Title: Operations Management (MD021) Project Management Agenda
1Operations Management(MD021)
2Agenda
- Projects and Project Management
- Tools and Technologies
- Network Diagrams
- Deterministic Time Estimates
- Project Crashing
- Probabilistic Time Estimates
- Risk Management
3Projects and Project Management
4Projects
- Projects are unique, one-time operations designed
to accomplish a specific set of objectives in a
limited time frame.
5The Life Cycle of Projects
6Project Management
- Project Management involves tasks of managing a
project throughout its life cycle from its
inception through to its completion - Often a team-based approach in companies
- How is it different?
- Limited time frame
- Narrow focus, specific objectives
- Less bureaucratic
- Why is it used?
- Special needs
- Pressures for new or improved products or services
7Project Management takes place across the Project
Life Cycle
8Project Management
- What are the Key Metrics?
- Time
- Cost
- Performance objectives
- What are the Key Success Factors?
- Top-down commitment
- Having a capable project manager
- Having time to plan
- Careful tracking and control
- Good communications
9Project Management
- What are the Major Administrative Issues?
- Executive responsibilities
- Project selection
- Project manager selection
- Organizational structure
- Organizational alternatives
- Manage within functional unit
- Assign a coordinator
- Use a matrix organization with a project leader
10Key Decisions
- Deciding which projects to implement
- Selecting a project manager
- Selecting a project team
- Planning and designing the project
- Managing and controlling project resources
- Deciding if and when a project should be
terminated
11Key Decisions
- Which project(s) to implement?
- Sometimes obvious whatever managers tell you to
do - Some companies have multiple, concurrent projects
that they must decide between - Selecting a project manager?
- Typically good to select someone with
professional experience in managing projects - Companies, however, often just assume that any
manager can manage a project leading to BAD
results
12Project Manager typically should be skilled at
managing projects
Work Quality Human Resources Time Communicat
ions Costs
13Key Decisions
- Selecting the Project Team?
- Managers often allocate their MEDIOCRE employees
to projects - In contrast, for success, project manager needs
to have BEST people on project - Planning/Designing/Managing/Controlling project?
- Many, many different techniques, tools,
strategies - Terminate the project?
- Sometimes, no matter how much money you sink in,
a project will never be successful. - Managers have a horrible tendency to be
optimistic about completion also, it is their
butt that will get fired if project fails - Need to kill a failing project as soon as
possible saves the wasting of any more money
14Ethical Issues in Project Management
- Temptation to understate costs
- Temptation to withhold information
- to get project approved
- to keep project from being terminated
- Misleading status reports
- Falsifying records
- Comprising workers safety
- Approving substandard work
15Tools and Technologies for Project Management
16Tools and Technologies
- What are the tools?
- Gantt charts
- Work breakdown structure
- Network diagram
- Risk management
- Technologies?
- Software packages
17Technology for Managing Projects
- Computer aided design (CAD)
- modeling/diagramming/flowcharting
- Groupware (Lotus Notes, Groove)
- team collaboration
- Project management software
- CA Super Project
- Harvard Total Manager
- MS Project
- Sure Track Project Manager
- Time Line
18Advantages of PM Software
- Imposes a methodology
- Provides logical planning structure
- Enhances team communication
- Flag constraint violations
- Automatic report formats
- Multiple levels of reports
- Enables what-if scenarios
- Generates various chart types
19Gantt Charts are often used in project planning
and scheduling
20Gantt Chart in MS Project
21Work Breakdown Structure
22Work Breakdown Structure
23Network Diagrams
24PERT and CPM
- PERT Program Evaluation and Review Technique
- CPM Critical Path Method
- Graphically displays project activities
- Estimates how long the project will take
- Indicates most critical activities
- Show where delays will not affect project
25Advantages of PERT
- Forces managers to organize
- Provides graphic display of activities
- Identifies
- Critical activities
- Slack activities
26Limitations of PERT
- Important activities may be omitted
- Precedence relationships may not be correct
- Estimates may include a fudge factor
- May focus solelyon critical path
27The Network Diagram
- Network (precedence) diagram
- Activity-on-arrow (AOA)
- Activity-on-node (AON) WE COVER THIS ONLY
- Activities
- project steps that consumer resources and/or time
- Events
- starting and finishing of activities
28The Network Diagram (contd)
- Path
- Sequence of activities that leads from the
starting node to the finishing node - Critical path
- The longest path determines expected project
duration - Critical activities
- Activities on the critical path
- Slack
- Allowable slippage for path the difference the
length of path and the length of critical path
29Project Network Activity on Node
AON
30Deterministic Time Estimates
31Time Estimates
- Deterministic
- Time estimates that are fairly certain
- Probabilistic
- Estimates of times that allow for variation
32Example of Deterministic Task Times (AON)
Completion Time? Critical Path? Slack Times
along Non-Critical Path(s)?
33Example of Solution for Deterministic Times
34Algorithm for identifying project completion
time, critical path, slack time
- Network activities
- ES Early Start earliest time an activity can
start - EF Early Finish earliest time an activity can
finish - LS Late Start latest time an activity can
start - LF Late Finish latest time an activity can
finish - Used to determine
- Expected project duration
- Slack time
- Critical path
35Forward/Backward Method
- Forward Pass
- Start at left side of diagram
- For each beginning activity, ES 0
- For each activity, ES activity time EF
- For the following activity, ES EF of preceding
activity - Or, if multiple preceding activities, ES
maximum(EFs of all preceding activities)
- Backward Pass
- Start at right side of diagram
- Use the largest EF as the LF for all ending
activities - For each activity, LS LF activity time
- For the preceding activity, LF LS of following
activity - Or, if multiple immediately following
activities,LF minimum(LSs of all following
activities)
36Solving an AON project network
37Project Crashing
38Project Crashing
- Crashing a project involves paying more money to
complete a project more quickly. - Since the critical path determines the length of
a project, it makes sense to reduce the length of
activities on the critical path. - CP activities should be reduced until the project
is reduced to the desired length or you are
paying more per day than you save. - If you have multiple CPs, they should be
shortened simultaneously.
39Time-cost Trade-offs Crashing
- Crash shortening activity duration
- Procedure for crashing
- Crash the project one period at a time
- Only an activity on the critical path
- Crash the least expensive activity
- Multiple critical paths find the sum of crashing
the least expensive activity on each critical
path
40Example of Crashing
13 b
6 a
S
F
5 c
Activity Normal Time Crash Time
Cost/Day to Crash
a 6
5 100 b
13 5
400 c
5 4
300
Critical Path (a,b) Normal completion time
19 Cost(18 days) 100 Cost(17 days)
500 Cost(16 days) 900 Cost(10 days) 3300
41Probabilistic Time Estimates
42Probabilistic Time Estimates Involve a
Distribution of Times
Typically, we assume that times follow a Beta
probability distribution function
43Probabilistic Time Estimates
- Optimistic time
- Time required under optimal conditions
- Pessimistic time
- Time required under worst conditions
- Most likely time
- Most probable length of time that will be required
44Expected Time
te expected time to optimistic time tm most
likely time tp pessimistic time
45Variance of Time
?2 variance to optimistic time tp
pessimistic time
46Example Using Probabilistic Time Estimates (AON)
Optimistic time
Most likely time
Pessimistic time
2-4-6 b
2-3-5 c
1-3-4 a
3-5-7 e
5-7-9 f
3-4-5 d
S
F
4-6-8 h
3-4-6 i
2-3-6 g
47Path Probabilities
Z indicates how many standard deviations of the
path distribution the specified tine is beyond
the expected path duration.
48Example Using Probabilistic Time Estimates (AON)
2-3-4 b
3-4-5 a
S
F
Task a te (3 4(4) 5)/6 24/6 4
Length of Path (a,b) 4 3 7
Task b te (2 4(3) 4)/6 18/6 3
Task a s2act (5-3)2/36 4/36
s2Path (a,b) 4/36 4/36 8/36
Task b s2act (4-2)2/36 4/36
sPath (a,b) sqrt(8/36) 0.471
Question Can we complete this project by Period
8?
ProbComplete by period 8 0.983
Z (8 7)/0.471 2.12
49Risk Management
50Project Risk Management
- Risk occurrence of events that have undesirable
consequences - Delays
- Increased costs
- Inability to meet specifications
- Project termination
51Risk Management
- Identify potential risks
- Analyze and assess risks
- Work to minimize occurrence of risk
- Establish contingency plans