An Introduction to our - PowerPoint PPT Presentation

About This Presentation
Title:

An Introduction to our

Description:

Hazardous job-site conditions at canal crossings (Kirkuk, Riyadh, Zegeton) ... Zegeton and Riyadh canal crossings completed by subcontractor from the Republic ... – PowerPoint PPT presentation

Number of Views:109
Avg rating:3.0/5.0
Slides: 46
Provided by: john156
Category:

less

Transcript and Presenter's Notes

Title: An Introduction to our


1
Report of Agreed Upon Procedures for the
International Advisory and Monitoring
Board Regarding the Task Force Restore Iraqi
Oil Contract Settlement between the U.S. Army
Corps of Engineers and Kellogg, Brown, Root
October 30, 2006
An Introduction to our Forensic Services
Practice
2
Summary of Agreed-Upon Procedures Report
  • Report of Agreed-Upon Procedures regarding
  • The Contract Settlement between
  • the U.S. Army Corps of Engineers
  • and Kellogg, Brown Root
  • related to the
  • Task Force Restore Iraqi Oil Project
  • for
  • U.S. Defense Reconstruction Support Office
  • and
  • International Advisory and Monitoring Board
  • By
  • Crowe Chizek and Company LLC
  • October 20, 2006

3
The KBR contract with theUS Corps of Engineers
(USACE)
  • Contract number DACA63-03-D-0005
  • Task Force Restore Iraqi Oil (TF RIO) contract
  • Awarded to KBR on March 8, 2003
  • Contracting Agency Southwestern Division of
    USACE
  • Cost-plus-award-fee contract
  • Period of Performance Base period of 2 years,
    plus 3 one-year options
  • Base Fee 2 Award Fee Up to 5
  • Ten Task Orders (T.O.s)
  • T.O.s 1 - 4 and part of 5 funded from U.S.
    appropriations
  • T.O.s 6 - 10 and most (82) of 5 funded from
    DFI funds
  • T.O.s 5 - 10 closed out as of December 31, 2005

4
Task Orders under the KBR TF RIO contract
  • Training/advice for oil spill response equipment
    pre-positioning
  • Design and specifications for quick repair of
    critical oil facilities
  • Safe shutdown and damage assessment oil well
    fire fighting and repairs
  • Base camp facilities (3) and life support for TF
    RIO and KBR personnel
  • Funded by DFI
  • Import and distribute refined fuel products
  • Restore essential oil infrastructure
  • Import and distribute refined fuel products
  • Import and distribute refined fuel products
  • Import and distribute refined fuel products
  • Import and distribute refined fuel products

5
The Environment of Contract Performance (March
2003 August 2004)
  • War-time conditions throughout Iraq
  • Exposure of fuel truck convoys to ambush, sniper
    fire, roadside bombs, and rocket-propelled
    grenades
  • Difficulty in obtaining military escorts for
    convoys from Kuwait
  • Refusal of Turkish drivers to deliver fuel to
    Baghdad
  • 85 casualties among KBR employees and contractors
    including 21 fatalities
  • Hazardous job-site conditions at Al-Fatah Bridge
    crossing of Tigris River
  • Hazardous job-site conditions at canal crossings
    (Kirkuk, Riyadh, Zegeton)

6
Environment (continued) Task Orders 5, 7-10 -
Humanitarian Fuel Mission
  • Utmost urgency to supply refined fuel products
  • Absence of long-term commitments in fuel supply
    mission due to
  • Uncertain requirements and duration of fuel
    supply mission
  • (Initial requirement for only 21 days supply)
  • Sporadic and uncertain funding of fuel supply
    mission
  • (21 modifications to Task Order 5)
  • Insurgent activity
  • Only one fuel supplier in Kuwait (Altanmia)
    authorized by Kuwait Petroleum Company (KPC)
  • Insufficient number of fuel trucks in Kuwait

7
Environment (continued) - Task Order 6 Oil
infrastructure projects
  • Urgency to restore oil infrastructure as quickly
    as possible to supply
  • Crude oil for export to generate revenue
  • Refined product for domestic consumption
  • Lack of construction site base camp at Al-Fatah
    Bridge to commence work
  • Dangerous security situation at Al-Fatah and
    three canal crossings
  • Geological complexities at Al-Fatah Bridge site
    hampering HDD drilling, particularly for large
    boreholes
  • Unstable electrical power - demand for back-up
    power generation

8
Total Payments under Task Orders 5 - 10
Task Order Reimbursed Direct Costs Indirect Costs Base Fee Award Fee Total
5 812,146,070 16,632,274 15,683,246 26,661,519 871,123,109
6 196,429,125 4,511,831 3,880,000 388,000 205,208,956
7 298,028,401 6,829,623 5,741,741 9,760,959 320,360,724
8 164,092,535 3,760,353 3,071,573 5,221,673 176,146,134
9 50,562,450 1,158,709 758,285 1,289,086 53,768,530
10 25,356,608 581,082 320,952 545,618 26,804,260
Total 1,546,615,189 33,473,872 29,455,797 43,866,855 1,653,411,713
As of Total 94 2 2 3 100
9
Total Payments for Task Orders 5 -10 funded by DFI
Task Order Reimbursed Direct Costs Indirect Costs Base Fee Award Fee Total
5 667,151,571 13,662,872 12,883,277 21,901,570 715,599,290
6 196,429,125 4,511,831 3,880,000 388,000 205,208,956
7 298,028,401 6,829,623 5,741,741 9,760,959 320,360,724
8 164,092,535 3,760,353 3,071,573 5,221,673 176,146,134
9 50,562,450 1,158,709 758,285 1,289,086 53,768,530
10 25,356,608 581,082 320,952 545,618 26,804,260
Total 1,401,620,690 30,504,470 26,655,828 39,106,906 1,497,887,894
As of Total 94 2 2 3 100
10
Snapshot of Completion Status
  • Oil supply mission (T.O. 5, 7-10)
  • Mission completed (May 2003 March 2004)
  • Fuel supply commitment transferred to DESC in
    April 2004
  • Oil infrastructure mission (T.O. 6)
  • HDD drilling of 15 pipelines at Al-Fatah
  • KBR completed 6 pipelines (28 of throughput)
    across Tigris River
  • PIJV completed remainder up-stream (U.S.
    appropriations)
  • Canal crossings completed by PIJV (U.S.
    appropriations)
  • Back-up Power Generators all delivered and
    installed
  • 12 GE TM500 gas turbine generators
  • One Pratt Whitney FT8 Twin-Pak gas turbine
    generator
  • 42 diesel generators for SOC and other locations

11
Snapshot of Completion Status (continued)
  • Settlement negotiations concluded on December 22,
    2005
  • DCAA questioned 208 million of incurred costs,
    but no recommendation to withhold reimbursement
    of questioned costs
  • Disallowed 3.8 million of costs related to
    diesel fuel transportation from Kuwait
  • KBR waived claim for 5.4 million in interest
  • Excluded 108 million (52) of 208 million in
    questioned costs from fee pool (37 million
    impact on potential award fee)

12
A Follow-on Procedure to SIGIR Engagement
  • SIGIR Agreed-upon Procedure Report September 30,
    2005
  • Major Findings in SIGIR report
  • The non-competitive award to KBR was properly
    justified
  • T.O. 5 costs were definitized and determined to
    be fair and reasonable
  • T.O.s 6 10 had not yet been definitized
  • Appropriate justification for the contract
    (signed by the
  • Assistant Secretary of the Army)
  • Goods and services received and paid for with DFI
    funds were provided for in contract
  • Total amount of DFI funds disbursed did not
    exceed the amount obligated for the contract

13
Our Scope of Work
  • Focus on Task Orders 5 10 of the KBR contract
  • (i) Review the Settlement between KBR and
    USACE
  • Review the Work Performed by DCAA
  • Confirm Physical Existence of Deliverables
    under
  • Task Order 6

14
Scope of Work Detailed Procedures
  • (i) Review Settlement between KBR and USACE
  • Provide a summary of the salient terms of the
    settlement, including the disposition of costs
    previously questioned by the DCAA and summarized
    in the September 2005 SIGIR report.
  • Comment on the reasonableness and basis for the
    settlement.
  • Compare the processes and procedures for contract
    reconciliation and settlement of
    non-competitively awarded KBR RIO contract
    actions using DFI funds with the processes and
    procedures for contract reconciliation and
    settlement of non-competitively awarded KBR RIO
    contract actions using U.S. appropriated funds.
  • Document the procedures undertaken by the USACE
    contracting officer to establish that goods were
    delivered and services were rendered for each of
    the six task orders of the KBR RIO contract.
  • Show how the management and performance award
    commission fees were calculated.
  • Obtain and summarize the terms for indirect
    costs, including overheads.

15
Scope of Work Detailed Procedures (continued)
  • (ii) Review Work Performed by DCAA
  • Obtain the contract files and review for
    completeness.
  • Obtain evidence that the contracting procedures
    were followed.
  • Perform a review of the reasonableness of the
    price of imported fuel products compared to other
    sources, for example, the prices charged to the
    CPA or U.S. forces in Iraq at that time.
  • Where no comparable price is available, assess
    the markup taking into account the wartime
    conditions.
  • Obtain evidence that the goods were delivered and
    the services were rendered in terms of quality
    and quantity in accordance with the terms of the
    relevant task order under the KBR RIO contract.
  • Determine by review of the agreement with the
    contractor that payments were properly justified.

16
Scope of Work Detailed Procedures (continued)
  • (iii) Confirm Physical Existence of Deliverables
    under Task Order 6.

17
Primary Sources of Information
  • From US Army Corps of Engineers (USACE)
  • KBR contracts and subcontracts
  • Task Orders and modifications
  • Price Negotiation Memoranda (PNM) prepared by the
    Corps
  • Administrative Contracting Officer
  • Procurement and accounting documentation
  • Interviews of USACE staff
  • Written statements of USACE staff
  • Correspondence and other materials

18
Primary Sources of Information (continued)
  • From Defense Contract Audit Agency (DCAA)
  • DCAA Audit Reports on each Task Order
  • Audit Workpapers
  • Financial analyses in support of contract
    negotiations by the USACE contracting officer
  • DCAA audit manuals
  • Interviews of DCAA staff
  • Correspondence and other materials

19
Primary Sources of Information (continued)
  • From Special Inspector General for Iraq
    Reconstruction (SIGIR)
  • SIGIR audit reports and special assessment
    reports
  • Workpapers in support of reports
  • Interviews of SIGIR staff

20
Primary Sources of Information (continued)
  • From Defense Energy Support Center (DESC)
  • Refined product pricing data
  • Interviews of DESC staff

21
Primary Sources of Information (continued)
  • From Kellogg, Brown Root (KBR)
  • KBR project accounting documentation
  • Correspondence pertaining to contract and task
    orders
  • Fuel supply data and correspondence
  • Horizontal Directional Drilling (HDD) subcontract
    information
  • Back-up generator information
  • Interviews of KBR staff

22
Results of Procedures
  1. Review Settlement between KBR and USACE
  2. Review Work Performed by DCAA
  3. Confirm Physical Existence of Task Order 6
    Deliverables

23
Results (i) Review Settlement between KBR and
USACE
  • Reviewed the terms of settlements for Task Orders
    5 through 10
  • Evaluated the basis and reasonableness of
    settlement based on
  • Negotiated terms of these settlements (costs and
    fees)
  • Related supporting documentation, including Price
    Negotiation Memoranda
  • Procedures followed by USACE and its Award Fee
    Evaluation Board
  • DCAA audit reports and procedures undertaken in
    auditing prices and costs as contained in work
    papers
  • Interviews with cognizant USACE, DCAA, SIGIR,
    DESC, and KBR personnel
  • Determined that the settlements were reasonable

24
Results (i) Review Settlement between KBR and
USACE(continued)
  • Reviewed documentation regarding determination of
    base and award fees including review of
    procedures followed by DCAA, the USACE
    contracting officer and the USACE Award Fee
    Evaluation Board
  • Recomputed base and award fees
  • Reviewed documentation regarding the terms for
    indirect costs, including overhead and GA
  • Recomputed indirect costs based on contractual
    overhead and GA rates

25
Results (ii) Review Work Performed by DCAA
  • Determined that contract files were complete and
    that contracting procedures were followed
  • Reviewed DCAA audit reports, audit procedures,
    supporting work papers and memoranda to USACE.
    Interviewed DCAA, USACE and KBR personnel
    regarding DCAA procedures.
  • Reviewed price of imported fuel products, and
    transportation, in the context of wartime
    conditions and assessed comparability to costs
    incurred by DESC commencing April 2004
  • Reviewed process of obtaining bids from qualified
    vendors
  • Reviewed evidence that goods were delivered and
    services rendered in accordance with the terms of
    task orders
  • Determined that payments were properly justified.

26
Results (iii) Confirm Physical Existence of
T.O. 6 Deliverables
  • Key Task Order 6 deliverables
  • HDD pipeline crossing at Al-Fatah Bridge over the
    Tigris River
  • Pipeline crossings at three canals (Kirkuk,
    Riyadh and Zegeton)
  • Back-up gas turbine and diesel generators
  • Conducted interviews with personnel and reviewed
    extensive documentation from
  • USACE
  • DCAA
  • SIGIR
  • KBR
  • U.S. State Dept.
  • Reviewed accounting documentation confirming
    delivery
  • Reviewed photographic evidence confirming
    delivery

27
Determining Reasonableness (per FAR 31.2013)
  • (a) A cost is reasonable if, in its nature and
    amount, it does not exceed that which would be
    incurred by a prudent person in the conduct of
    competitive business . . .
  • (b) What is reasonable depends upon a variety of
    considerations and circumstances, including --
  • (1) Whether it is the type of cost generally
    recognized as ordinary and necessary for the
    conduct of the contractors business or the
    contract performance
  • (2) Generally accepted sound business practices,
    arms-length bargaining, and Federal and State
    laws and regulations
  • (3) The contractors responsibilities to the
    Government, other customers, the owners of the
    business, employees, and the public at large and
  • (4) Any significant deviations from the
    contractors established practices.

28
Factors supporting reasonableness of payments for
Task Orders 5, 7-10
  • The contracting process by USACE was consistent
    with US government contracting procedures for
    cost reimbursement contracts
  • The DCAA followed its standard audit procedures
  • Reviewed interim payment vouchers from KBR
    (together with USACE)
  • Provided provisional approval for payments
    subject to later audit
  • Sought additional information from KBR
  • Audited incurred costs
  • Audited indirect costs based on negotiated
    contractual rates
  • Prepared audit reports
  • Provided advice to contracting agency (USACE) in
    settling contract

29
Factors supporting reasonableness of payments for
Task Orders 5, 7-10 (continued)
  • Certain costs were questioned by the DCAA (176
    million for fuel supply task orders 32 million
    for T.O. 6 )
  • Questioned costs were incurred for the benefit of
    the mission
  • Questioned costs are not necessarily disallowable
    costs
  • Questioned costs are costs incurred by a
    contractor that DCAA recommends for further
    consideration by the contracting officer
  • Neither the DCAA proposal audits nor its
    financial advice to the contracting officer
    included not reimbursing KBRS for the large
    majority of the costs it had incurred in
    executing the mission. DCAA did not issue a Form
    1, Notice of Costs Suspended and/or Disapproved
    under Cost Reimbursement Contracts

30
Factors supporting reasonableness of payments for
Task Orders 5, 7-10 (continued)
  • The prices of fuel products and related
    costs of transportation into Iraq in these
    wartime conditions were a reflection of existing
    market conditions.
  • Multiple bids received on May 5, 2003 from Kuwait
    vendors
  • Altanmia, Maar Specialties, and Elafco General
    Trading
  • Altanmia was the low bidder and offered best
    terms and
  • plan for fuel delivery
  • Additional bids sought on May 7, 2003
  • Altanmia, Jassim Transport and Stevedoring
    Company,
  • Mohammed Al-Mojil Group, American United and
    SABA
  • Altanmia again offered best terms
  • Altanmia had exclusive right from KPC to purchase
    and distribute fuel

31
Factors supporting reasonableness of payments for
Task Orders 5, 7-10 (continued)
  • DCAA proposed comparison to DESC for
    transportation costs as a reliable benchmark for
    assessing Altanmias costs
  • Both USACE Contracting Officer and DESC
    disagreed
  • DESC was funded for 3 months up-front, making it
    easier for contract negotiation
  • DESC benefited from KBR experience and lessons
    learned
  • Contractors had trucks in place when DESC took
    over. Start-up costs were covered
  • KPC dealt directly with DESC (as a U.S.
    government entity)
  • Producer relationships in place with DESC to
    support military requirements. KBR lacked DESCs
    expertise in contracting for fuels
  • Expense of insurance coverage not required for
    DESC contractors
  • DESC used economic price adjustment in contracts

32
Factors supporting reasonableness of payments for
Task Orders 5, 7-10 (continued)
  • USACE determined prices and transportation costs
    to be reasonable (from PNM for T.O. 5)
  • The government will not refuse to pay KBRS the
    actual incurred costs that have been questioned
    in DCAA audits based on
  • A comparison of prices paid for transportation of
    fuel from Kuwait to prices paid for fuel from
    Turkey or
  • A comparison of prices paid for transportation of
    fuel and the prices paid by DESC
  • Costs incurred for fuel and its transportation
    were not found to be
  • In violation of FAR cost principles
  • In violation of Cost Accounting Standard (CAS)
  • In violation of any prime contract term
  • In violation of any Task Order term
  • Fraudulent
  • The result of willful management misconduct

33
Fuel truck staging at Habur border in Turkey
34
Fuel truck staging at Habur border in Turkey
35
Task Order 6 and the Crossing at the Al-Fatah
Bridge
  • Bridge destroyed during combat operations in
    April 2003
  • Severed all flow of petroleum products across the
    Tigris River
  • Bridge again attacked on October 18, 2005 when
    insurgents bombed temporary pipelines strung
    across bridge

36
Al-Fatah Bridge after aerial bombing
37
Task Order 6 Deliverables excerpts from contract
  • The Al-Fatah Bridge crossing
  • The task envisioned under this task order
    is to construct a new, pipeline-only bridge
    across the river or to tunnel under the river.
    The deciding factors for this decision will be
    time in as much as the economic impact is
    stated above.
  • The three canal crossings
  • . The effort under this task order consists
    of design and construction of three horizontal,
    directionally drilled crossings at the Kirkuk
    Irrigation Canal, the Riyadh Access Road and
    Irrigation Canal and the Zegeton River crossing.
  • The Emergency Back-up Generators
  • . . . coordinate with MOO and ACO to
    develop a plan to procure and install emergency
    back up generation capacity at designated key
    infrastructure locations as directed by the ACO.

38
Task Order 6 (continued) The Crossing at
Al-Fatah
  • Decision to tunnel under the river using HDD made
    by senior oil advisors to CPA and Iraq Ministry
    of Oil
  • HDD drilling of tunnels for 15 pipelines selected
    because of
  • Speed
  • Security
  • Permanence
  • Cost
  • Successfully installed only six pipelines (out of
    15) (28 of desired throughput)
  • 26-inch crude oil pipeline
  • 24-inch dry gas pipeline
  • 14-inch LPG (sour gas) pipeline
  • 12-inch refined product pipeline
  • 16-inch fuel gas line
  • 8-inch natural gas line

39
Task Order 6 (continued) The Crossing at
Al-Fatah
  • Project completed by PIJV using U.S.
    appropriations
  • Constructed by excavating trench across the
    river, installing the pipeline (encased in
    concrete coating), and covering it with gravel.
  • Nine large diameter pipelines installed
  • 14-inch LPG line
  • 20-inch crude oil line
  • 30-inch crude oil line
  • 32-inch crude oil line
  • 40-inch crude oil line
  • four spare pipelines (8-inch, 12-inch, 16-inch
    and 20-inch)

40
Task Order 6 (continued) Canal Crossings
  • KBR scope of work for canal crossings terminated
    in August 2004
  • Project awarded by PCO to PIJV in November 2004
    using U.S. appropriations
  • Kirkuk canal crossing completed by PIJV
  • Zegeton and Riyadh canal crossings completed by
    subcontractor from the Republic of Georgia,
    TriQuest International Group, Ltd.
  • All canal crossings require weld testing before
    being placed into operation.
  • Remaining work to be completed on 40-inch
    pipeline includes inspection and repair (as
    necessary) of 14 welds, cleaning and testing, at
    which time it will be commissioned

41
Task Order 6 (continued) Back-up Generators
  • 10 GE 18 MW TM500 gas turbine generators
  • 2 GE 10 MW gas turbine generator
  • 1 Pratt Whitney FT8 TwinPak gas turbine
    generator
  • 34 miscellaneous diesel generators (1 MW) for SOC
  • 6 diesel generators, switchgear and day tanks
    installed at Um Qasar and Al Nasiryah.
  • 2 diesel generators leased and installed at Az
    Zubair and Al Fao.

42
North Rumaila CPS 1, 2 3 TM-2500
CPS 1 TM-2500
CPS 2 TM-2500
CPS 3 TM-2500
43
South Rumaila CPS 6, 7, 8 9 TM-2500
CPS 7 TM-2500
CPS 6 TM-2500
CPS 9 TM-2500
CPS 8 TM-2500
TM-2500 Jeep
44
Qarmat Ali 2 ea. TM-2500
45
  • Questions ?
Write a Comment
User Comments (0)
About PowerShow.com