Title: FERC UPDATE


1
ISOGrid Planning
Presentation to CREPC October 1, 2002 Armando J.
Perez Director of Grid Planning California ISO
2
Presentation Contents
  • Components of ISO Grid Expansion Plan
  • General Planning Process
  • Transmission Projects
  • Generation Projects
  • Policy and Coordination
  • Transmission Cost Recovery

3
Special Focused Plans
New Generator Interconnection Plans
ISO Controlled Grid Plan
ISO Grid Plan Components
Reliability Must-Run Generation Studies
4
General Planning Process
Develop Study Plan Agree on Assumptions
5
Economic Reliability Benefits
  • Almost All Projects have both Reliability and
    Economic Benefits and may be justified from
    either or both perspectives.
  • Reliability Benefits - Primarily based on
    complying with Planning Standards resulting in
    fewer, shorter, and less widespread outages.
  • Economic Benefits Reduction in the cost of
    power to ratepayers (access to lower cost
    resources and mitigation of market power).

6
Project Development Process
  • Determine Project Need
  • Determine Best Transmission Solution
  • Conduct Competitive Solicitation
  • Need methodology to compare projects with
    different time frames and benefits.
  • Need a means for rate recovery of
    non-transmission expenses.
  • Approve Best Project

7
Minimum Level of Reliability is Specified in
Planning Standards
8
Transmission Projects
  • 255 Projects Approved Since ISO Formation
  • 1.74 Billion
  • 145 Already In-service
  • Generator interconnections not included
  • 60 Additional Projects Currently Under Study

9
Major Approved Projects
10
Generation Projects
  • 225 Projects have been Followed by ISO
  • 42 Projects On-line (6000 MW)
  • 71 Projects in Planning, Permitting or
    Construction (26,000 MW)
  • 112 Projects Cancelled or Placed on Hold (33,000
    MW)

11
Proposed New Generation
18 Projects
17 Projects
MW
8 Projects
25 Projects
3 Projects
Year
12
Policy and Coordination
  • Policy In various forums, we develop standards,
    procedures, methodologies, requirements, new
    organizations, etc.
  • Continental Level NERC FERC
  • Western Interconnection Level WECC, CREPC SSG
  • ISO Level Stakeholder Groups
  • Coordination - Our planned changes will affect
    the entire interconnection and vice versa. All
    changes require some level of coordination.

13
Transmission Cost Recovery
  • High Voltage Access Charge
  • 200 kV and above
  • Eventually Grid-wide
  • 10 year transition period
  • Grid-wide for new facilities
  • Low Voltage Access Charge
  • Below 200 kV
  • Initially 3 TAC Areas (Northern, East Central,
    Southern)
  • Wheeling Out Charge
  • Offsets access charge

14
Questions ?