Title: SNS Project Status
1SNS Project Status
- Ernest L. Williams Jr.
- 27 April 2005
- EPICS Collaboration Meeting _at_ SLAC
2Outline
- Installation Status
- Global Systems
- Network
- Timing
- MPS
- CCR
- Accelerator Systems
- Cryogenic Controls
- PPS
- Target Controls
- Operational Improvements
- Issues
- Summary
3The Spallation Neutron Source
- The SNS construction project will conclude in
2006 - At 1.4 MW it will be 8x ISIS, the worlds
leading pulsed spallation source - An upgrade to 3MW has been approved for CD0
planning.
4Communication Infrastructure is nearly complete
- CD4 Fiber Backbone is complete
- Tubes installed for future addition of blown
fiber - Global cables nearing completion
- Ethernet
- Timing
- MPS
- All accelerator cable SROs entered
- CISCO Switch firmware bug found (and fixed)
Fiber Backbone
Cable Infrastructure
5Timing System Installation is Keeping Up
- All IOCs (including NADS)
- Multiple Fixed Rep Rates for RF Systems
- CLO Test Timing Network
- Infrastructure for Diagnostics, LLRF, XFD, and
Power supply groups - Line Synch monitor
- Delivered from BNL
- Setting up test network for XFD Chopper testing
- General Time added to EPICS
- Provides best time from multiple sources
- Assures monotonicity
- Accepted into EPICS Core
- SNS Event Link Monitor
- Event statistics
- Actual Events vs. Scheduled Events
6Number of MPS Inputs has nearly Doubled(170 ?
313)
170
- All linac MPS hardware installed includes 27
new chassis - Copper phased out, using fiber everywhere
- After CD4, corrector PS status will be added
7Operations have moved to the CCR(Central Control
Room in CLO)
- Move took place in February as scheduled
- Two console arcs are complete (ahead of schedule)
- PPS and ODH systems moved (That was the worrisome
part) - Software Development Area in use
- All work planned for FY05 is complete
- Servers are moved to CER (Central
Equipment Room) - TPS also now in the CCR
- Prototype Console moved to Target Control Room
- Upgraded all multi-head OPIs
- Faster processor
- More RAM
- Faster graphics adapter (Matrox G450)
- X-windows and Java Apps have a much better
performance
PPS Equipment
8Linac Controls Installation isKeeping Up with
the Project Schedule
- We have kept up (barely!!) with RF testing, RF
Conditioning, PS testing, cryomodule cool-down,
etc. - Medium-Beta SCL controls mostly complete
- Cryomodule MB1 controls testing remains
- Some warm section vacuum controls testing
remains - Some MPS hardware installation remains
- High-Beta SCL controls approaching completion
- RF, Cryo, Vacuum controls checkout are well
along - Magnet power supply interface checkout has been
integrated with overall power supply checkout - HEBT controls installation in progress
- Automated procedures have helped keep schedule
9Linac LLRF Installation is Keeping Up(This is
the biggest task in terms of numbers and
complexity)
- Number of installed LLRF IOCs 46 (up from 12)
for 80 systems (out of a total of 96
systems) - Configuration automated via scripts, avoiding
inconsistencies between SCL systems - From last ASAC "Add Adaptive feed forward to
firmware if required" - Was required for higher beam current
- Not foreseen in current FCM, so successfully
added to IOC software - recently refined to eliminate parameters that
were hard to tune - Automation of RF ramp-up, warmup, loop closure
- Allowed hands-off recovery from trips on the NC
Linac - Needs adaptation for SCL
- Waveform updates synchronized to timing system
- Allows physics apps to compare data from several
systems for the same beam pulse - Refining overview screens, giving better notice
of trip reasons, active overrides, etc.
10Cryogenic Control System nearly complete!!
tested
- All CHL Controls equipment installed and
- All IOC and PLC programming complete
- CHL Gas Management, Purifier and Warm Compressor
- CHL 2.1K and 4.5K Cold Boxes
- Medium and High Beta Cryomodules
- HEBT Service Building IOC and PLC
- 2K Cold Box Turn-on was automated
- Cryomodules will complete in April
Full RF Power
First Liquid
Cool Down
Warm Up
11The Cryogenic Control System layout
2 Servers
4 OPIs
11 IOCs
17 PLCs
12Ring Controls is ahead of scheduleBNL effort
completed in March
- Handover Plan - Complete and in use (cooling
water and ramping software scope moved to ORNL) - FSDs - Complete, in use and being updated as
needed to keep them as-built - Design - Essentially complete. All drawings and
specs needed are in use for fabrication and
installation and being updated as needed to keep
them as-built - Hardware Fabrication - WBS 1.9 work complete
except for installing 1 PLC for cooling water
skid. WBS 1.5 work complete except for 2 motion
control racks, 2 PLCs for RF, and Vacuum racks - Procurement - All hardware procured except 1 PLC
for water skid and some miscellaneous parts - Cabling - Schedule for Ring and RTBT cables
depends on budget allocations - HEBT Communications cables pulled, being
terminated - HEBT Process control cabling in process
- Software - Vac, BLM, Mag PSC/PSI, HPRF, Beam Dump
TCs ready for handover. All software ready for
field testing by Jun 05 - Test Plans - Drafted for all systems except RF -
Will be updated as needed during installation
13PPS System Installation is keeping up(in spite
of many configuration changes)
- 75 of the PPS controlled devices in the Linac
have been connected - The temporary Linac shielding has been removed
and the Linac has been returned to one segment
for phase 1.3 - PPS remote I/O racks for the HEBT are installed
- Conduit cable for PPS devices installed in HEBT
tunnel - Installation of conduit cable for PPS devices
in Ring tunnel is 100 complete - The PPS control room racks have been relocated to
the CLO CCR as a part of phase 1.3 (SCL
commissioning)
14The Target Instrument PPS are alsothe
responsibility of the Controls Team
- Cable conduit design for target building
complete, installation underway using AIMSI
crafts (beamline 2 and transfer service bay) and
fixed price subcontractor (high bay) - Target PPS equipment design is 85 complete
- Target PPS equipment fabrication is 70 complete
- Equipment installation ramping up as electricians
become available - Instrument PPS design for beamline 2 underway.
Prototype user panel being fabricated
15The number of IOCs has risen dramatically
- 223 IOCs currently on Accelerator Network
- 109 VME / VXI --- vxWorks-based
- 2 Linux-based Soft IOC Servers
- Running 24 Soft IOCs (18 6)
- 90 Intel-Pentium --- Win32-based IOCs (the
NADS) - Wirescanners, Faraday Cups, BPMs, BCMs
- Upgraded control system to EPICS R3.14.7
- Improved reliability in channel access.
- Results in fewer white screens in the control
room. - Upgraded OS for VME/VXI-based IOCs
- vxWorks 5.5.1 (SNS CVS Release SNS07)
- Better network driver and network stack
configuration - Auto-retry on boot-up if boot server is
unavailable. - Better memory management
16Power Supply Group is Routinely UsingAutomated
Testing and Calibration
- Method uses EPICS and so assures end-to-end
testing including control system - Resulted in large schedule reduction one test
instead of two - PS Calibration, current/field mapping and cycling
profiles come from Oracle RDB - 9 SCL IOCs installed, 8 operational
- 1 HEBT IOC installed and operational
17Turn-on and Turn-off of HPRF Systemshas been
automated
State Diagram monitors the process for each HVCM
Overall summary is displayed
18The New Archive Engine is stable and
amany-featured Java Archive Viewer is now in use
- Archives now well organized with central
configuration file and scripts for - generation of directory structure and skeleton
files - start/stop/restart/monitoring of sampling engines
- update of status web page
- email notification of engine status and disk
usage - Currently 11 distinct archives each running one
or more sampling engines (total 25). - (Conventional Facilities, Magnets, RF, Cryo, ...)
- Data rate kept to 2GB/day with occasional peaks
at 4GB/day. - Limiting performance factor is currently neither
CPU nor network but disk I/O. -
- New Java Viewer is stable and many features are
being exploited - Uses XAL Framework
- Web interface available
- Plots actual data in various formats
- Offers absolute and relative request times
- Performs computations, exports data to
spreadsheets - Investigating new uses via command line and web
- Scroll, zoom, legends, titles, multiple plot
styles, arithmetic and boolean operations
19The new Archive Viewer (Chevtsov)has many useful
features
- Relative start/end times "-5 d(ays)" ? "now"
- Multiple value axes
- Tool-tip info for individual data points
- XAL Framework
Support for calculations based on archived
data Export to spreadsheets, progress bar Green
squares in plot launch tool-tips for meta data,
in this case daily restart of sampling engine.
20Database Collaboration with APS has grown(SNS,
APS, SLAC, TRIUMF, BESSY, FNAL, Diamond, PSI)
- IRMIS Integrated Relational Model for Installed
Systems (v1.0 release in April) - Agreed Core Schema describes control system
with three hierarchies - Signal
- Housing
- Power
- Uses the SNS Physics XAL Framework
- Pelaia et al
- RDB synchronized using crawlers
- 106 SNS IOCs successfully crawled
- EPICS versions 3.13.9, 3.14.6, 3.14.7
- 228,270 PVs found
- SCL 112141
- DTLÂ Â Â Â Â 33607Â Â
- CCLÂ Â Â Â Â 27443Â Â
- MEBTÂ Â 10918Â Â
- HEBTÂ Â Â 8074Â Â Â Â
- Crawlers in development for all EPICS clients,
IOCs, edm, Archiver, Alarms, etc.
21Issues
- Increased installation pace.
- RF Processing and installation checkout means
Control Systems Group must provide operational
support. - Hardware/Software Configuration Management is
highly correlated with reliability/availability.
Work is in progress using a RDB, CVS, and good
release control scheme.
22Issues How to manage increasing number of IOCS?
- 223 IOCs currently on Accelerator Network
- 109 VME / VXI --- vxWorks-based
- 2 Linux-based Soft IOC Servers
- Running 24 Soft IOCs (18 6)
- 90 Intel-Pentium --- Win32-based IOCs (the
NADS) - Wirescanners, Faraday Cups, BPMs, BCMs
- Upgraded control system to EPICS R3.14.7
- Improved reliability in channel access.
- Results in fewer white screens in the control
room. - Upgraded OS for VME/VXI-based IOCs
- vxWorks 5.5.1 (SNS CVS Release SNS07)
- Better network driver and network stack
configuration - Auto-retry on boot-up if boot server is
unavailable. - Better memory management
23Issues How to manage increasing number of IOCS?
24Issues How to manage increasing number of IOCS?
25Summary
- Installation is keeping pace
- Required use of more automated configuration and
testing, database use - PPS keeps pace notwithstanding changes
- Cryo controls nearing completion
- Will be ready for SCL commissioning
- Ready to pick up on Ring controls
- Operational Improvements as well
- Automated HPRF turn-on
- Automated 2K Cold Box turn-on
- Improved Archive viewing tools