SNS Project Status - PowerPoint PPT Presentation

About This Presentation
Title:

SNS Project Status

Description:

SNS Project Status Ernest L. Williams Jr. 27 April 2005 EPICS Collaboration Meeting _at_ SLAC Outline Installation Status Global Systems Network Timing MPS CCR ... – PowerPoint PPT presentation

Number of Views:69
Avg rating:3.0/5.0
Slides: 26
Provided by: wwwssrlSl3
Category:
Tags: sns | project | status

less

Transcript and Presenter's Notes

Title: SNS Project Status


1
SNS Project Status
  • Ernest L. Williams Jr.
  • 27 April 2005
  • EPICS Collaboration Meeting _at_ SLAC

2
Outline
  • Installation Status
  • Global Systems
  • Network
  • Timing
  • MPS
  • CCR
  • Accelerator Systems
  • Cryogenic Controls
  • PPS
  • Target Controls
  • Operational Improvements
  • Issues
  • Summary

3
The Spallation Neutron Source
  • The SNS construction project will conclude in
    2006
  • At 1.4 MW it will be 8x ISIS, the worlds
    leading pulsed spallation source
  • An upgrade to 3MW has been approved for CD0
    planning.

4
Communication Infrastructure is nearly complete
  • CD4 Fiber Backbone is complete
  • Tubes installed for future addition of blown
    fiber
  • Global cables nearing completion
  • Ethernet
  • Timing
  • MPS
  • All accelerator cable SROs entered
  • CISCO Switch firmware bug found (and fixed)

Fiber Backbone
Cable Infrastructure
5
Timing System Installation is Keeping Up
  • All IOCs (including NADS)
  • Multiple Fixed Rep Rates for RF Systems
  • CLO Test Timing Network
  • Infrastructure for Diagnostics, LLRF, XFD, and
    Power supply groups
  • Line Synch monitor
  • Delivered from BNL
  • Setting up test network for XFD Chopper testing
  • General Time added to EPICS
  • Provides best time from multiple sources
  • Assures monotonicity
  • Accepted into EPICS Core
  • SNS Event Link Monitor
  • Event statistics
  • Actual Events vs. Scheduled Events

6
Number of MPS Inputs has nearly Doubled(170 ?
313)
170
  • All linac MPS hardware installed includes 27
    new chassis
  • Copper phased out, using fiber everywhere
  • After CD4, corrector PS status will be added

7
Operations have moved to the CCR(Central Control
Room in CLO)
  • Move took place in February as scheduled
  • Two console arcs are complete (ahead of schedule)
  • PPS and ODH systems moved (That was the worrisome
    part)
  • Software Development Area in use
  • All work planned for FY05 is complete
  • Servers are moved to CER (Central
    Equipment Room)
  • TPS also now in the CCR
  • Prototype Console moved to Target Control Room
  • Upgraded all multi-head OPIs
  • Faster processor
  • More RAM
  • Faster graphics adapter (Matrox G450)
  • X-windows and Java Apps have a much better
    performance

PPS Equipment
8
Linac Controls Installation isKeeping Up with
the Project Schedule
  • We have kept up (barely!!) with RF testing, RF
    Conditioning, PS testing, cryomodule cool-down,
    etc.
  • Medium-Beta SCL controls mostly complete
  • Cryomodule MB1 controls testing remains
  • Some warm section vacuum controls testing
    remains
  • Some MPS hardware installation remains
  • High-Beta SCL controls approaching completion
  • RF, Cryo, Vacuum controls checkout are well
    along
  • Magnet power supply interface checkout has been
    integrated with overall power supply checkout
  • HEBT controls installation in progress
  • Automated procedures have helped keep schedule

9
Linac LLRF Installation is Keeping Up(This is
the biggest task in terms of numbers and
complexity)
  • Number of installed LLRF IOCs 46 (up from 12)
    for 80 systems (out of a total of 96
    systems)
  • Configuration automated via scripts, avoiding
    inconsistencies between SCL systems
  • From last ASAC "Add Adaptive feed forward to
    firmware if required"
  • Was required for higher beam current
  • Not foreseen in current FCM, so successfully
    added to IOC software
  • recently refined to eliminate parameters that
    were hard to tune
  • Automation of RF ramp-up, warmup, loop closure
  • Allowed hands-off recovery from trips on the NC
    Linac
  • Needs adaptation for SCL
  • Waveform updates synchronized to timing system
  • Allows physics apps to compare data from several
    systems for the same beam pulse
  • Refining overview screens, giving better notice
    of trip reasons, active overrides, etc.

10
Cryogenic Control System nearly complete!!
tested
  • All CHL Controls equipment installed and
  • All IOC and PLC programming complete
  • CHL Gas Management, Purifier and Warm Compressor
  • CHL 2.1K and 4.5K Cold Boxes
  • Medium and High Beta Cryomodules
  • HEBT Service Building IOC and PLC
  • 2K Cold Box Turn-on was automated
  • Cryomodules will complete in April

Full RF Power
First Liquid
Cool Down
Warm Up
11
The Cryogenic Control System layout
2 Servers
4 OPIs
11 IOCs
17 PLCs
12
Ring Controls is ahead of scheduleBNL effort
completed in March
  • Handover Plan - Complete and in use (cooling
    water and ramping software scope moved to ORNL)
  • FSDs - Complete, in use and being updated as
    needed to keep them as-built
  • Design - Essentially complete. All drawings and
    specs needed are in use for fabrication and
    installation and being updated as needed to keep
    them as-built
  • Hardware Fabrication - WBS 1.9 work complete
    except for installing 1 PLC for cooling water
    skid. WBS 1.5 work complete except for 2 motion
    control racks, 2 PLCs for RF, and Vacuum racks
  • Procurement - All hardware procured except 1 PLC
    for water skid and some miscellaneous parts
  • Cabling - Schedule for Ring and RTBT cables
    depends on budget allocations
  • HEBT Communications cables pulled, being
    terminated
  • HEBT Process control cabling in process
  • Software - Vac, BLM, Mag PSC/PSI, HPRF, Beam Dump
    TCs ready for handover. All software ready for
    field testing by Jun 05
  • Test Plans - Drafted for all systems except RF -
    Will be updated as needed during installation

13
PPS System Installation is keeping up(in spite
of many configuration changes)
  • 75 of the PPS controlled devices in the Linac
    have been connected
  • The temporary Linac shielding has been removed
    and the Linac has been returned to one segment
    for phase 1.3
  • PPS remote I/O racks for the HEBT are installed
  • Conduit cable for PPS devices installed in HEBT
    tunnel
  • Installation of conduit cable for PPS devices
    in Ring tunnel is 100 complete
  • The PPS control room racks have been relocated to
    the CLO CCR as a part of phase 1.3 (SCL
    commissioning)

14
The Target Instrument PPS are alsothe
responsibility of the Controls Team
  • Cable conduit design for target building
    complete, installation underway using AIMSI
    crafts (beamline 2 and transfer service bay) and
    fixed price subcontractor (high bay)
  • Target PPS equipment design is 85 complete
  • Target PPS equipment fabrication is 70 complete
  • Equipment installation ramping up as electricians
    become available
  • Instrument PPS design for beamline 2 underway.
    Prototype user panel being fabricated

15
The number of IOCs has risen dramatically
  • 223 IOCs currently on Accelerator Network
  • 109 VME / VXI --- vxWorks-based
  • 2 Linux-based Soft IOC Servers
  • Running 24 Soft IOCs (18 6)
  • 90 Intel-Pentium --- Win32-based IOCs (the
    NADS)
  • Wirescanners, Faraday Cups, BPMs, BCMs
  • Upgraded control system to EPICS R3.14.7
  • Improved reliability in channel access.
  • Results in fewer white screens in the control
    room.
  • Upgraded OS for VME/VXI-based IOCs
  • vxWorks 5.5.1 (SNS CVS Release SNS07)
  • Better network driver and network stack
    configuration
  • Auto-retry on boot-up if boot server is
    unavailable.
  • Better memory management

16
Power Supply Group is Routinely UsingAutomated
Testing and Calibration
  • Method uses EPICS and so assures end-to-end
    testing including control system
  • Resulted in large schedule reduction one test
    instead of two
  • PS Calibration, current/field mapping and cycling
    profiles come from Oracle RDB
  • 9 SCL IOCs installed, 8 operational
  • 1 HEBT IOC installed and operational

17
Turn-on and Turn-off of HPRF Systemshas been
automated
State Diagram monitors the process for each HVCM
Overall summary is displayed
18
The New Archive Engine is stable and
amany-featured Java Archive Viewer is now in use
  • Archives now well organized with central
    configuration file and scripts for
  • generation of directory structure and skeleton
    files
  • start/stop/restart/monitoring of sampling engines
  • update of status web page
  • email notification of engine status and disk
    usage
  • Currently 11 distinct archives each running one
    or more sampling engines (total 25).
  • (Conventional Facilities, Magnets, RF, Cryo, ...)
  • Data rate kept to 2GB/day with occasional peaks
    at 4GB/day.
  • Limiting performance factor is currently neither
    CPU nor network but disk I/O.
  • New Java Viewer is stable and many features are
    being exploited
  • Uses XAL Framework
  • Web interface available
  • Plots actual data in various formats
  • Offers absolute and relative request times
  • Performs computations, exports data to
    spreadsheets
  • Investigating new uses via command line and web
  • Scroll, zoom, legends, titles, multiple plot
    styles, arithmetic and boolean operations

19
The new Archive Viewer (Chevtsov)has many useful
features
  • Relative start/end times "-5 d(ays)" ? "now"
  • Multiple value axes
  • Tool-tip info for individual data points
  • XAL Framework

Support for calculations based on archived
data Export to spreadsheets, progress bar Green
squares in plot launch tool-tips for meta data,
in this case daily restart of sampling engine.
20
Database Collaboration with APS has grown(SNS,
APS, SLAC, TRIUMF, BESSY, FNAL, Diamond, PSI)
  • IRMIS Integrated Relational Model for Installed
    Systems (v1.0 release in April)
  • Agreed Core Schema describes control system
    with three hierarchies
  • Signal
  • Housing
  • Power
  • Uses the SNS Physics XAL Framework
  • Pelaia et al
  • RDB synchronized using crawlers
  • 106 SNS IOCs successfully crawled
  • EPICS versions 3.13.9, 3.14.6, 3.14.7
  • 228,270 PVs found
  • SCL 112141
  • DTL      33607  
  • CCL      27443  
  • MEBT   10918  
  • HEBT    8074    
  • Crawlers in development for all EPICS clients,
    IOCs, edm, Archiver, Alarms, etc.

21
Issues
  • Increased installation pace.
  • RF Processing and installation checkout means
    Control Systems Group must provide operational
    support.
  • Hardware/Software Configuration Management is
    highly correlated with reliability/availability.
    Work is in progress using a RDB, CVS, and good
    release control scheme.

22
Issues How to manage increasing number of IOCS?
  • 223 IOCs currently on Accelerator Network
  • 109 VME / VXI --- vxWorks-based
  • 2 Linux-based Soft IOC Servers
  • Running 24 Soft IOCs (18 6)
  • 90 Intel-Pentium --- Win32-based IOCs (the
    NADS)
  • Wirescanners, Faraday Cups, BPMs, BCMs
  • Upgraded control system to EPICS R3.14.7
  • Improved reliability in channel access.
  • Results in fewer white screens in the control
    room.
  • Upgraded OS for VME/VXI-based IOCs
  • vxWorks 5.5.1 (SNS CVS Release SNS07)
  • Better network driver and network stack
    configuration
  • Auto-retry on boot-up if boot server is
    unavailable.
  • Better memory management

23
Issues How to manage increasing number of IOCS?
24
Issues How to manage increasing number of IOCS?
25
Summary
  • Installation is keeping pace
  • Required use of more automated configuration and
    testing, database use
  • PPS keeps pace notwithstanding changes
  • Cryo controls nearing completion
  • Will be ready for SCL commissioning
  • Ready to pick up on Ring controls
  • Operational Improvements as well
  • Automated HPRF turn-on
  • Automated 2K Cold Box turn-on
  • Improved Archive viewing tools
Write a Comment
User Comments (0)
About PowerShow.com