Title: FERC
1FERC Hydrokinetic ProjectsOcean Energy for
New England ConferenceHosted by the Marine
Renewable Energy Center at the Advanced
Technology and Manufacturing Center Fall River,
MAOctober 6, 2008
2Topics
- Flexibility at FERC Approach to New Technologies
- Hydrokinetic Project Proposals
- Next steps information
3Hydrokinetic Projects
Conventional hydropower projects
Hydrokinetic projects generate electricity from
waves or directly from the flow of water in
ocean currents, tides, or inland waterways
4Regulatory Approach
- The Commission
- supports the development of hydrokinetic projects
- recognizes the conundrum of need for real-world
testing, yet limited information to prepare
application - Tailored existing program
- Preliminary permits
- Test projects
- Pilot project license
5Types of Issuances
- Preliminary permits
- Maintains priority of application for three years
- Conduct feasibility studies and prefiling
activities - Doesnt authorize construction
- Licenses
- Authorizes construction
- and operation
- Original up to 50 years
- Relicense 30-50 years
6Preliminary Permit ReviewStrict Scrutiny
February 15, 2007
- Applications
- Appropriately sized area
- Details of proposed
- technology
- Post-issuance administration
- Schedule of activities
- Progress reports
- Cancel permit if no progress
7Hydrokinetic Project Permits (as of September
23, 2008)
- Issued, existing preliminary permits
- 34 tidal, 9 wave, 0 ocean current, 68 inland
- Pending preliminary permits
- 20 tidal, 4 wave, 3 ocean current, 66 inland
8FERC-Issued Hydrokinetic License and Preliminary
Permits
9FERC-Issued Hydrokinetic Preliminary Permits
10Pending Preliminary Permits
11Test Projects(no FERC license needed)
- Verdant Declaratory Order- April 2005, July 2005
- No license required if
-Experimental technology -Short term
installation for conducting studies -Test
project does not transmit into, or displace power
from, the national electric energy grid
12Pilot Project LicenseWhitepaper updated April
14, 2008
- Test technologies, evaluate sites, monitor
effects, and generate electricity - Agency and public input, with FERC oversight
- Complete licensing in as few as 6 months
- Guard against environmental harm
- Short license term, small footprint, removable
- Careful monitoring
- Project shutdown or removal if harm
13Pilot Project Licensing Procedures Available
for projects that are
- small, short term
- not in sensitive areas
- removable able to be shut down
- removed, with site restored
- initiated by draft application in a form
sufficient to support environmental analysis - On case-by-case basis
14Hydrokinetic Project Proposals (as of June 4,
2008)
- Pre-filing license applications
- Reedsport (OR)
- Coos Bay (OR)
- Douglas County (OR)
- Roosevelt Island (NY)
- License issued
- Makah Bay (WA)
15Typical Statutes
- Federal Power Act
- National Environmental Policy Act
- Endangered Species Act
- Marine Mammal Protection Act
- Magnuson-Stevens Fisheries Act
- Fish and Wildlife Coordination Act
- Coastal Zone Management Act
- Clean Water Act
- National Historic Preservation Act
16Licensing StandardFederal Power Act
Give equal consideration to power and
environmental values
17Standard Licensing Processes
- Integrated Licensing Process (ILP)-default
- Traditional Licensing Process (TLP)
- Alternative Licensing Process (ALP)
18Hydrokinetic Websitewww.ferc.gov
- Process guidance
- Issued and pending permits and licenses
- Timeline of Commission actions
19Next Steps
- Project specific
- Participate in prefiling and process applications
- Programmatic
- Coordinate with states and agencies to establish
agreements (MOUs, etc) - Continue outreach
- Consider additional strategies as projects
progress, i.e., how best to build out from a
pilot project
20Questionswww.ferc.gov
- Kristen Murphy
- 202.502.6236
- Kristen.murphy_at_ferc.gov
21(No Transcript)