Project Location: Nyamilu, Kenya - PowerPoint PPT Presentation

1 / 46
About This Presentation
Title:

Project Location: Nyamilu, Kenya

Description:

T. Jordan, I2U2 Meeting, December 2005. What is a laboratory? ... T. Jordan, I2U2 Meeting, December 2005. They include tools to: deliver data. foster investigation ... – PowerPoint PPT presentation

Number of Views:187
Avg rating:3.0/5.0
Slides: 47
Provided by: uc3
Category:

less

Transcript and Presenter's Notes

Title: Project Location: Nyamilu, Kenya


1
Implementation Trip for EWB-LSU
  • Project Location Nyamilu, Kenya
  • Chapters EWB-LSU Dartmouth-EWB
  • Brief Description of Project
  • Installation of 3.6 miles of water distribution
    piping
  • Construction of ferrocement water storage tanks
  • Construction of 13 water distribution points
  • Project Risk Level Level 2
  • Dates of this Implementation Travel July 12
    August 21

2
Background
  • Nyamilu is a small farming community
  • located in southwest Kenya.
  • Constant water shortages and outbreaks of
  • waterborne diseases are common in this
  • region due to the limited availability of
  • water.
  • The situation has also been compounded by
  • an ongoing drought making a reliable water
  • system all the more necessary.

3
Background (cont.)
  • The communitys struggles pressed one of
  • the villagers, Jerry Baraza, to seek help
  • from EWB-USA
  • In Fall of 2004, EWB chapters at
  • Dartmouth College and Louisiana State
  • University adopted The Nyamilu
  • Community Water Project

4
Travel History
  • Phase I
  • The Dartmouth-EWB team traveled to Kenya in the
    Summer of 2005 to install a new well and complete
    a site assessment.
  • The Dartmouth team worked with the Nyamilu
    community development leader to map the locations
    of homesteads and current water sources using GPS
    while meeting with the local people to get an
    idea of the population of the village.
  • Each of the current water sources were tested.
    Nearly every source had bacteria present.

5
Travel History (cont.)
  • Phase I
  • The team estimated that there were nearly 1700
    people living in the village.
  • After the survey was completed the group
    consulted with community leaders and reviewed the
    data to determine the locations of the
    distribution points.
  • Nine distribution points around the village were
    decided upon that would best accommodate the
    communitys needs.
  • The group also contracted a drilling company to
    have a 98 meter well drilled and installed a
    solar-powered submersible pump at 37 meters.

6
Contact Information
  • Project Leads
  • James Dupree (President) jdupre9_at_lsu.edu
    (985) 855-2570
  • Leah Lemoine
    llemoi7_at_lsu.edu (337) 278-2520
  • Hannah Murnen hmurnen_at_dartmouth.edu
    (603) 646-7673
  • Professional Mentors
  • John Dupree JJDupree_at_bellsouth.net
    (337) 523-1401
  • Al Pawlowski
    avp2_at_lsu.edu (225) 578-6834
  • Faculty Advisor
  • Dr. William Moe
    moemwil_at_lsu.edu (225) 578-9174
  • Health Point Person
  • Blake Lemoine
    jlemo22_at_lsu.edu
  • NGO/Community Contact
  • Jerry Ochieng ochiengjerry_at_yahoo.com
    254 722 792 414

7
Project Team
  • Andrew Bankston
  • Chris Bergeron
  • James Dupree
  • Blake Lemoine
  • Leah Lemoine
  • William Moe
  • Al Pawlowski
  • Rachel Stich
  • Elaine Tate

8
Travel Team
  • Chapter Traveling EWB-LSU
  • List of Travel Team Names
  • James Dupree
  • Chris Bergeron
  • On-the-ground Contact
  • Jerry Ochieng
  • 254 724 664 254, 254 720 821 809, 254
    722 792414
  • Charles Onyango Otieno
  • PO Box 54 Suna Migori, Kenya
  • 254 735 509 747
  • Leah Lemoine
  • Al Palaski

9
Travel Team (cont.)
  • Nearest US Consulate Contact info
  • Consular Section U.S. Embassy
  • United Nations Avenue
  • Village Market
  • Nairobi, Kenya
  • Nearest Hospital Contact Info
  • Ojele Memorial Hospital,
  • (59)-20346, www.omh2.org
  • Suna-Migori, lt6 miles from village
  • admin_at_omh2.org, info_at_omh2.org

254 375 3704 254 375 3700 (automated) kenya_acs
_at_state.gov Consularnairob_at_state.gov
10
Travel / Transportation
  • New Orleans (MSY) ? Nairobi (NBO)
  • air transportation
  • Nairobi ? Nyamilu
  • Some of the supplies will be purchased in Nairobi
    before traveling to the village. Truck
    transportation will be arranged through Jerry
    prior to traveling.
  • Additional transportation will be provided by
    Jerry throughout the teams stay in Nyamilu.
  • July 14 - Morning
  • arrive in Nairobi
  • meet with Jerry
  • begin collecting supplies and making arrangements
    to transport them to the village
  • team will stay in Nairobi for the night
  • July 15 Morning
  • Depart for Nyamilu
  • July 15 - Evening
  • Arrive in Nyamilu

11
Travel / Transportation (cont.)
  • Nyamilu ? Supplies ? Nyamilu
  • truck / driver provided by the village to collect
    materials required for the project
  • travel times / supplies decided on site with
    regard to
  • project itinerary
  • predetermined materials list
  • Nyamilu ? Nairobi
  • Jerrys vehicle (Oldsmobile) / driver provided
  • August 21 - Morning
  • Depart for Nairobi
  • Flight will depart in late evening
  • Return to New Orleans, LA

12
Accommodations
  • Jerry Ochieng has agreed to board the team in his
    guest house for the duration of the project.
  • Any hotel stays will be in Nairobi with expenses
    covered by team funds.
  • Jerry has agreed to see to it that meals and
    bottled water will be provided to the team for
    the duration of the project.
  • Meals outside the village will be covered by
    personal funds.
  • The team plans to visit the nearby city of
    Migori, and the Kipingi village during the trip.

13
Safety Emergency Plan
  • Safety Plan
  • Team will register with the U.S. Embassy in
    Nairobi so that the Department of State can help
    us if we require information, advice, or
    emergency assistance.
  • Team members will always travel in groups of 2
    or more.
  • All members shall know where everyone is at any
    time.
  • A meeting place within the village will be
    designated in case group members are separated in
    Nyamilu.
  • A meeting place in Migori will be determined
    for similar circumstances.
  • Anyone leaving the village will be escorted by
    a villager.
  • Vehicle transportation will be provided with a
    driver when required
  • All team members will receive recommended
    vaccinations for Typhoid, Hepatitis, Malaria, and
    Yellow Fever.
  • Emergency Plan Exit Strategy
  • In the case of an emergency, the U.S. Embassy
    will be contacted from Migori for further
    instruction and assistance. There is a vehicle
    available to us if we need to leave the village.

14
Safety Emergency Plan (cont.)
A first aid kit will be kept with the group along
with other important medications
  • Insect Repellant
  • Water purification tablets /
  • portable water filters
  • Hypodermic syringes to be used at
  • a hospital
  • Antidiarrheal medication (e.g.,
  • bismuth subsalicylate, loperamide)
  • Antibiotic for self-treatment of
  • moderate to severe diarrhea
  • Antihistamine
  • Decongestant, alone or in
  • combination with antihistamine
  • Antimotion sickness medication
  • Acetaminophen, aspirin, ibuprofen, or other
  • medication for pain or fever
  • Mild laxative
  • Cough suppressant/expectorant
  • Throat lozenges
  • Antacid
  • Antifungal and antibacterial ointments or
  • creams
  • 1 hydrocortisone cream
  • Epinephrine auto-injector (e.g., EpiPen), for
  • severe allergic reactions
  • All traveling team members will have proper
  • International Travel Insurance covering
    accidents,
  • sickness, and emergency evacuation.

15
General Safety
  • The United States Department of State recommends
    that private American citizens in Kenya evaluate
    their personal security situation in light of
    continuing terrorist threats and the limited
    ability of the Kenyan authorities to detect and
    deter such acts.
  • They recommend that Americans who travel to Kenya
    despite this Travel Warning should register
    through the State Departments travel
    registration website, https//travelregistration.s
    tate.gov.
  • By registering, American citizens make it easier
    for the Embassy to contact them in case of
    emergency.

16
General Safety (cont.)
  • There is currently a drought affecting the Horn
    of Africa.
  • Correspondence with Jerry has informed the group
    that there is an increasing need for water in the
    village due to the drought.
  • To date the northern regions of Kenya are facing
    the most severe effects.
  • The team will monitor the effects of the drought
    before the trip in order to avoid as many
    problems as possible while in Kenya.

17
Objectives of Implementation Trip
  • The goals
  • Provide a sustainable source of
  • and clean and accessible drinking
  • water to the entire village
  • Provide sufficient water storage to
  • serve in times of high demand
  • Teach villagers the skills necessary to
  • build, maintain and expand a reliable
  • water system

18
Equipment
  • The team will bring certain equipment with them
    in order to save time buying supplies in Kenya.
    Important system components will also be brought
    over in order to ensure these are good quality.
    (customs)
  • Water testing equipment???
  • Measuring / surveying equipment
  • Electrical equipment Voltmeter, wire
    cutters/strippers
  • Various valves for distribution points and mains
  • PVC bushings, valves
  • All listed equipment complies with FAA and Kenya
    Customs regulations and can be checked on to
    airlines.

19
Technical Description of Project
  • System Capacity
  • After the new well was drilled a 24 hour pump
    down test was performed to determine the recharge
    rate.
  • The well was rated to be able to provide a
    constant 1.2m3/h or about 5.3gpm based on the
    drilling companys tests.
  • With the solar pump running for a full six hour
    workday the well can provide just over 1900
    gallons to the community.
  • At this capacity the community will be able to
    draw a maximum average of 1.12 gallons (4.24L)
    per person each day.

20
Technical Description of Project
  • During Dartmouths trip a solar pump was
    installed with a maximum head rating of 30
    meters.
  • Since there was no figure for the output of the
    well when a pump was bought this resulted in the
    selected pump not being able to utilize the full
    capacity of the well.
  • In order to make having a large distribution
    system worthwhile a new pump will need to be
    installed.
  • Lorentz PS600 HR-20 (Max flow 3.6m3/h)

21
Technical Description of Project
  • Dartmouth recommended buying a new pump in Kenya
    since they are readily available.
  • A replacement pump will need to be able to
    support a maximum head of 180 feet while
    providing a daily average output of 7.2m3.

22
Technical Description of Project
  • Water Storage
  • The EWB team plans to provide the community with
    a 5 day storage capacity (40,000L) in order to
    make the system more reliable and convenient.
  • Different storage methods were examined and a
    ferrocement tank was determined to be the best
    choice.
  • With many members of the community willing to
    provide assistance with construction a low cost
    yet highly reliable water storage tank could be
    built.
  • This self-help effort will allow funds to be
    spent on expanding the system rather than on
    labor and expensive materials.
  • 0.03/Liter

23
Technical Description of Project
  • The design and construction of ferrocement water
    storage has been carefully studied to better
    ensure a good quality tank can be built. A local
    resident with experience building water
    distribution and storage systems will also be
    available while working in Nyamilu.
  • In order to gain experience in building a tank,
    the team will design and build a practice tank
    prior to implementation. Experience will also be
    gained in mixing and using concrete along with
    installing PVC piping.
  • Smaller Thai Jar type ( lt 3m3) tank
    construction will also be studied in order to
    possibly provide the volunteers a water storage
    option that can be easily learned and repeated.
  • During construction, observations will be made in
    order to develop better time management. This
    will be utilized during implementation when time
    will be limited.

24
Technical Description of Project

Water Storage, Art Ludwig
25
Technical Description of Project
  • Distribution Points
  • There are 13 proposed locations throughout the
    village where water will be available.
  • Each point will be constructed with galvanized
    iron pipe and a concrete slab to protect the
    underground piping.
  • All locations will have a separate shut off in
    the case that the point needs to be repaired
    allowing the rest of the network to remain
    unaffected.

26
Technical Description of Project
27
Technical Description of Project
  • The distribution system consists of over 3.6
    miles of PVC piping.
  • In order to accurately calculate the behavior of
    the system under working conditions WaterCAD
    software was used.
  • The system has been designed to provide no less
    than 5 gpm when all distribution points are in
    use.
  • The following map presents the topographical
    layout of the village along with the proposed
    pipe layout.

28
(No Transcript)
29
Technical Description of Project
Static Pressures
Dynamic Pressures
30
A detailed view of the systems performance.
(all points at 5gpm)
31
Community Participation, Education Ownership
  • The NGO, Jerry, has assured us that a group of
    ten volunteers will be available to help with the
    project.
  • Excavation of trenches for the pipes and
    collection of certain materials will be completed
    prior to the teams arrival.
  • The volunteers will work with members of EWB-LSU
    for the duration of the implementation to assist
    in completing the project and to gain knowledge
    on maintaining and building a water system.
  • The importance of maintaining a clean water
    source along with other safety precautions will
    be stressed.

32
Community Participation, Education Ownership
  • The EWB team will meet each daily to divide the
    days tasks between volunteers and students so
    that the project may be completed in an efficient
    manner.
  • During Dartmouths visit a team of leaders,
    namely, The Nyamilu Community Development
    Committee and experts from the community agreed
    to be responsible for the administration,
    operation and maintenance of the system. The
    procedures necessary to operate the water system
    will be covered throughout implementation.

33
Implementation Metrics
  • Technical
  • EWB-LSU and D-EWB will remain in contact with
    the community after implementation to see that
    the system remains in good working condition and
    to provide consultation regarding any problems
    that may arise.

34
Implementation Metrics (cont.)
  • Health
  • The water sources other than the current new well
    have proven to be of severe health risk
    containing such water-borne diseases as E. coli,
    Dysentery, Cholera, and Typhoid.
  • If the new system is expanded to provide easy
    access to all parts of the village it will help
    to reduce many of these cases .
  • Water samples from the new well will be collected
    and tested in order to assess the need for a
    filtration system in the future.
  • Economics
  • A reduction of water quality related health
    issues will allow people to spend less time and
    money treating those with such illnesses. Those
    with other health issues will have a better
    chance of getting the help they require.
  • Time spent by women walking to collect water each
    day will be decreased significantly thus
    providing them with opportunities to partake in
    profitable opportunities such as farming.

35
Community Involvement
  • EWB-LSU has been in regular contact with the
    community through correspondence with Jerry since
    the start of the design process.
  • Periodic consultations with Jerry have helped us
    to develop a system that will best accommodate
    the needs of the community.
  • The communication between EWB-LSU and EWB-Kenya
    has been very good. Both the team and Jerry feel
    that this project will be a success.
  • The finished project will be able to provide
    water to over 1700 people living in the village.

36
Assessment for Future Project Phases
  • Project assessments will be completed following
    the completion of the current project for
  • Nyamilu
  • The Kipingi Community
  • A neighboring village
  • Requirements and metrics of a project assessment
  • Ability to communicate before and during design
    phase
  • Magnitude of Impact
  • Health metrics
  • Economic impacts
  • Land surveys
  • Population surveys
  • Population density
  • Community participation

37
Assessment for Future Project Phases (cont.)
  • Information necessary to determine overall
    project impact will be obtained by meeting with
    and interviewing members of the communities.
  • The possibility of another project in this region
    will depend greatly on the results of the current
    project.
  • EWB-LSU feels that it is beneficial to
    concentrate on a particular region in order to
    plan future projects more efficiently.

38
Assessment for Future Project Phases (cont.)
  • Specific details regarding future project phases
    in Nyamilu will examine the impact of
  • Water filtration
  • It is unclear as to the exact quality of the
    water being pumped from the well, a sand filter
    or other means of purifying water may be
    necessary as future phases. The water quality
    will be tested on site. Preserved water samples
    from the well will also be collected in order to
    perform further quality tests following the
    teams return.

39
Assessment for Future Project Phases (cont.)
  • Drip Irrigation
  • Nyamilu relies mainly on the sale of crops for
    income, an irrigation system could help to
    further stimulate the economy in the village
  • The benefits of an improved irrigation system
    will be determined through observations and
    discussions with community members during
    implementation.

40
Assessment for Future Project Phases (cont.)
  • Specific details regarding Kipingi Community
    Assessment
  • Requirements Design and Implement a Permanent
    Water Supply with a borehole, Submersible Pump,
    Wind/Solar Power, Water Tank and limited
    distribution with five water collection points
    within the village for domestic use.
  • Water is currently collected from a nearby
    communitys well but the residents are hostile
    toward the Kipingi People because they belong to
    a different county-administrative unit.
  • The community wishes to sink a borehole. Hydro
    geological surveys have been carried out and a
    suitable aquifer identified and beaconed. The
    proposed borehole is 100 meters deep. The water
    supply shall serve approximately 50 homesteads.
  • Communication with the village will be similar to
    the current project through Jerry.

41
Assessment for Future Project Phases (cont.)
  • Specific details regarding Kipingi Community
    Assessment
  • If possible the LSU team will evaluate the
    communitys need for a water system by visiting
    with the village and surveying members of the
    community.
  • Land surveys will be completed to collect any
    necessary information for designing a new system.
    GPS and flexible tube water levels will be used
    to collect the data.

42
Budget Hours
  • Budget breakdown
  • Leah has been in charge of budgeting throughout
    the project
  • Hours on the project
  • Planning for this portion of the project began in
    Fall of 2004 and has steadily progressed since.
  • The group worked an average of 2-3 hours each for
    each week of planning.
  • The estimated total amount of time dedicated to
    this project is 180 hours.

43
Donors Funding
  • Sources of funds and in-kind contributions
  • Corporate Sponsors
  • ??
  • ??
  • ??
  • LSU Engineering Department
  • LSU Organization Relief Fund
  • EWB-LSU fundraisers
  • Eat Out for Hunger
  • Did your team meet its funding goals?
  • The team has met nearly 60 of its goal.
    Fundraising is still ongoing so that the complete
    system can be built during implementation.

44
Response to TAC Comments
  • Suggestions from the TAC will be used to
    improve our system and bring forth any aspects of
    the project that may have been overlooked. The
    information will be taken into consideration when
    the final design is made.

45
Project Lead Sign-Off
  • I Dr. William Moe as the faculty advisor of this
    project, have reviewed the technical and
    logistical contents of this project, and approve
    of the proposed design. I will also comply with
    TAC recommended changes and make suggested
    changes before traveling on the implementation
    trip.
  • Signed ______________________

46
Final Checklists before Travel
  • The goal of the review process is to make sure
    that your team has a successful implementation
    trip
  • 1) Submit this presentation to the project
    management staff and TAC liaison at
    projects_at_ewb-usa.org. Turn in WITH the
    following
  • Volunteer Waiver Form (605) for each person
    traveling. Please submit all at one time.
  • 2) Prior to the TAC meeting The Project
    Management Staff and the liaison will review this
    presentation with the project lead, mentor and
    other relevant team members via a conference call
    prior to its presentation at the TAC meeting.
  • 3) Before final travel, your team should have the
    following checklists signed off by the persons
    listed below, and get a final OK from the EWB-USA
    Project Staff
  • Travel Readiness Checklist (601) to project
    staff
  • Personal Health Checklist (603) to teams
    health point person (to be taken on the trip)
  • Detailed Field Equipment Checklist to mentor or
    project lead
  • Proved this presentation emergency contact
    information to each and every member of the team
  • Have each person review the Travel Tips
    Presentation (602)
  • 4) The Project team will be responsible for
    following up on TAC Comments and submitting
    changes/revisions to the project staff
  • 5) The Project team MUST notify the project staff
    of any changes to travel dates or travel teams.
    Additional team members MUST send in Waivers
    (605) prior to travel.
Write a Comment
User Comments (0)
About PowerShow.com