Title: Fuel Cell
1Fuel Cell
Heat
.JMH -- 20/april/05 330 pm Ive rearranged some
of the nick slides -- it is more in line with the
flow of the process. Ive taken some things
out. Ive made the background with header
footer on all but Title slide I added the PFD
repeatedly in nicks section to bring the viewer
back home Ive partially covered the non-circled
parts of the PFD when showing a new section Ive
enlarged all the PFD images to max I put some of
your pictures here there Ive added the Turn
it over introductions Ive revised and corrected
the fuel cell details
2Fuel Cell Design
- ENCH 340
- Spring, 2005
- UTC
3Technical and EconomicAspects of a 25 kW Fuel
Cell
- Chris Boudreaux
- Jim Henry, P.E.
- Wayne Johnson
- Nick Reinhardt
4Technical and EconomicAspects of a 25 kW Fuel
Cell
- Chemical and Thermodynamic Aspects
- Investigate the design of
- --a 25 kW Fuel Cell
- --Coproduce Hydrogen
- --Grid parallel
- --Solid Oxide Electrolyte
Our Competence
Not Our Competence
5Outline
- Introduction to the project
- Process Description
- Process Equip. Design
- Economic Analysis
6Introduction
- Overall Reaction
- Methane Air --gt Electricity
- Hydrogen
Heat CO2
7Introduction
Gas
Reformer
Water
SynGas
Electricity
Air
Fuel Cell
Heat
POC
Hydrogen
Pressure Swing Absorption
Exhaust
8Fuel Cell-Chemistry
SynGas
POC
H2
H2
CO
H2O
CO2
CO
O-
O-
Air
Air
O2 N2
Solid Oxide Electrolyte Is porous to O-
9Fuel Cell-Electricity
Electrons
SynGas
POC
H2
H2O
CO2
CO
Load
O-
O-
Air
Air
O2 N2
10Fuel Cell-Challenges
SynGas
POC
H2
Hot SynGas
H2
CO
H2O
CO2
CO
Recover H2
O-
O-
Air
Air
O2 N2
Hot Air
Recover Heat
11Process DescriptionTurn it over to Nick
Reinhardt
12SOFC PFD
13Fuel Preparation - 100
14Desulfurizer (DS 101)
- 2 ppm H2S in natural gas feed
- H2S removed in DS-101 with disposable carbon
filters - 10 of CH4 fed to combustor
- 90 of CH4 fed fuel humidifier
15Fuel Humidifier (FH 102)
- 1.25 Kmol H20 per Kmol CH4 fed to FH-102
- Heat provided from combustor exhaust
16Fuel Preheater (HX 103)
- Heat provided from fuel cell exhaust
17Reformer (R 104)
- Equilibrium determined to be
- 85 CH4 ? CO
- 15 CH4 ? CO2
- CH4 H2O ? CO 3H2
- CH4 2H2O ? CO2 4H2
- Heat provided from reaction in combustor
18Combustor (COMB 105)
- Extent of reaction for combustion assumed to be
100 - CH4 2O2 ? CO2 2H2O
- Necessary O2 provided from fuel cell air exhaust
19SOFC PFD
20Air Handling and WGS - 200
21Air Compressor (COMP 224)
- Air intake for the system
- 6.65 standard cubic meters per minute flow
22Air Preheater (HX 223)
- Heat provided by water gas shift exhaust
23Water Gas Shift (WGS 222)
- CO H2O ? CO2 H2
- Equilibrium determined to be 94
24Air Side Heat Recovery (HX 221)
- Heat provided by combustor exhaust
25SOFC PFD
26Fuel Cell - 300
27Fuel Cell (FC 331)
28SOFC PFD
29Post Processing
30Fuel Exhaust Condenser (HX 443)
- Uses external cooling source
- Condenses process water from exhaust gases
- Condensed water flows to WP-441
- Non-condensible exhaust flows to comp-445 and PSA
system - 99.5 of water is condensed
31Chiller (Ref 446)
- Provides cold water utility for HX-443
- Supply temp 0C
- Return temp 50C
- Rate 1.8 gpm
- Cooling 35,500 kJ/hr (9.9kW)
- Power 2.4 kW to run
32PSA Compressor (COMP 445)
- Provides dried, compressed exhaust gas to the PSA
system. - 2 stage compressor
33Pressure Swing Adsorber (PS 442)
- Uses custom adsorbant to purify hydrogen
- 80-90 recovery possible
- 99.9 purity on the product gas achievable with
slight recovery cost - Delivery pressure 20 bar
- Recovered Hydrogen .177 kmol/hr _at_ 90
34Hydrogen Compressor (COMP 447)
- Produced compressed hydrogen for sale
- Multi-stage compressor
- Pressure input 2-20 bar
- Pressure output 200 bar
35Water Purifier (WP 441)
- Basic cartridge filtration of incoming water
(either city supply or process supply) - Excess process water discharged to city sewer
36Water Pump (P 444)
- Supplies water to section 100 fuel humidifier
37Process and Equipment DesignTurn it over to
Chris Boudreaux
38SOFC PFD
39(No Transcript)
40(No Transcript)
41Equipment Assumptions
- All equipment was assumed to be stainless steel
42Heat Exchangers
- 10 approach temperature was used
- q UAF?Tlm
- F 0.9
- U 30 W/m2C
- ?Tlm (?T2 ?T1) / ln(?T2 / ?T1)
43Pumps and Compressors
- Power mz1RT1(P2/P1a 1)/a
- T1 inlet temp
- R Gas Constant
- Z1 compressibility
- m molar flow rate
- a (k-1)/k
- k Cp / Cv
44Other
- PSA, WGS, and desulfurizer have purchased
internals
45Economic AnalysisTurn it over to Wayne Johnson
46Economic Components
- Capital Costs
- Operating Costs
- Income Generated
- Payback Period
- Return on Investment
47Capital Cost Assumptions
- Cap Cost Program
- Stainless Steel
- Minimum Size Basis for all components
48Capcost Output
49Capital Costs
50Sizing Adjustments
- Equation from Text
- Ca/Cb (Aa/Ab)n
- Ca Cost of Desired Equipment
- Cb Cost of Base Equipment
- Aa Desired Cost Attribute
- Ab Base Cost Attribute
- n Cost Exponent (0.6)
51Sizing Adjustments
- Ab 450 kilowatts Cb 150,000
- Aa 1.2 kilowatts n 0.6
- Total adjusted cost 4,282
52Adjusted Costs
53Total Installation
- Total Equipment cost 51,474
- Lang factor 4.74 for fluid processing plant
- Total Installation 243,985
54Operating Costs
- Fuel 158,000 BTU/hr
- 0.158 therms/hr
- Fuji Hunt price 7.7/therm
- Labor 24 hr coverage with 4 shifts
- Average salary 30K
- Benefits 2x salary
- Total 240,000 annually
- Use contract labor
55Income
- Electricity 25kW
- Price 0.05/kWhr
- Hydrogen 0.18 kmol/hr
- .35 kg/hr
- Fuji Hunt price 11.64/kg
56Total Income vs. Expense
57Investment Results
- Non-discounted Payback
- 7.4 Years
- Return on Investment
- 13.5
58Conclusions
- Materials are expensive
- Operation is expensive
- Electricity costs are low
- Fuel cell not recommended at this time
59Questions?
60Alternative
- CH4 2H2O CO2 4H2
- Currently 0.2kmol CH4 0.18kmol of H2
- Revenue 35,000 in H2 sales
- Potential revenue at 50 H2 recovery
70,000
61Alternative
- Remove fuel cell
- Optimize reformer and WGS for H2 generation
- H2 is only product
62 63Fuel Cell
Heat
. Objective Develop and demonstrate a 25 kW, grid
parallel, solid oxide fuel cell system that
coproduces hydrogen. , the installation be
configured to simultaneously and efficiently
produce hydrogen from a commercial natural gas
feedstream in addition to electricity. This
ability to produce both hydrogen and electricity
at the point of use provides an early and
economical pathway to hydrogen production. .
Ceramic processing and challenges in the design
and manufacturing process of SOFCs will be
addressed . The amount of hydrogen that the
unit produces may be controlled by the adjusting
the natural gas flow at steady power production
(i.e., adjusting the fuel utilization). A nominal
production rate of 25 kg of hydrogen per day
falls within the expected upper and lower
utilization limits for 25 kW electricity
production. The system produces a hydrogen-rich
exhaust stream that will be purified using a
Pressure Swing Absorption (PSA) unit. The
hydrogen flow and purity are interdependent. It
is expected that purity gt98 is achievable for
flows of 2-3 kg/day. Critical impurities, such as
CO and CO2 will be measured. It is not clear
that this size system makes sense for commercial
production. We are looking at a 25 kW module as a
building block for commercial production to begin
in 2006. The size of the 25 kW module is
estimated to be smaller than a 5 ft cube. The
cost of early commercial systems is expected to
be lt10K/kW