Solutions to Chapter 12 Exercises - PowerPoint PPT Presentation

1 / 30
About This Presentation
Title:

Solutions to Chapter 12 Exercises

Description:

Solutions to Chapter 12 Exercises Exercise 1 There are four paths: A-C-I (7 days) A-D-G-J (13 days) B-E-G-J (11 days) B-F-H-J (10 days) Thus, the critical path is A-D ... – PowerPoint PPT presentation

Number of Views:229
Avg rating:3.0/5.0
Slides: 31
Provided by: businessF4
Category:

less

Transcript and Presenter's Notes

Title: Solutions to Chapter 12 Exercises


1
Solutions to Chapter 12 Exercises

2
Exercise 1
  • There are four paths
  • A-C-I (7 days)
  • A-D-G-J (13 days)
  • B-E-G-J (11 days)
  • B-F-H-J (10 days)
  • Thus, the critical path is A-D-G-J and these are
    the activities that should be monitored
    most closely because if they slip, the entire
    project will be delayed.

3
Exercise 1 concluded
  • The time to complete the four paths is now
  • A-C-I (5.5 days)
  • A-D-G-J (11.5 days)
  • B-E-G-J (12.5 days)
  • B-F-H-J (11.5 days)
  • The critical path is now B-E-G-J and the project
    completion is expected to be 12.5 days.
  • Activities G and J remain as critical activities
    while A and D are no longer critical.

4
Exercise 2
5
Exercise 2 Path Slacks
  • Path A-C-I Slack 6
  • Path A-D-G-J Slack 0
  • Path B-E-G-J Slack 2
  • Path B-F-H-J Slack 10

6
Exercise 3 Network Diagram
2
6
1
3
7
4
5
7
Exercise 3 Activity Expected Times, Variances
and Standard Deviations
8
Exercise 3 Path Expected Times, Variances, and
Standard Deviations
9
Exercise 3 Probability Project Finishes within
17 Weeks
All paths must be considered since they all have
a reasonable chance of taking longer than 17
weeks. Thus, there is a very small chance (i.e.,
.005) that the project can be completed in 17
weeks or less.
10
Exercise 3 Probability Project Finishes within
24 Weeks
Only paths 1-2-6-7 and 1-3-5-7 need be considered.
However, all paths can be easily included by
simply changing cell B1 from 17 to 24. With all
paths considered, there is a over an 86 chance
of completing the project in 24 weeks.
11
Exercise 3 Should the Project be Pursued?
  • Using the spreadsheet it can be easily determined
    that the probability of finishing within 18 weeks
    is .176 and the probability of the project
    taking 22 weeks or longer is 48.321.
  • The expected value of the project is thus
  • (.176 ? 10,000) (48.321 ? -5,000)
    -2398.40
  • Given the negative expected value, the firm
    should not bid.

12
Exercise 4
The path with the longest expected time is
a-b-dummy-f-h-i 16.
e 3
b 5
i 1
a 3
0
h 3
c 3
g 2
d 1
f 4
13
Exercise 5
14
Exercise 5a continued
15
Exercise 5b continued
16
Exercise 5c concluded
17
Exercise 6
1
6
4
5
9
7
3
2
8
18
Exercise 6 continued
19
Exercise 6 concluded
Path 2-3-4-5-7-8-9 has the longest expected time.
Thus, the project would be expected to take
66.33.
20
Exercise 7
(000)
Plan
Plan
Progress,
40
30
Actual
35
24
20
17
55 70
55 70
Time, Days
Time, Days
21
Exercise 7 concluded
  • Spending variance EC - AC 17,000 - 30,000
    -13,000. This indicates a cost overrun of
    13,000.
  • Schedule variance EC - SC 17,000 - 24,000
    -7,000 indicating the project is behind.
  • Time variance TE - TA 55 -70 -15 days
    indicating a 15 day delay.

22
Exercise 8
(000)
Plan
84
Value
81
Actual
78
1 TE 2 3
Time, Months
23
Exercise 8 concluded
  • Spending variance EC - AC 81,000 - 78,000
    3,000.
  • Schedule variance EC - SC 81,000 - 84,000
    -3,000.
  • TE can be estimated from chart by determining how
    much time should have elapsed according to the
    plan to achieve the current value completed. In
    this case TE is approximately 1.5 months.
  • Thus, the spending variance TE - TA 1.5 - 2
    -0.5 month.

24
Exercise 9
  • Spending variance EC - AC 39,000 - 34,000
    5,000.
  • Schedule variance EC - SC 39,000 - 42,000
    -3,000.

25
Exercise 10a
26
Exercise 10a (concluded)
27
Exercise 10b
  • From the above spreadsheet, the average project
    completion time is 90.33 days with a standard
    deviation of 5.16 days.
  • Across the 100 replications of the simulation
    model, the project finished as quickly as 78.85
    days and took as long as 103.51 days.

28
Exercise 10c
29
Exercise 10d
  • Path A-C-F has an expected duration of 88.8 days
    with a standard deviation of 4.81 days. Based on
    this, the probability that it is completed in 80
    days or less can be calculated as
  • From the z table in the Appendix A, the
    probability of the path being completed in 80
    days or less is 3.51. Alternatively, this can
    be found using Excel as follows
    normdist(80,88.8,4.81,true) 3.37.
    Incidentally, the value found using Excel is
    actually more accurate since rounding the value
    of z was not required.
  • Path B-D-F has an expected duration of 85.2 days
    and standard deviation of 7.31 days. Using Excel
    the probability it is completed in 80 days or
    less is found as normdist(80,85.2,7.31,true)
    23.84.
  • Path B-E has an expected duration of 59.0 days
    and standard deviation of 6.93 days. Using Excel
    the probability it is completed in 80 days or
    less is found as normdist(80,59,6.93,true)
    99.88.
  • The probability the entire project is completed
    in 80 days or less is calculated as
    (.0337)(.2384)(.9988) 0.80

30
Exercise 10e
  • The results shown in the spreadsheet to part a
    are consistent with the probability calculated in
    part d.
  • In only one of the 100 replications was the
    project completed in 80 days or less (i.e., rep
    number 14).
  • One percent of the replications is quite close
    to the 0.8 calculated in part d.
Write a Comment
User Comments (0)
About PowerShow.com