FY 07 Congressional
Insert Concept submittal 11 Dec 06
6- PROJECT USAMRIID Recapitalization Stage I
-
- SCOPE/DESCRIPTION The USAMRIID Stage 1 Project
will decompress the existing USAMRIID facility
and allow the agency to conduct work in
appropriate facilities. The new USAMRIID Stage 1
facility will include approximately 687,000 gross
square feet (GSF) of laboratories, aerobiology,
vivarium, and administrative space. Existing
Buildings 1412 and 1408 at Fort Detrick, as well
as several additional USAMRIID assets, are
planned for demolition after the completion and
occupancy of Stage 1. Stage 1 also supports the
Base Realignment and Closure- (BRAC-) recommended
relocation of the medical biological defense
research programs from the Walter Reed Army
Institute of Research and the Naval Medical
Research Center at Forrest Glen, Maryland, to
USAMRIID. This relocation will allow the
formation of the Joint Center of Excellence in
Medical Biological Defense Research - .
- CONTRACT DATA
- AE CUH2A Smith Carter Hemisphere Princeton,
NJ -
- SCHEDULE
- Design Start 24 March 2006
- S2 (15) Submittal 11 October 2006
- S4 (35) Submittal 28 March 2007
- Design Complete March 2008
- ISSUES
- Evaluating peer review comments
- Verifying parking requirements will be met under
revised Master Plan - Verifying CUP load requirements
-
7- PROJECT Steam Sterilization Plant (SSP)
-
- SCOPE/DESCRIPTION New facility to thermally
treat all high containment waste generated by
existing USAMRIID facilities and USAMRIID Stage
1. - CONTRACT DATA
- AE Summer Consultants, Inc. McLean, Va
-
- SCHEDULE
- Design Start 11 March 2005
- S6 (100) Submittal 21 July 2006
- Design Complete 15 December 2006
- Contract Award TBD
- ISSUES
- Current design cannot be executed within
Programmed Amount - Option to combine infrastructure with RIID Stage
1 under evaluation -
8- PROJECT Satellite Communications Facility
(SATCOM) -
- SCOPE/DESCRIPTION The project consists of
co-locating the Satellite Communications
Facility, currently operating in Building 1685
and the Primary Technical Control Facility,
currently operating from Building 1671 in a new
masonry building constructed on the site of the
existing Building 1685. -
- CONTRACT DATA
- AE (Selected) RTKL Baltimore, MD
-
- SCHEDULE
- Design Authorized February 2006
- Design Start 2 October 2006
- Concept Submittal 7 February 2007 / Mid-Point
Review to be conducted mid-December 2006 - Design Complete 1 November 2007
- ISSUES
- This is a Congressionally mandated design
project. - NETCOM has determined that additional equipment
is available to allow expansion of the existing
building rather than renovating with existing
equipment in place. - Design Review / Charrette conducted 26 October
2006. Building layout has yet to be determined,
yet is being developed by A-E based on equipment
layout. 15 Design review will be submitted 30
November 2006, with On-Board Review scheduled for
week of 11 December 2006.
9- PROJECT Research Acquisition Building
(RAA/DA) -
- SCOPE/DESCRIPTION Construct a permanent building
to provide administrative space for the U.S.
Army Medical Materiel Development Activity. - CONTRACT DATA
- AE Baltimore District In-house Design
-
- SCHEDULE
- Design Start 24 April 2006
- Design Charrette Submittal 20 July 2006
- Concept Submittal 11 December 2006
- Design Complete 1 November 2007
- ISSUES
- This is a Congressionally mandated design and
potential FY 07 Congressional Add construction
project. During the Charrette process decisions
were made regarding the desired location of the
building (adjacent to Bldg 810) and occupancy
requirements of the building (205 personnel).
Final Charrette Report was distributed on 17 July
2006. Updated ASIP to be completed in October
2006. -
10Fort Detrick Integrated Program Office
Projects (Construction)
Fire Station Expansion Renovation FY 03 PN
055838 4.24M Earth Savers Inc Start Date 31
January 2006 Occupancy 01 April 2007
Remote Truck Inspection Fac FY 05 MCA PN 060026
(Cong Add) 4 M Construction contract
awarded 07 Sep 06
JMLC FY 06 DODM PN 050302 34.0 M Mascaro
Construction Start Date 14 March 2006 Occupancy
28 December 2008
Main Gate FY 02 PN 057895 4.95 M ESA
Environmental Start Date 7 January
2005 Occupancy 01 December 2005
UEPH II FY 03 PN 046876 16.0M (Barracks,DFAC,
COF) Coakley Williams Construction Start Date 31
October 2003 Comnpletion 24 Jun 06
11- PROJECT Remote Truck Inspection Station
-
- SCOPE/DESCRIPTION Construct an access control
point and truck inspection facility with truck
holding area to meet current security
requirements. - CONTRACT INFORMATION DACA31-03-C-0027 Awarded
to Capitol Technology Services - Contract amount 3,722,000 (original) 3,722,00
0 (current)
- SCHEDULE
- Award 7 Sept 06 NTP 20 Nov 06
- Original Contract Completion NTP365
Current Contract Completion 20 Nov 07 - Schedule 0 Actual 0
- ISSUES
- NTP delayed to Mid-November to accommodate late
winter/spring 07 start
12- PROJECT Main Gate
-
- SCOPE/DESCRIPTION Relocate 7th St gate to
improve force protection/antiterrorism levels and
traffic management. Construct four lanes of
pavement, heated/cooled guard house with office,
vehicle check canopy, active vehicle barriers,
cameras, guard booths, heated/cooled over-watch
station, pond with fountain, masonry pier
decorative access fence with vehicle-rated cable
system. - CONTRACT INFORMATION DACA65-02-D-0055 Awarded
to ESA Environmental - 4,350,000 NTE (original) 5,303,188 (current)
-
- SCHEDULE
- Award 30 Sept 02 Construction NTP 7 Jan 05
- Original Contract Completion 30 Sept
03 Contract Completion 1 Dec 05 - Actual Completion 11 Nov 05
- Schedule 100 Actual 98
- ISSUES
- New Contract to be awarded for Main Sign and
Planting grass _at_ pond. Sign to be presented at
the Real Property Master Planning Board on 29 Nov
06.
13- PROJECT Joint Medical Logistics Center
(JMLC) -
- SCOPE/DESCRIPTION Design/build a multi-story
130,000 SF facility for joint medical logistics
operations. Facilities include but are not
limited to site work, utilities, information
systems, parking, comprehensive interior design
package, specialized storage areas, conference
rooms, security intrusion detection system,
uninterruptible power supply back-up
generators, and HVAC. - CONTRACT INFORMATION W912DR-06-C-001 Awarded to
Mascaro Construction - Contract amount 26,448,000.00
(original) 26,448,000.00 (current) -
- SCHEDULE
- Award 14 Feb 06 NTP 14 Mar 06
- Original Contract Completion 30 Aug 08 Current
Contract Completion 30 Aug 08 - Expected Occupancy Date 28 Dec 08
- Schedule 10 Actual 10
- ISSUES
- Design progress meetings occurring weekly on
Mondays _at_ 1100 Govt only and 1400 w/ contractor. - MDE permit package under review
- Change for Electrical Primary Route bldg 459
- Additional Parking
14- PROJECT Fire Station Expansion and
Renovation -
- SCOPE/DESCRIPTION Complete the renovation of the
existing fire station facility and construction
of the new Fire Fighting Equipment Structure
addition to the existing facility for the Fire
and Emergency Services Facility at Fort Detrick,
Maryland (Building 1504). Due to funding issues,
the task order contract is broken down into two
construction phases. Phase 1 was awarded with
existing funds and Phase 2 was awarded after
receipt of additional funding from the
Congressional Reprogramming. - CONTRACT INFORMATION W912DR-04-D-0045 Awarded
to Earth Savers, Inc. - Base Bid - Phase 1 2,110,850.00 Duration
240 calendar days - Optional Bid Item Phase 21,054,423.00 Duratio
n 120 calendar days -
- SCHEDULE
- Award 12 Dec 05 NTP 31 Jan 06
- Original Contract Completion 28 Sep 06 Current
Contract Completion 26 Feb 07 - Occupancy Date 01 Apr 07
- ISSUES
- None.
-
15- PROJECT UEPH Phase II
-
- SCOPE/DESCRIPTION Construction of two new 17,600
SF, three story Barracks structures. Each
structure contains a total of 48 Living/Sleeping
Quarters approx. 150 SF each. Construction of
one new 12,600 SF Dining Facility. The Dining
Facility includes a kitchen, serving, dining,
carry-out and two dining areas. Construction of
one new 5,000 SF Company Operations Facility. - CONTRACT INFORMATION DACA31-03-C-0027 Awarded
to Coakley Williams Construction - Contract amount 14,080,150 (original) 15,253,1
51 (current)
- SCHEDULE
- Award 30 Sept 03 NTP 31 Oct 03
- Original Contract Completion 22 Apr 05
Current Contract Completion 24 June 06 - Schedule 100 Actual 100
- ISSUES
- None