Title: Presentation
1Presentation
2SIF Life Cycle
Hazards analysis (HAZOP /PHA)
SIS Requirements specification
SIF definition
Risk analysis (SIL assessment)
Design/Implementation
Assign tags / SFC to subsystems
Safe failure assessment (for SFCs)
Test intervals calcs
ALARP assessment
Analyze results (e.g. yearly)
Test Procedures
Execute Tests (validations)
3Lets have a look how this valve can fail?
4Dangerous Failure
GO
5Safe Failure
STOP
6RISK REDUCTION GENERAL CONCEPTS
ACTUAL
ACCEPTABLE
INTERMEDIATE
INITIAL RISK
REMAINING RISK
RISK
RISK
Risk with the
Risk without the
Risk with the
addition of other
addition of any
addition of other
TOLERABLE RISK
risk reduction
protective features
risk reduction
facilities and
facilities
SIF function
ALARP region
INCREASING
RISK
NECESSARY
RISK REDUCTION
ACTUAL RISK REDUCTION
Partial risk
other risk reduction facilities
covered by
SIF
Total risk reduction
7LAYERS OF PROTECTION (THE ONION MODEL)
the bowtie
consequences
threats
(independent)
8What is risk?
- Risk can be mapped on a graph
high risk
Increasing risk
Lines of equal risk
Likelihood
Consequences
low risk
9What is risk?
High Risk
Likelihood
Low Risk
Consequence
10Risk reduction
Preventive and Mitigating SIF effects
High Risk
Likelihood,(or DR)
Low Risk
CQ1
CQ2
Consequence
11A Risk Assessment Matrix (RAM)
Broadly acceptable risks
Tollerable risk
The required SIL (to make the risk broadly
acceptable) can directly be entered in the cell
that represents the initial risk.
Intollerable risks
1
2
3
4
High Risk
1
a
1
2
3
Likelihood (y-1)
10-1
a
a
1
2
10-2
Example Only
-
a
a
1
Low Risk
Consequence
12Risk Matrix
SIL2
SILa
SIL4
SIL3
SIL1
SILa
SIL4
SIL3
SIL2
SILa
SIL3
SIL2
SIL1
SIL2
SIL1
SILa
SIL1
SILa
SILa
13Chain of events
Process under control
Process deviation or disturbance
Process out of control
Demand scenario
Hazardous situation
Design intent prevent ltreleased hazardgt
Released Hazard
SIF
Hazardous event
Consequences of failure on demand
Consequences
14Risk Matrix
SILa
SIL4
SIL3
SIL2
SILa
SIL4
SIL3
SIL2
SIL1
SILa
SIL3
SIL2
SIL1
SIL2
SIL1
SILa
SILa
SILa
SIL1
15Process Safety Time
16SIL Assessment
- Team
- Facilitator (TE)
- Process engineer
- Operations
- Instr./Control eng.
- Operational safety
- Equipment specialists(PT)
- Min. Preparation
- Unit structure data
- PID/PFS
- CE diagrams etc.
- Required data
- Asset data
- failure rates
- complex/simple
- Safe F. frac.
- repair time
- LS type(s)
- Test related data
- Cov. factor
- duration
- Self diagnostic cov.
SIF design
17Alarp Principle IEC 61511
Risk Classes
Interpretation
Unacceptable Region
Risk can not be justified except in
extraordinary circumstances
Intolerable Risk
I
Undesirable Risk Tolerable only if further risk
re -duction is impra -ticable or if its
cost is grossly disproportionate to improve
gained
Risk is tolerable only if a. Further Risk
reduction is Impractical or if its cost is
disproportionate to the Improvement gained
or b. Society desires the benefit of The
activity given the associated Risk As Risk
is reduced, the less, in Proportion, it is
necessary to spend To satisfy ALARP, The concept
of Diminishing proportion is Represented by the
triangle
II
Tolerable Region
Increasing Individual Risk and Social Concerns
Tolerable Risk if the cost of risk reduction
would exceed the im- provement gained
III
Level of residual risk regarded as Negligible,
and further measures to Reduce risk not usually
required. No Need for detailed working
to Demonstrate ALARP
Broadly Acceptable Region
Negligible Risk
IV
Negligible Risk
18Tolerable and Acceptable risks
risk
SIL Class at least required to make the risk
tolerable the minimum solution, e.g. SIL 1
intolerable
SIL Class required to make the risk more
tolerable an intermediate solution, e.g.SIL 2
tolerable
SIL Class required to make the risk acceptable
the normal solution , e.g. SIL 3
broadly acceptable
SIL assessment aims to reduce the risk
to broadly acceptable
19Tolerable/Acceptable Risk, defaults
Personal Safety
Severity rating
0
N
L
M
H
E
Demand
No
health
slight effect /
Minor health
Major health
PDT or 1 to 3
Multiple
interval (y)
effect/injury
injury
effect / injury
effect/injury
fatalities
fatalities
Consequence
severity
Production losses and Equipment damage
Severity rating
0
N
L
M
H
E
Demand
Very Slight
Slight
Minor
Local damage
Major
Extensive
interval (y)
damage
damage
damage
100K
-
1M
damage
damage
lt 1K
lt 10K
10K
-
100K
1M
-
10M
gt10M
Consequence
severity
Environment
Severity rating
0
N
L
M
H
E
Demand
No effect
Slight effect
Minor effect
Localized
Major effect
Massive effect
interval (y)
effect
Consequence
severity
20Example
Personal Safety
- Demand rate 10 Yrs
- Safety Major Health Effect
- Economic loss 2 M
- Environment Minor Effect
Severity rating
0
N
L
M
H
E
Demand
No
health
slight effect /
Minor health
Major health
PDT or 1 to 3
Multiple
interval (y)
effect/injury
injury
effect / injury
effect/injury
fatalities
fatalities
Consequence
severity
Production losses and Equipment damage (Economic)
Severity rating
0
N
L
M
H
E
Demand
Very Slight
Slight
Minor
Local damage
Major
Extensive
interval (y)
damage
damage
damage
100K
-
1M
damage
damage
lt 1K
lt 10K
10K
-
100K
1M
-
10M
gt10M
Consequence
severity
Environment
Severity rating
0
N
L
M
H
E
Demand
No effect
Slight effect
Minor effect
Localized
Major effect
Massive effect
interval (y)
effect
Consequence
severity
21Quiz
- What is the frequency of occurrence Loss of
Containment in the following chain of events ?
PAH hi pressure alarm
22Solution
Loss of containment only if the following
events (Alarm Success AND Operator Fails AND
Relief Fails) OR (Alarm Fails AND
ReliefFails)
23Quizcontinued
Now add a SIF layer Probability of failure
0.01 So What is the frequency of occurrence
Loss of Containment In the following chain of
events?
PAH hi pressure alarm PZHH hi hi pressure
trip function,SIF
24Solution
Real demand frequency (on SIF) (3x0,9x0.1)
(3x0.1) 0.57 Freq/Yr Real demand rate 1/0.57
1.75 years
Loss of containment only if the following
events (Alarm Success AND Operator Fails AND
SIF Fails AND Relief Fails) OR (Alarm Fails
AND SIF Fails AND Relief Fails)
25Applied LOPA in SIFpro
26Example of defenses
pre-alarm and trip
Downstream blockage
Loss of containment
Explosion of gas cloud
One operator killed and 6 months downtime
ignition
exposure
Conditional modifiers
Mitigation layers
Protection layers
Initiating events
hazard
Released hazard
Consequences
RV pops
Flaring
RV repair Environmental impact
The PSHH function
27Lopa General Structure
Conditional modifiers
Mitigation layers
Protection layers
Initiating events
Hazardous event
Hazardous event
Consequences
Total initiating event frequency
Hazard rate
Real demand frequency
SIF
FG
28Example- Furnace fuel
Furnace
Crude feed
TZHH
NG
Fuel gas
29Example- Syngas reactor
Syngas (CO, H2) to Synthesis reactor
Syngas reactor
TZHH
CH4
O2
30Example - Compressor
Collateral SIFs
Sensor M XZ2 XZ3
LZHH X X X
XZHH X X X
Seal oil
LZLL
XZ4
UZ3
UZ1
UZ2
M
XZHH
LZHH
31How is it done?
Hazards analysis (HAZOP /PHA)
SIS Requirements specification
SIF definition
Risk analysis (SIL assessment)
Design/Implementation
Assign tags / SFC to subsystems
Safe failure assessment (for SFCs)
Test intervals calcs
ALARP assessment
Analyze results (e.g. yearly)
Test Procedures
Execute Tests (validations)
32Instruments do fail sometimes!
frequency of failure (y -1)
time
33Instruments fail randomly..
frequency of failure (y -1)
time
34Probability of failure as function of time
First few years PFDt is about linear PFDt ld
t
35PFD as function of time with testing
Because a demand may occur any time we are
interested in the average risk reduction, i.e.
the PFDavg
36Thank You !