Title: Improving Efficiency
1- Improving Efficiency Reliability
- of
- STEAM TURBINE
- Through R M
-
- BY
- AMITABH SRIVASTAVA
- SR.DGM, BHEL HARDWAR
-
2- IN THE PRESENT POWER SECTOR SCENARIO
- FOCUS IS ON
- ENHANCING EFFICIENCY
- RELIABILITY
- STRICTER POLLUTION NORMS
- COST REDUCTION
3 RESULTING TO ENHANCED EMPHASIS ONgt
REDUCTION IN GENERATION COST ? HIGH
EFFICIENCY OF TG CYCLE ? LOWER
EQUIPMENT COST ? SHORTER GESTATION
PERIOD ? REDUCED MAINTENANCE TIME gt
INCREASED RELIABILITY gt MINIMIZING
ENVIRONMENTAL HAZARDS
4IMPROVEMENT IN STEAM TURBINE PERFORMANCE
- POSSIBLE BY
- 1. IMPROVED BLADE PROFILE
- REDUCTION IN THE AERODYNAMIC
- FLOW LOSSES e.g.
- PROFILE LOSS
- SECONDARY FLOW LOSS
- TIP LEAKAGE LOSS
- MORE UNIFORM FLOW DISTRIBUTION
- CONTD..
5IMPROVEMENT IN STEAM TURBINE PERFORMANCE
POSSIBLE BY .contd... 2. OPTIMISED
FLOWPATH 3. IMPROVEMENT IN SHAFT SEALING
SYSTEM 4. REDUCTION IN PRESSURE DROPS 5.
REDUCED FRICTION LOSSES 6. OPTIMISATION OF
INLET EXHAUST SECTION 7. OPTIMISED EXHAUST LOSS
6DEVELOPMENT OF PROFILES FOR CYLINDRICAL TURBINE
BLADES
T4 PROFILE HAS 1 LOWER PROFILE LOSSES COMPARED
TO T2 PROFILE. NEWLY DEVELOPED TX HAS 0.2
LOWER PROFILE LOSSES COMPARED TO T4 PROFILE.
7CONSIDERATIONS IN RETROFITTING UPGRADATION OF
OLDER SETS
- COST EFFECTIVENESS
- MODIFICATIONS IN TURBINE INTERNALS
- ONLY
- INCREASE IN POWER OUTPUT WITH MINIMUM
- CHANGES
- OUTER CASING, PIPINGS, VALVES, PEDESTAL
- FIXING ARRANGEMENT , STEAM PARAMETERS
- FOUNDATION DETAILS REMAIN UNALTERED
- SHORTEST POSSIBLE OUTAGE TIME
-
8RETROFITTING UPGRADATION OF OLDER SETS
- PRE-REQUISITE
- IDENTIFY THE UNIT
- PRESENT LEVEL OF PERFORMANCE
- RESIDUAL LIFE ASSESSMENT STUDY OF CRITICAL
COMPONENTS - ANALYSIS OF HISTORY OPERATING DETAILS
9RETROFITTING UPGRADATION OF OLDER SETS
- MAJOR MODIFICATIONS IN
- GUIDE MOVING BLADE
- (LATEST STATE OF ART PROFILE)
- STEAM FLOWPATH
- ROTORS INNER CASINGS OF TURBINE
- SHAFT SEALINGS
- ADVANTAGE IN HEATRATE / OUTPUT CAN BE
WORKED OUT ON CASE TO CASE BASIS
3 DS BLADE (HPT/IPT)
TWISTED PROFILE BLADE (HP/IPT)
BANANA TYPE BLADE (LPT)
10- Retrofitting of HP Turbine
- with
- STATE OF ART REACTION BLADING
11210 MW STEAM TURBINE (IMPULSE DESIGN SET-LMW)
HP TURBINE
12210 MW STEAM TURBINE (IMPULSE DESIGN SET)
HP TURBINE
EXISTING 210 MW HP TURBINE WITH IMPULSE BLADING
PROPOSED NEW DESIGN WITH LATEST STATE OF ART
BLADING
13PROPOSED NEW DESIGN WITH LATEST STATE OF ART
BLADING
14HP TURBINE
- EXISTING
- IMPULSE BLADING
- ( PRESSURE DROP ONLY IN STATIONARY BLADES)
- EFFICIENCY 83.6
- (FOR NEW MACHINE)
- EFFICIENCY FOR EXISTING CONDITION 80
- NEW
- REACTION BLADING ( PRESSURE DROP IN
STATIONARY AS WELL AS MOVING BLADES - EFFICIENCY 86.5
15- ACTIVITIES INVOLVED
- REMOVAL OF EXISTING HP ROTOR, LINERS AND
DIAPHRAGMS - INSTALLATION OF NEW LINERS FITTED WITH STATIONARY
BLADES AND NEW HP ROTOR - FITTING DIMENSIONS ARE TO BE MEASURED DURING
PREVIOUS OVERHAUL AND LINERS ARE MACHINED
ACCORDINGLY. - REMOVED HP ROTOR AND DIAPHRAGMS CAN BE USED AS
SPARE FOR OTHER SETS
16- THE RETROFIT CAN BE DONE WITHIN NORMAL OVERHAUL
PERIOD. - PAY BACK PERIOD IS LESS THAN 3 YEARS
17A. Reference data for ORIGINAL brand new
turbine Reference Heat Balance Diagram TCD -
210 - 33 - 2, Regime No. 1 Rated
parameters Main steam Flow 662
T/h Main Steam Pressure 130 ata Main
Steam Temperature 535 Deg C Hot reheat
Temperature 535 Deg C Condenser Vacuum
0.1042 ata TG Heatrate
2062 kCal/kWh
18- B. Expected present performance level (210 MW
Original rating) - Considering deterioration due to ageing as per
ASME-PTC-6Report 1985 - Expected Power output
- with 662 T/h main steam flow
- and rated parameters 202.4 MW
- Expected TG Heatrate
- with 662 T/h main steam flow
- and rated parameters 2164 kCal/kWh
19EXPECTED PERFORMANCE IMPROVEMENT IN THE EXISTING
IMPULSE DESIGN SET DUE TO HP TURBINE REFURBISHMENT
- INCREASE IN POWER OUTPUT 8.6 MW
- IMPROVEMENT IN HEATRATE 4
-
- (FROM EXISTING PERFORMANCE LEVEL OF THE SET
WITH RATED STEAM PARAMETERS THROTTLE STEAM
FLOW)
20EXPECTED PERFORMANCE IMPROVEMENT IN THE EXISTING
IMPULSE DESIGN SET DUE TO HP TURBINE REFURBISHMENT
21COMPARISON
GAIN WITH UPRATED HPT ADDITIONAL GEN. OF MU
MW X1000 X HRS.X PLF 8.6 X 1000 X 8000 X 0.80
55.04 MU ADDITIONAL GEN. OF REVENUE _at_ RS 2/
PER UNIT 55.04 X 2 RS 11 CR
22Retrofit of LP TURBINE
200/210 MW IMPULSE DESIGN SET (LMW)
23EXISTING
AFTER RETROFIT
24(No Transcript)
25(No Transcript)
26- WORK INVOLVED IN RETROFIT OF LP TURBINE
- WORK TO BE DONE AT SITE
- CUTTING OF DEFLECTORS / RIBS BLANKING THE SPACE
IN LP CASING TO FACILITATE REMOVAL OF BAUMEN
STAGE. - MODIFICATION OF STRUCTURE AT THE EXHAUST END OF
LPC TO FACILITATE INSTALLATION OF DIFFUSOR. - CONTD.
27WORK INVOLVED IN RETROFIT OF LP TURBINE WORK TO
BE DONE AT SITE
- MODIFICATION OF STRUCTURE AT THE STEAM INLET END
OF LPC TO FACILITATE INSTALLATION OF 1ST STAGE OF
GUIDE BLADES.
28A. Reference data for ORIGINAL brand new
turbine Reference Heat Balance Diagram TCD -
210 - 33 - 2, Regime No. 1 Rated
parameters Main steam Flow 662
T/h Main Steam Pressure 130 ata Main
Steam Temperature 535 Deg C Hot reheat
Temperature 535 Deg C Condenser Vacuum
0.1042 ata TG Heatrate
2062 kCal/kWh
29- B. Expected present performance level (210 MW
Original rating) - Considering deterioration due to ageing as per
ASME-PTC-6Report 1985 - Expected Power output
- with 662 T/h main steam flow
- and rated parameters 202.4 MW
- Expected TG Heatrate
- with 662 T/h main steam flow
- and rated parameters 2164 kCal/kWh
30EXPECTED PERFORMANCE IMPROVEMENT IN THE
EXISTING SET DUE TO LP TURBINE REFURBISHMENT
- INCREASE IN POWER OUTPUT 10.1 MW
- IMPROVEMENT IN HEATRATE 102 KCAL / KWH
-
- (FROM EXISTING PERFORMANCE LEVEL OF THE SET
WITH RATED STEAM PARAMETERS THROTTLE STEAM
FLOW)
31COMPARISON
32COMPARISON
GAIN WITH UPRATED LPT ADDITIONAL GEN. OF MU
MW X1000 X HRS.X PLF 10.1 X 1000 X 8000 X 0.80
64.64 MU ADDITIONAL GEN. OF REVENUE _at_ RS 2/
PER UNIT 64.64 X 2 RS 12.93 CR
33COMPARISON
34COMPARISON
GAIN WITH UPRATED HPT LPT ADDITIONAL GEN. OF
MU MW X1000 X HRS.X PLF 11.6 X 1000 X 8000 X
0.80 74.74 MU ADDITIONAL GEN. OF REVENUE _at_ RS
2/ PER UNIT 74.74 X 2 RS 14.848 CR
35TECHNICAL PROPOSAL
FOR R M OF 210 MW STEAM TURBINES (KWU DESIGN)
OF TUTICORIN TPS
36CROSS SECTIONAL VIEW OF 210 MW STEAM TURBINE
37EXISTING DESIGN
- HP Turbine
- HP ROTOR WITH MOVING BLADES OF T2 PROFILE
- INNER CASING WITH STATIONARY BLADES OF
- T2 PROFILE
- INLET INSERTS WITH 580X9 MM BUTTRESS
- THREADS
- EXHAUST ELBOWS WITH SERRATED GASKET.
38210 MW STEAM TURBINE (REACTION DESIGN
SET-KWU)
HP TURBINE
RETROFITTING 210 MW REACTION TURBINE WITH
IMPROVED BLADING
39HP INLET INSERTS
HP OUTER CASING
BREECH NUT
40HP INLET INSERTS
HP INLET INSERTS (OLD DESIGN) HP OUTER CASING
BREECH NUTS THREAD SIZE 580X9 MM HP INLET
INSERTS (NEW DESIGN) HP OUTER CASING BREECH
NUTS THREAD SIZE 580X20 MM
41IMPROVEMENTS IN PROPOSED DESIGN
- HP MODULE
- INNER CASING HP ROTOR WITH OPTIMISED HIGHLY
EFFICIENT T4 PROFILE BLADING. - ADVANTAGE
- INCREASED EFFICIENCY
42IMPROVEMENTS IN PROPOSED DESIGN (CONTD.)
- HP MODULE (CONTD.)
- MODIFIED HPT INLET INSERTS WITH BUTTRESS THREADS
OF SIZE 580X20 MM IN HP OUTER CASING BREECH
NUTS.
ADVANTAGE EASE IN ASSEMBLY DISMANTLING.
43IMPROVEMENTS IN PROPOSED DESIGN (CONTD.)
HP MODULE (CONTD.) MODIFIED HP EXHAUST ELBOWS
WHICH HAVE U-RING IN PLACE OF SERRATED GASKET.
ADVANTAGE ENHANCED RELIABILITY.
44HP EXHAUST ELBOWS
Exhaust Elbow
HP OUTER CASING
45HP EXHAUST ELBOWS
46HP EXHAUST ELBOWS
U-RING
47SCOPE OF SUPPLY
- FOR HP TURBINE
- COMPLETELY ASSEMBLED HP MODULE WITH T4 PROFILE
BLADING ALONGWITH MODIFIED HP INLET ASSEMBLY HP
EXHAUST ELBOWS.
48210 MW STEAM TURBINE (REACTION DESIGN SET-KWU)
IP TURBINE
RETROFITTING 210 MW REACTION TURBINE WITH
IMPROVED T4 PROFILE BLADING
ADVANTAGE IMPROVED PERFORMANCE.
49SCOPE OF SUPPLY (CONTD.)
- FOR IP TURBINE
- IP INNER CASING IP ROTOR WITH T4 PROFILE
BLADING. - A SET OF HPR-IPR IPR-LPR COUPLING BOLTS.
- NECESSARY KEYS ETC.
50WORK REQUIRED TO BE DONE AT SITE
- NOT INCLUDED IN THE SCOPE OF THIS TECHNICAL
OFFER - PERFORMANCE TESTING PRIOR AFTER R M.
- OVERHAULING.
- RLA STUDY.
- COMPONENTS IDENTIFIED DURING OVERHAULING/ RLA
STUDY WHICH NEED REPLACEMENT
51WORK REQUIRED TO BE DONE AT SITE (FOR HP Turbine)
- REMOVAL OF OLD HP MODULE FROM ITS POSITION AFTER
DISMANTLING OF HP INLET INSERTS AND HP EXHAUST
ELBOWS. - OLD HP INLET ASSEMBLY (INLET INSERTS WITH BREECH
NUTS) HP EXHAUST ELBOWS ARE TO BE CUT FROM MS
PIPES CRH PIPES RESPECTIVELY.
52WORK REQUIRED TO BE DONE AT SITE(CONTD.)
- INSTALLATION OF NEW IMPROVISED HPT MODULE IN
POSITION, CENTERING ALIGNMENT. - WELDING OF HP INLET ASSEMBLY OF NEW MODULE WITH
MAIN STEAM PIPES.
53WORK REQUIRED TO BE DONE AT SITE(CONTD.)
-
- HP EXHAUST ELBOWS ARE TO BE WELDED WITH CRH STEAM
PIPES. - ASSEMBLY OF HP INLET INSERTS HP EXHAUST ELBOWS
TO BE COMPLETED.
54WORK REQUIRED TO BE DONE AT SITEFOR IP Turbine
- REMOVAL OF OLD IP ROTOR IP INNER CASING.
- INSTALLATION OF NEW IP INNER CASING IP ROTOR
WITH T4 PROFILE BLADING, ITS CENTERING
ALIGNMENT. - COMPLETION OF BOX UP OF IP Turbine.
55CONDITION AFTER R M OF HPT IPT (UNDER RATED
CONDITION)
- RATED PARAMETERS
- At 100 MCR condition
- MAIN STEAM FLOW 641.3 T/HR
- MS/ HRH STEAM TEMP535/535 DEG C
- MAIN STEAM PR 150 ATA
- BACK PR 0.121 ATA
56EXPECTED PRESENT PERFORMANCE
CONSIDERING DETERIORATION DUE TO AGING AS PER
ASME-PTC-6 REPORT 1985 FOR AVERAGE LIFE OF 20
YEARS, FOLLOWING WILL BE EXPECTED PERFORMANCE AT
641.3 T/HR MAIN STEAM FLOW AND RATED PARAMETERS
OUTPUT 202.3 MW HEAT RATE 2067 KCAL/KWH
57COMPARISON OF PERFORMANCE
58PAY BACK PERIOD
1) REDUCTION IN OH PERIOD 25 DAYS RESULTING TO
ADDITIONAL POWER GENERATION FOR 25
DAYS YIELDING TO GUAREENTED MINIMUM ADDITIONAL
REVENUE 209MW x 1000 x 25DAYS x 24HRS x
0.80PLF x 2.00RS RS 20.06 CRORES
59PAY BACK PERIOD
- ADDITIONAL ANNUAL REVENUE GENERATION DUE TO
INCREASE IN OUTPUT IMPROVED HEAT RATE - 6.7 MW x 1000 x 8000 HRS x 0.80 PLF x RS
2.00 -
- RS 8.576 CRORES PER YEAR
- HENCE, PAY BACK PERIOD lt 3 YEARS
60Thank you
61PRESENT EXPECTED CONDITION OUT PUT 202.3 MW
(641.3T/HR) THEREFORE, OUT PUT 210 MW (665.7
T/HR) FOR THIS FLOW IT IS OPERATING NEAR TO VWO
CONDITION WHICH IS NOT DESIRABLE.
62EXPECTED CONDITION AFTER RM OUT PUT 209 MW
(641.3T/HR) THEREFORE, OUT PUT 216.95 MW (665.7
T/HR) FOR THIS FLOW IT WILL BE OPERATING NEAR
VWO CONDITION WHICH IS NOT DESIRABLE.