Title: An Introduction to our
1Report of Agreed Upon Procedures for the
International Advisory and Monitoring
Board Regarding the Task Force Restore Iraqi
Oil Contract Settlement between the U.S. Army
Corps of Engineers and Kellogg, Brown, Root
October 30, 2006
An Introduction to our Forensic Services
Practice
2Summary of Agreed-Upon Procedures Report
- Report of Agreed-Upon Procedures regarding
- The Contract Settlement between
- the U.S. Army Corps of Engineers
- and Kellogg, Brown Root
- related to the
- Task Force Restore Iraqi Oil Project
- for
- U.S. Defense Reconstruction Support Office
- and
- International Advisory and Monitoring Board
- By
- Crowe Chizek and Company LLC
- October 20, 2006
3The KBR contract with theUS Corps of Engineers
(USACE)
- Contract number DACA63-03-D-0005
- Task Force Restore Iraqi Oil (TF RIO) contract
- Awarded to KBR on March 8, 2003
- Contracting Agency Southwestern Division of
USACE - Cost-plus-award-fee contract
- Period of Performance Base period of 2 years,
plus 3 one-year options - Base Fee 2 Award Fee Up to 5
- Ten Task Orders (T.O.s)
- T.O.s 1 - 4 and part of 5 funded from U.S.
appropriations - T.O.s 6 - 10 and most (82) of 5 funded from
DFI funds - T.O.s 5 - 10 closed out as of December 31, 2005
4Task Orders under the KBR TF RIO contract
- Training/advice for oil spill response equipment
pre-positioning - Design and specifications for quick repair of
critical oil facilities - Safe shutdown and damage assessment oil well
fire fighting and repairs - Base camp facilities (3) and life support for TF
RIO and KBR personnel - Funded by DFI
- Import and distribute refined fuel products
- Restore essential oil infrastructure
- Import and distribute refined fuel products
- Import and distribute refined fuel products
- Import and distribute refined fuel products
- Import and distribute refined fuel products
5The Environment of Contract Performance (March
2003 August 2004)
- War-time conditions throughout Iraq
- Exposure of fuel truck convoys to ambush, sniper
fire, roadside bombs, and rocket-propelled
grenades - Difficulty in obtaining military escorts for
convoys from Kuwait - Refusal of Turkish drivers to deliver fuel to
Baghdad - 85 casualties among KBR employees and contractors
including 21 fatalities - Hazardous job-site conditions at Al-Fatah Bridge
crossing of Tigris River - Hazardous job-site conditions at canal crossings
(Kirkuk, Riyadh, Zegeton)
6Environment (continued) Task Orders 5, 7-10 -
Humanitarian Fuel Mission
- Utmost urgency to supply refined fuel products
- Absence of long-term commitments in fuel supply
mission due to - Uncertain requirements and duration of fuel
supply mission - (Initial requirement for only 21 days supply)
- Sporadic and uncertain funding of fuel supply
mission - (21 modifications to Task Order 5)
- Insurgent activity
- Only one fuel supplier in Kuwait (Altanmia)
authorized by Kuwait Petroleum Company (KPC) - Insufficient number of fuel trucks in Kuwait
7Environment (continued) - Task Order 6 Oil
infrastructure projects
- Urgency to restore oil infrastructure as quickly
as possible to supply - Crude oil for export to generate revenue
- Refined product for domestic consumption
- Lack of construction site base camp at Al-Fatah
Bridge to commence work - Dangerous security situation at Al-Fatah and
three canal crossings - Geological complexities at Al-Fatah Bridge site
hampering HDD drilling, particularly for large
boreholes - Unstable electrical power - demand for back-up
power generation
8Total Payments under Task Orders 5 - 10
Task Order Reimbursed Direct Costs Indirect Costs Base Fee Award Fee Total
5 812,146,070 16,632,274 15,683,246 26,661,519 871,123,109
6 196,429,125 4,511,831 3,880,000 388,000 205,208,956
7 298,028,401 6,829,623 5,741,741 9,760,959 320,360,724
8 164,092,535 3,760,353 3,071,573 5,221,673 176,146,134
9 50,562,450 1,158,709 758,285 1,289,086 53,768,530
10 25,356,608 581,082 320,952 545,618 26,804,260
Total 1,546,615,189 33,473,872 29,455,797 43,866,855 1,653,411,713
As of Total 94 2 2 3 100
9Total Payments for Task Orders 5 -10 funded by DFI
Task Order Reimbursed Direct Costs Indirect Costs Base Fee Award Fee Total
5 667,151,571 13,662,872 12,883,277 21,901,570 715,599,290
6 196,429,125 4,511,831 3,880,000 388,000 205,208,956
7 298,028,401 6,829,623 5,741,741 9,760,959 320,360,724
8 164,092,535 3,760,353 3,071,573 5,221,673 176,146,134
9 50,562,450 1,158,709 758,285 1,289,086 53,768,530
10 25,356,608 581,082 320,952 545,618 26,804,260
Total 1,401,620,690 30,504,470 26,655,828 39,106,906 1,497,887,894
As of Total 94 2 2 3 100
10Snapshot of Completion Status
- Oil supply mission (T.O. 5, 7-10)
- Mission completed (May 2003 March 2004)
- Fuel supply commitment transferred to DESC in
April 2004 - Oil infrastructure mission (T.O. 6)
- HDD drilling of 15 pipelines at Al-Fatah
- KBR completed 6 pipelines (28 of throughput)
across Tigris River - PIJV completed remainder up-stream (U.S.
appropriations) - Canal crossings completed by PIJV (U.S.
appropriations) - Back-up Power Generators all delivered and
installed - 12 GE TM500 gas turbine generators
- One Pratt Whitney FT8 Twin-Pak gas turbine
generator - 42 diesel generators for SOC and other locations
11Snapshot of Completion Status (continued)
- Settlement negotiations concluded on December 22,
2005 - DCAA questioned 208 million of incurred costs,
but no recommendation to withhold reimbursement
of questioned costs - Disallowed 3.8 million of costs related to
diesel fuel transportation from Kuwait - KBR waived claim for 5.4 million in interest
- Excluded 108 million (52) of 208 million in
questioned costs from fee pool (37 million
impact on potential award fee)
12A Follow-on Procedure to SIGIR Engagement
- SIGIR Agreed-upon Procedure Report September 30,
2005 - Major Findings in SIGIR report
- The non-competitive award to KBR was properly
justified - T.O. 5 costs were definitized and determined to
be fair and reasonable - T.O.s 6 10 had not yet been definitized
- Appropriate justification for the contract
(signed by the - Assistant Secretary of the Army)
- Goods and services received and paid for with DFI
funds were provided for in contract - Total amount of DFI funds disbursed did not
exceed the amount obligated for the contract
13Our Scope of Work
- Focus on Task Orders 5 10 of the KBR contract
- (i) Review the Settlement between KBR and
USACE - Review the Work Performed by DCAA
- Confirm Physical Existence of Deliverables
under - Task Order 6
14Scope of Work Detailed Procedures
- (i) Review Settlement between KBR and USACE
- Provide a summary of the salient terms of the
settlement, including the disposition of costs
previously questioned by the DCAA and summarized
in the September 2005 SIGIR report. - Comment on the reasonableness and basis for the
settlement. - Compare the processes and procedures for contract
reconciliation and settlement of
non-competitively awarded KBR RIO contract
actions using DFI funds with the processes and
procedures for contract reconciliation and
settlement of non-competitively awarded KBR RIO
contract actions using U.S. appropriated funds. - Document the procedures undertaken by the USACE
contracting officer to establish that goods were
delivered and services were rendered for each of
the six task orders of the KBR RIO contract. - Show how the management and performance award
commission fees were calculated. - Obtain and summarize the terms for indirect
costs, including overheads.
15Scope of Work Detailed Procedures (continued)
- (ii) Review Work Performed by DCAA
- Obtain the contract files and review for
completeness. - Obtain evidence that the contracting procedures
were followed. - Perform a review of the reasonableness of the
price of imported fuel products compared to other
sources, for example, the prices charged to the
CPA or U.S. forces in Iraq at that time. - Where no comparable price is available, assess
the markup taking into account the wartime
conditions. - Obtain evidence that the goods were delivered and
the services were rendered in terms of quality
and quantity in accordance with the terms of the
relevant task order under the KBR RIO contract. - Determine by review of the agreement with the
contractor that payments were properly justified.
16Scope of Work Detailed Procedures (continued)
- (iii) Confirm Physical Existence of Deliverables
under Task Order 6.
17Primary Sources of Information
- From US Army Corps of Engineers (USACE)
- KBR contracts and subcontracts
- Task Orders and modifications
- Price Negotiation Memoranda (PNM) prepared by the
Corps - Administrative Contracting Officer
- Procurement and accounting documentation
- Interviews of USACE staff
- Written statements of USACE staff
- Correspondence and other materials
18Primary Sources of Information (continued)
- From Defense Contract Audit Agency (DCAA)
- DCAA Audit Reports on each Task Order
- Audit Workpapers
- Financial analyses in support of contract
negotiations by the USACE contracting officer - DCAA audit manuals
- Interviews of DCAA staff
- Correspondence and other materials
19Primary Sources of Information (continued)
- From Special Inspector General for Iraq
Reconstruction (SIGIR) - SIGIR audit reports and special assessment
reports - Workpapers in support of reports
- Interviews of SIGIR staff
20Primary Sources of Information (continued)
- From Defense Energy Support Center (DESC)
- Refined product pricing data
- Interviews of DESC staff
21Primary Sources of Information (continued)
- From Kellogg, Brown Root (KBR)
- KBR project accounting documentation
- Correspondence pertaining to contract and task
orders - Fuel supply data and correspondence
- Horizontal Directional Drilling (HDD) subcontract
information - Back-up generator information
- Interviews of KBR staff
22Results of Procedures
- Review Settlement between KBR and USACE
- Review Work Performed by DCAA
- Confirm Physical Existence of Task Order 6
Deliverables
23Results (i) Review Settlement between KBR and
USACE
- Reviewed the terms of settlements for Task Orders
5 through 10 - Evaluated the basis and reasonableness of
settlement based on - Negotiated terms of these settlements (costs and
fees) - Related supporting documentation, including Price
Negotiation Memoranda - Procedures followed by USACE and its Award Fee
Evaluation Board - DCAA audit reports and procedures undertaken in
auditing prices and costs as contained in work
papers - Interviews with cognizant USACE, DCAA, SIGIR,
DESC, and KBR personnel - Determined that the settlements were reasonable
24Results (i) Review Settlement between KBR and
USACE(continued)
- Reviewed documentation regarding determination of
base and award fees including review of
procedures followed by DCAA, the USACE
contracting officer and the USACE Award Fee
Evaluation Board - Recomputed base and award fees
- Reviewed documentation regarding the terms for
indirect costs, including overhead and GA - Recomputed indirect costs based on contractual
overhead and GA rates
25Results (ii) Review Work Performed by DCAA
- Determined that contract files were complete and
that contracting procedures were followed - Reviewed DCAA audit reports, audit procedures,
supporting work papers and memoranda to USACE.
Interviewed DCAA, USACE and KBR personnel
regarding DCAA procedures. - Reviewed price of imported fuel products, and
transportation, in the context of wartime
conditions and assessed comparability to costs
incurred by DESC commencing April 2004 - Reviewed process of obtaining bids from qualified
vendors - Reviewed evidence that goods were delivered and
services rendered in accordance with the terms of
task orders - Determined that payments were properly justified.
26Results (iii) Confirm Physical Existence of
T.O. 6 Deliverables
- Key Task Order 6 deliverables
- HDD pipeline crossing at Al-Fatah Bridge over the
Tigris River - Pipeline crossings at three canals (Kirkuk,
Riyadh and Zegeton) - Back-up gas turbine and diesel generators
- Conducted interviews with personnel and reviewed
extensive documentation from - USACE
- DCAA
- SIGIR
- KBR
- U.S. State Dept.
- Reviewed accounting documentation confirming
delivery - Reviewed photographic evidence confirming
delivery
27Determining Reasonableness (per FAR 31.2013)
- (a) A cost is reasonable if, in its nature and
amount, it does not exceed that which would be
incurred by a prudent person in the conduct of
competitive business . . . - (b) What is reasonable depends upon a variety of
considerations and circumstances, including -- - (1) Whether it is the type of cost generally
recognized as ordinary and necessary for the
conduct of the contractors business or the
contract performance - (2) Generally accepted sound business practices,
arms-length bargaining, and Federal and State
laws and regulations - (3) The contractors responsibilities to the
Government, other customers, the owners of the
business, employees, and the public at large and - (4) Any significant deviations from the
contractors established practices.
28Factors supporting reasonableness of payments for
Task Orders 5, 7-10
- The contracting process by USACE was consistent
with US government contracting procedures for
cost reimbursement contracts - The DCAA followed its standard audit procedures
- Reviewed interim payment vouchers from KBR
(together with USACE) - Provided provisional approval for payments
subject to later audit - Sought additional information from KBR
- Audited incurred costs
- Audited indirect costs based on negotiated
contractual rates - Prepared audit reports
- Provided advice to contracting agency (USACE) in
settling contract
29Factors supporting reasonableness of payments for
Task Orders 5, 7-10 (continued)
- Certain costs were questioned by the DCAA (176
million for fuel supply task orders 32 million
for T.O. 6 ) - Questioned costs were incurred for the benefit of
the mission - Questioned costs are not necessarily disallowable
costs - Questioned costs are costs incurred by a
contractor that DCAA recommends for further
consideration by the contracting officer - Neither the DCAA proposal audits nor its
financial advice to the contracting officer
included not reimbursing KBRS for the large
majority of the costs it had incurred in
executing the mission. DCAA did not issue a Form
1, Notice of Costs Suspended and/or Disapproved
under Cost Reimbursement Contracts
30Factors supporting reasonableness of payments for
Task Orders 5, 7-10 (continued)
- The prices of fuel products and related
costs of transportation into Iraq in these
wartime conditions were a reflection of existing
market conditions. - Multiple bids received on May 5, 2003 from Kuwait
vendors - Altanmia, Maar Specialties, and Elafco General
Trading - Altanmia was the low bidder and offered best
terms and - plan for fuel delivery
- Additional bids sought on May 7, 2003
- Altanmia, Jassim Transport and Stevedoring
Company, - Mohammed Al-Mojil Group, American United and
SABA - Altanmia again offered best terms
- Altanmia had exclusive right from KPC to purchase
and distribute fuel
31Factors supporting reasonableness of payments for
Task Orders 5, 7-10 (continued)
- DCAA proposed comparison to DESC for
transportation costs as a reliable benchmark for
assessing Altanmias costs - Both USACE Contracting Officer and DESC
disagreed - DESC was funded for 3 months up-front, making it
easier for contract negotiation - DESC benefited from KBR experience and lessons
learned - Contractors had trucks in place when DESC took
over. Start-up costs were covered - KPC dealt directly with DESC (as a U.S.
government entity) - Producer relationships in place with DESC to
support military requirements. KBR lacked DESCs
expertise in contracting for fuels - Expense of insurance coverage not required for
DESC contractors - DESC used economic price adjustment in contracts
32Factors supporting reasonableness of payments for
Task Orders 5, 7-10 (continued)
- USACE determined prices and transportation costs
to be reasonable (from PNM for T.O. 5) - The government will not refuse to pay KBRS the
actual incurred costs that have been questioned
in DCAA audits based on - A comparison of prices paid for transportation of
fuel from Kuwait to prices paid for fuel from
Turkey or - A comparison of prices paid for transportation of
fuel and the prices paid by DESC - Costs incurred for fuel and its transportation
were not found to be - In violation of FAR cost principles
- In violation of Cost Accounting Standard (CAS)
- In violation of any prime contract term
- In violation of any Task Order term
- Fraudulent
- The result of willful management misconduct
33Fuel truck staging at Habur border in Turkey
34Fuel truck staging at Habur border in Turkey
35Task Order 6 and the Crossing at the Al-Fatah
Bridge
- Bridge destroyed during combat operations in
April 2003 - Severed all flow of petroleum products across the
Tigris River - Bridge again attacked on October 18, 2005 when
insurgents bombed temporary pipelines strung
across bridge
36Al-Fatah Bridge after aerial bombing
37Task Order 6 Deliverables excerpts from contract
- The Al-Fatah Bridge crossing
- The task envisioned under this task order
is to construct a new, pipeline-only bridge
across the river or to tunnel under the river.
The deciding factors for this decision will be
time in as much as the economic impact is
stated above. - The three canal crossings
- . The effort under this task order consists
of design and construction of three horizontal,
directionally drilled crossings at the Kirkuk
Irrigation Canal, the Riyadh Access Road and
Irrigation Canal and the Zegeton River crossing.
- The Emergency Back-up Generators
- . . . coordinate with MOO and ACO to
develop a plan to procure and install emergency
back up generation capacity at designated key
infrastructure locations as directed by the ACO.
38Task Order 6 (continued) The Crossing at
Al-Fatah
- Decision to tunnel under the river using HDD made
by senior oil advisors to CPA and Iraq Ministry
of Oil - HDD drilling of tunnels for 15 pipelines selected
because of - Speed
- Security
- Permanence
- Cost
- Successfully installed only six pipelines (out of
15) (28 of desired throughput) - 26-inch crude oil pipeline
- 24-inch dry gas pipeline
- 14-inch LPG (sour gas) pipeline
- 12-inch refined product pipeline
- 16-inch fuel gas line
- 8-inch natural gas line
39Task Order 6 (continued) The Crossing at
Al-Fatah
- Project completed by PIJV using U.S.
appropriations - Constructed by excavating trench across the
river, installing the pipeline (encased in
concrete coating), and covering it with gravel. - Nine large diameter pipelines installed
- 14-inch LPG line
- 20-inch crude oil line
- 30-inch crude oil line
- 32-inch crude oil line
- 40-inch crude oil line
- four spare pipelines (8-inch, 12-inch, 16-inch
and 20-inch)
40Task Order 6 (continued) Canal Crossings
- KBR scope of work for canal crossings terminated
in August 2004 - Project awarded by PCO to PIJV in November 2004
using U.S. appropriations - Kirkuk canal crossing completed by PIJV
- Zegeton and Riyadh canal crossings completed by
subcontractor from the Republic of Georgia,
TriQuest International Group, Ltd. - All canal crossings require weld testing before
being placed into operation. - Remaining work to be completed on 40-inch
pipeline includes inspection and repair (as
necessary) of 14 welds, cleaning and testing, at
which time it will be commissioned
41Task Order 6 (continued) Back-up Generators
- 10 GE 18 MW TM500 gas turbine generators
- 2 GE 10 MW gas turbine generator
- 1 Pratt Whitney FT8 TwinPak gas turbine
generator - 34 miscellaneous diesel generators (1 MW) for SOC
- 6 diesel generators, switchgear and day tanks
installed at Um Qasar and Al Nasiryah. - 2 diesel generators leased and installed at Az
Zubair and Al Fao.
42North Rumaila CPS 1, 2 3 TM-2500
CPS 1 TM-2500
CPS 2 TM-2500
CPS 3 TM-2500
43South Rumaila CPS 6, 7, 8 9 TM-2500
CPS 7 TM-2500
CPS 6 TM-2500
CPS 9 TM-2500
CPS 8 TM-2500
TM-2500 Jeep
44Qarmat Ali 2 ea. TM-2500
45