2GMP Manufacturing Environments
- Air Handling Systems
- HVAC Systems
- Heating
- Ventilation
- Air Conditioning
- Module 4 Pressure Cascades
- Building Layouts
3GMP Manufacturing Environments
- Topics for this Module
- The integration of air conditioning systems and
building layouts. - The requirements for pressure cascades and how to
achieve them. - How building finishes and plant components affect
facility cleanliness. - Pharmaceutical Equipment
4Inter-dependence of Air Handling Systems
Buildings
- Building layouts, Pressure cascades, Air handling
systems and Pharmaceutical equipment are all
inter-related. - No one can exist without the other.
5What is a Pressure Cascade?
Pressure Cascade A process whereby air flows from
the cleanest area, which is maintained at the
highest pressure to a less clean area at a lower
pressure.
6What Is the Purpose of a Pressure Cascade?
- Helps prevent cross-contamination between
adjacent areas. - Helps prevent ingress of contaminants from
outside. - Is used to enhance separation between areas of
different cleanliness.
The unit of measurement for pressure is the
PASCAL (Pa)
7Air Pressure Cascade
8Measuring the Air Pressure Cascade
- The pressure differential over the doorway is
measured with a portable magnahelic gauge or
micro manometer.
- Permanently installed gauges are preferred.
9Room Pressure Air Movement
- A room pressure cascade system forces air to
flow from clean areas to less-clean areas.
- Air movement, such as laminar flow (UDAF) over
- the product, protects the product. (aseptic
packing / filling)
- Directional air movement helps carry
- contaminants away from a critical process. ?
10Typical OSD Plant Cross-contamination
Protection
What should the room pressures be ?
11Dispensary Layout
Is this a good layout ?
PIC/S PH 1/97 (Rev.3) 3.3 3.12
12Improved Dispensary Layout
Airflow direction
What should the room pressures be ?
13Sampling Booth Layout (1)
EXTRACT HOOD
SAMPLING BOOTH
WAREHOUSE
14Poor Design Extract System
Section Through Sampling Booth
15Sampling Booth Layout (2)
UDAF HOOD
SAMPLING BOOTH
AIR LOCK
AIR LOCK
CHANGE
Step-over-bench
16Typical Section Through Sampling Boooth
17What to Qualify in the Sampling Booth Suite
- Cleanroom class ISO 8
- HEPA filter integrity test
- Airflow rates
- UDAF velocity
- Room pressures
- Containment smoke tests
- Temperatures (lt 25C)
18Ablution Layout 1
Production Plant
Toilets
Staff
Change Room
Staff
19Ablution Layout 2
Production Plant
Change Room
Toilets
Staff
Staff
20Change Room Layout
21Protective Garments Outside ??
It is pointless having a change room if it is not
used properly
22Sterile Suite Pressure Cascade
23Product Flow Diagram
Wood free zone
RAW MAT. RECEIPT
PACK. MAT. RECEIPT
DISPENSARY
PACK. MAT STORE
MANUFACTURING
PRIMARY PACK MAT. CLEAN DOWN
PRIMARY PACKING
GMP ZONE
SECONDARY PACKING
DISPATCH
24Staff flow Diagram
STAFF ENTRY
CANTEEN
RAW MAT. RECEIPT
PACK. MAT. RECEIPT
DISPENSARY
CHANGE
PACK. MAT STORE
GMP CHANGE
PRODUCTION
PRIMARY PACK MAT. CLEAN DOWN
PRIMARY PACKING
GMP ZONE
SECONDARY PACKING
DISPATCH
25Negative Pressure Facilities
- Required for facilities handling potent compounds
such as penicillin hormones. - Special precautions required to prevent product
contamination from the atmosphere. - Exhaust air must be efficiently filtered and safe
filter handling must be used.
26Safe Change Filters
- Used for filtering hazardous materials
- Dirty filters are removed into a plastic bag
- The bag is automatically sealed at the filter
unit housing - A new filter is inserted via a plastic bag and
the cover closed - At no time is the operator or the atmosphere
exposed to the hazardous powder.
27Case Study Penicillin Plant
MALE ABLUT.
Add room pressures, Cleanroom class and comment
on layout
LAUNDRY
FINISH. GOODS
28Case Study Penicillin Plant
29Building Finishes
- In module 1 we discussed the need for all
facility components to complement each other. - Therefore a good air handling system must be
complemented by a building of good design and
good finishes. - On the next slide we will be looking at some of
the Acceptable and Un-acceptable building
finishes.
30Building Finishes
31Floors / drains
Tiled Floor
Epoxy Floor
32Poor Good Windows
Bacteria City !!!
33Paint Finish
- Not only building paintwork must be considered
but also equipment
Is there anything wrong with this Tablet Press?
34Building Equipment Finishes
35Services Distribution
Impossible to clean!
Easy to clean!
36Keep a Balance
- Dont ignore building finishes
and then go overboard on staff dress code.
37Services Distribution
- Where ever possible services should be located
behind wall panels - Exposed services pipes are very difficult to
clean sometimes impossible to clean - Equipment such as Film Coaters should be enclosed
so that only the front face is in the GMP area.
This makes cleaning much easier. - Make use of service corridors behind equipment
(but must be under negative pressure)
38Split Unit
Poor quality Air filter
Cooling Coil
Condensate drip tray
Fan liberates dust into the air
39Fluid Bed Drier
- Is the quality of the
- supply air to the FBD
- correct?
- What filtration is used?
- Is the exhaust air filtered?
40Group session
Airlock
41Modified Layout with Cascade
MAL Material Air Lock PAL Personnel Air Lock
42Product Flow Diagram
Work session Connect the arrows between
processes for Product Flow and Staff Flow
Raw Mat. Store
Quarantine
Released Materials
Primary Change room
Sampling A/L
Sampling A/L
GMP Change Room
Pack Mat. Store
Sampling Booth
Dispensary Pre-Staging
Dispensary Post-Staging
Dispensary Weiigh Booth
Primary Pack Mat. Clean Down
Secondary Packing
Pharmaceutical Manufacturing
Primary Packing
F/G Dispatch
43Product Flow Diagram
Work session Connect the arrows between
processes for Product Flow and Staff Flow
Raw Mat. Store
Quarantine
Released Materials
Primary Change room
Sampling A/L
Sampling A/L
GMP Change Room
Pack Mat. Store
Sampling Booth
Dispensary Pre-Staging
Dispensary Post-Staging
Dispensary Weiigh Booth
Primary Pack Mat. Clean Down
Secondary Packing
Pharmaceutical Manufacturing
Primary Packing
F/G Dispatch