SCOPE/DESCRIPTION: Phase 1 will provide highly reliable conditioned electricity, ... 687,000 gross square feet (GSF) of laboratories, aerobiology, vivarium, ... – PowerPoint PPT presentation

Number of Views:349
Avg rating:3.0/5.0
Slides: 16
Provided by: cptsea
Category:
Tags: army | corps | engineers | feet | links

less

Transcript and Presenter's Notes

Title: U.S. Army Corps of Engineers


1
  • U.S. Army Corps of Engineers
  • Monthly Project Review w/ USAG
  • 21 November 2006

2
  • Agenda
  • Project Reviews
  • EUL
  • CUP
  • Hotel-Conf Ctr/Gateway
  • Design Projects
  • USAMRIID
  • Steam Sterilization Plant
  • SATCOM
  • RAA/DA
  • Construction Projects
  • Remote Truck Inspection
  • Main Gate
  • JMLC
  • Fire Station
  • UEPH
  • General Discussion Items

3
  • PROJECT Enhanced Use Lease For Central Utility
    Plant (CUP)
  • SCOPE/DESCRIPTION Phase 1 will provide highly
    reliable conditioned electricity, steam, chilled
    water, and emergency standby electrical
    generation to multiple off-taker facilities owned
    by the Army, Department of Homeland Security, and
    the National Institutes of Health. Specifically
    three NIBC tenants to include approximately 16MW
    of diesel-fueled back-up emergency power, 173,000
    pounds per hour of steam capacity, 3,500 tons per
    hour of chilled water capacity, and the optional
    capability to improve power quality and
    reliability by passing Fort Detrick-purchased
    electricity through a power conditioning system.
    The Phase 2 CUP expansion is intended to include
    full-scale co-generation and will be constructed
    as the NIBC and other commercial energy markets
    grow.
  • CONTRACT DATA
  • Developer Chevron

  • SCHEDULE
  • Lease Signed April 1, 2006
  • Loan Closed August 3, 2006 (financing for
    project)
  • Ground Breaking October 2006
  • Commercial Operation 1st quarter 2008
  • CHEVRON CAPITAL COST
  • 100 Million
  • ISSUES

4
  • PROJECT Enhanced Use Lease For Gateway Center
  • SCOPE/DESCRIPTION Hotel and conference center
    mixed use office, laboratory and retail space.
    Retail space is MWR and AAAFES operated.
    Possible other retail users with their approval.
    Land rent will be taken in in-kind services to
    offset OM costs at Fort Detrick. Approximately
    20 acres will comprise the hotel and conference
    center and 4 acres will comprise the remainder.
  • CONTRACT DATA
  • Developer To be selected

  • SCHEDULE
  • Industry Forum January 2007
  • Source Selection February 2007
  • Developer Selected March 2007
  • Lease Signed November 2007
  • ISSUES
  • The market study is being revised.

5
Fort Detrick Integrated Program Office
Projects (Design)
USAMRIID Recapitalization Stage I FY 07 DODM PN
058395 550 M S2 design under review
USAMRIID Sterilization Plant (SSP) FY 06 DODM PN
059215 21.2 M S7 design under review over budget
Satellite Communications Facility (SATCOM) FY 10
MCA PN 058625 14 M Congressional Design Concept
submittal 07 Feb 07
DEF Satellite Communications Facility (SATCON) FY
10 MCA PN 057579 24 M Design on hold
Research Support Ops Center (RESOC) FY 13 MCA PN
055840 27 M Design on hold
Research Acq Bldg (RAA/DA) LR MCA PN
055839 12.4 M Potential FY 07 Congressional
Insert Concept submittal 11 Dec 06
6
  • PROJECT USAMRIID Recapitalization Stage I
  • SCOPE/DESCRIPTION The USAMRIID Stage 1 Project
    will decompress the existing USAMRIID facility
    and allow the agency to conduct work in
    appropriate facilities. The new USAMRIID Stage 1
    facility will include approximately 687,000 gross
    square feet (GSF) of laboratories, aerobiology,
    vivarium, and administrative space. Existing
    Buildings 1412 and 1408 at Fort Detrick, as well
    as several additional USAMRIID assets, are
    planned for demolition after the completion and
    occupancy of Stage 1. Stage 1 also supports the
    Base Realignment and Closure- (BRAC-) recommended
    relocation of the medical biological defense
    research programs from the Walter Reed Army
    Institute of Research and the Naval Medical
    Research Center at Forrest Glen, Maryland, to
    USAMRIID. This relocation will allow the
    formation of the Joint Center of Excellence in
    Medical Biological Defense Research
  • .
  • CONTRACT DATA
  • AE CUH2A Smith Carter Hemisphere Princeton,
    NJ

  • SCHEDULE
  • Design Start 24 March 2006
  • S2 (15) Submittal 11 October 2006
  • S4 (35) Submittal 28 March 2007
  • Design Complete March 2008
  • ISSUES
  • Evaluating peer review comments
  • Verifying parking requirements will be met under
    revised Master Plan
  • Verifying CUP load requirements

7
  • PROJECT Steam Sterilization Plant (SSP)
  • SCOPE/DESCRIPTION New facility to thermally
    treat all high containment waste generated by
    existing USAMRIID facilities and USAMRIID Stage
    1.
  • CONTRACT DATA
  • AE Summer Consultants, Inc. McLean, Va

  • SCHEDULE
  • Design Start 11 March 2005
  • S6 (100) Submittal 21 July 2006
  • Design Complete 15 December 2006
  • Contract Award TBD
  • ISSUES
  • Current design cannot be executed within
    Programmed Amount
  • Option to combine infrastructure with RIID Stage
    1 under evaluation

8
  • PROJECT Satellite Communications Facility
    (SATCOM)
  • SCOPE/DESCRIPTION The project consists of
    co-locating the Satellite Communications
    Facility, currently operating in Building 1685
    and the Primary Technical Control Facility,
    currently operating from Building 1671 in a new
    masonry building constructed on the site of the
    existing Building 1685.
  • CONTRACT DATA
  • AE (Selected) RTKL Baltimore, MD

  • SCHEDULE
  • Design Authorized February 2006
  • Design Start 2 October 2006
  • Concept Submittal 7 February 2007 / Mid-Point
    Review to be conducted mid-December 2006
  • Design Complete 1 November 2007
  • ISSUES
  • This is a Congressionally mandated design
    project.
  • NETCOM has determined that additional equipment
    is available to allow expansion of the existing
    building rather than renovating with existing
    equipment in place.
  • Design Review / Charrette conducted 26 October
    2006. Building layout has yet to be determined,
    yet is being developed by A-E based on equipment
    layout. 15 Design review will be submitted 30
    November 2006, with On-Board Review scheduled for
    week of 11 December 2006.

9
  • PROJECT Research Acquisition Building
    (RAA/DA)
  • SCOPE/DESCRIPTION Construct a permanent building
    to provide administrative space for the U.S.
    Army Medical Materiel Development Activity.
  • CONTRACT DATA
  • AE Baltimore District In-house Design
  • SCHEDULE
  • Design Start 24 April 2006
  • Design Charrette Submittal 20 July 2006
  • Concept Submittal 11 December 2006
  • Design Complete 1 November 2007
  • ISSUES
  • This is a Congressionally mandated design and
    potential FY 07 Congressional Add construction
    project. During the Charrette process decisions
    were made regarding the desired location of the
    building (adjacent to Bldg 810) and occupancy
    requirements of the building (205 personnel).
    Final Charrette Report was distributed on 17 July
    2006. Updated ASIP to be completed in October
    2006.

10
Fort Detrick Integrated Program Office
Projects (Construction)
Fire Station Expansion Renovation FY 03 PN
055838 4.24M Earth Savers Inc Start Date 31
January 2006 Occupancy 01 April 2007

Remote Truck Inspection Fac FY 05 MCA PN 060026
(Cong Add) 4 M Construction contract
awarded 07 Sep 06
JMLC FY 06 DODM PN 050302 34.0 M Mascaro
Construction Start Date 14 March 2006 Occupancy
28 December 2008
Main Gate FY 02 PN 057895 4.95 M ESA
Environmental Start Date 7 January
2005 Occupancy 01 December 2005
UEPH II FY 03 PN 046876 16.0M (Barracks,DFAC,
COF) Coakley Williams Construction Start Date 31
October 2003 Comnpletion 24 Jun 06
11
  • PROJECT Remote Truck Inspection Station
  • SCOPE/DESCRIPTION Construct an access control
    point and truck inspection facility with truck
    holding area to meet current security
    requirements.
  • CONTRACT INFORMATION DACA31-03-C-0027 Awarded
    to Capitol Technology Services
  • Contract amount 3,722,000 (original) 3,722,00
    0 (current)
  • SCHEDULE
  • Award 7 Sept 06 NTP 20 Nov 06
  • Original Contract Completion NTP365
    Current Contract Completion 20 Nov 07
  • Schedule 0 Actual 0
  • ISSUES
  • NTP delayed to Mid-November to accommodate late
    winter/spring 07 start

12
  • PROJECT Main Gate
  • SCOPE/DESCRIPTION Relocate 7th St gate to
    improve force protection/antiterrorism levels and
    traffic management. Construct four lanes of
    pavement, heated/cooled guard house with office,
    vehicle check canopy, active vehicle barriers,
    cameras, guard booths, heated/cooled over-watch
    station, pond with fountain, masonry pier
    decorative access fence with vehicle-rated cable
    system.
  • CONTRACT INFORMATION DACA65-02-D-0055 Awarded
    to ESA Environmental
  • 4,350,000 NTE (original) 5,303,188 (current)

  • SCHEDULE
  • Award 30 Sept 02 Construction NTP 7 Jan 05
  • Original Contract Completion 30 Sept
    03 Contract Completion 1 Dec 05
  • Actual Completion 11 Nov 05
  • Schedule 100 Actual 98
  • ISSUES
  • New Contract to be awarded for Main Sign and
    Planting grass _at_ pond. Sign to be presented at
    the Real Property Master Planning Board on 29 Nov
    06.

13
  • PROJECT Joint Medical Logistics Center
    (JMLC)
  • SCOPE/DESCRIPTION Design/build a multi-story
    130,000 SF facility for joint medical logistics
    operations. Facilities include but are not
    limited to site work, utilities, information
    systems, parking, comprehensive interior design
    package, specialized storage areas, conference
    rooms, security intrusion detection system,
    uninterruptible power supply back-up
    generators, and HVAC.
  • CONTRACT INFORMATION W912DR-06-C-001 Awarded to
    Mascaro Construction
  • Contract amount 26,448,000.00
    (original) 26,448,000.00 (current)

  • SCHEDULE
  • Award 14 Feb 06 NTP 14 Mar 06
  • Original Contract Completion 30 Aug 08 Current
    Contract Completion 30 Aug 08
  • Expected Occupancy Date 28 Dec 08
  • Schedule 10 Actual 10
  • ISSUES
  • Design progress meetings occurring weekly on
    Mondays _at_ 1100 Govt only and 1400 w/ contractor.
  • MDE permit package under review
  • Change for Electrical Primary Route bldg 459
  • Additional Parking

14
  • PROJECT Fire Station Expansion and
    Renovation
  • SCOPE/DESCRIPTION Complete the renovation of the
    existing fire station facility and construction
    of the new Fire Fighting Equipment Structure
    addition to the existing facility for the Fire
    and Emergency Services Facility at Fort Detrick,
    Maryland (Building 1504). Due to funding issues,
    the task order contract is broken down into two
    construction phases. Phase 1 was awarded with
    existing funds and Phase 2 was awarded after
    receipt of additional funding from the
    Congressional Reprogramming.
  • CONTRACT INFORMATION W912DR-04-D-0045 Awarded
    to Earth Savers, Inc.
  • Base Bid - Phase 1 2,110,850.00 Duration
    240 calendar days
  • Optional Bid Item Phase 21,054,423.00 Duratio
    n 120 calendar days

  • SCHEDULE
  • Award 12 Dec 05 NTP 31 Jan 06
  • Original Contract Completion 28 Sep 06 Current
    Contract Completion 26 Feb 07
  • Occupancy Date 01 Apr 07
  • ISSUES
  • None.

15
  • PROJECT UEPH Phase II
  • SCOPE/DESCRIPTION Construction of two new 17,600
    SF, three story Barracks structures. Each
    structure contains a total of 48 Living/Sleeping
    Quarters approx. 150 SF each. Construction of
    one new 12,600 SF Dining Facility. The Dining
    Facility includes a kitchen, serving, dining,
    carry-out and two dining areas. Construction of
    one new 5,000 SF Company Operations Facility.
  • CONTRACT INFORMATION DACA31-03-C-0027 Awarded
    to Coakley Williams Construction
  • Contract amount 14,080,150 (original) 15,253,1
    51 (current)
  • SCHEDULE
  • Award 30 Sept 03 NTP 31 Oct 03
  • Original Contract Completion 22 Apr 05
    Current Contract Completion 24 June 06
  • Schedule 100 Actual 100
  • ISSUES
  • None