Title: Supreme Court Directs Environment Approval first
1Phone - 080 40155666, 8494 9301 72 Email -
contact_at_gruhakalyan.com
Supreme Court Directs Environment Approval First
http//gruhakalyan.com
2Phone - 080 40155666, 8494 9301 72 Email -
contact_at_gruhakalyan.com
Supreme Court Directs Environment Approval
Real estate companies in the top metro cities of
the country opined that the environment clearance
is a must for their projects and the local
authorities approve the plans of buildings only
after the project is approved by the environment
department. The Supreme Court in its order has
directed that environment clearance has to be
taken first before even the work commences.
This decree was passed after an observation on
the 15th of January, 2016.There have been
frequent disputes between the environment
department and the developers.
http//gruhakalyan.com
3Phone - 080 40155666, 8494 9301 72 Email -
contact_at_gruhakalyan.com
- In a recent dispute on July 2015 the National
Green Tribunal (NGT) had disallowed the office
memo of the environment ministry which directed
the builder to rectify their mistake while the
building construction was still on. - According to the Tribunal the memo issued by the
environment ministry had altered and did not
conform to the Environment Protection Act. 1986
and neither did it adhere to the EIA Notification
of 2006. - But the order of the NGT was stayed by the
division bench constituted earlier. The division
bench was headed by the then Chief Justice of
India, HL Dattu.
http//gruhakalyan.com
4Phone - 080 40155666, 8494 9301 72 Email -
contact_at_gruhakalyan.com
- On the decision taken by the bench on January
15ththe apex court said that there is a need to
reexamine the earlier order issued by it. In this
the apex court backed the order of the NGT that
any housing project cannot commence without the
green clearance. - But in their opinion the developers of all the
major metros like Bangalore, Noida, Mumbai,
Gurgaon and few others said that they have always
taken the environment clearance for the building
plan to be sanctioned. - Let us look at the various norms in the other
cities of India and see what was prevalent in
these cities. As per the builders of Gurgaon the
developers have to apply for a licensefor the
land once the land is bought from the owner.
http//gruhakalyan.com
5Phone - 080 40155666, 8494 9301 72 Email -
contact_at_gruhakalyan.com
- Once the license is obtained one has to apply for
the environment clearance. - In Noida the norm is that after any land is
allotted by the Noida local authorities the
builder applies for the environment clearance as
that is one of the pre-condition for obtaining
the building plans for being sanctioned by the
local authorities. - The President of the Confederation of Real Estate
Developers Association of India (CREDAI),
National Capital region said that local
government does not clear the plans for
construction unless the plan is first of all
being cleared by the environment department.
http//gruhakalyan.com
6Phone - 080 40155666, 8494 9301 72 Email -
contact_at_gruhakalyan.com
- In Haryana there is a circular and a clause as
per the local laws which make the green clearance
compulsory in the approval process of the
building plan. - The majority of the builders and the developers
association opine that getting an environment
clearance is an unavoidable problem for the
builders and is the main reason for the delays in
completing the projects. - The experts opine that on an average the time
taken to get environment clearance is roughly 18
months depending on the city.The developers opine
that environment clearance takes the longest time
and this time has to be shortened to reduce the
completion time and make the products more
affordable for the consumers.
http//gruhakalyan.com
7Phone - 080 40155666, 8494 9301 72 Email -
contact_at_gruhakalyan.com
- The developers from Mumbai opined that most of
the projects of Mumbai require the CRZ (Coastal
Regulatory Zone) clearance whereas some of the
sub urban areas require adhering to the forest
related regulations. - In the coastal areas and Mumbai no project can
start construction unless the builder obtains
approvals from related authorities like the
Maharashtra Coastal Zone Authority (MCZMA). - This is also a state level subsidiary authority
under the ministry of environment of forests.
Such special zones also need such approvals which
makes the time of approval even longer opined the
realtors of Mumbai.
http//gruhakalyan.com
8Phone - 080 40155666, 8494 9301 72 Email -
contact_at_gruhakalyan.com
- According to the Tribunal the memo issued by the
environment ministry had altered and did not
conform to the Environment Protection Act. 1986
and neither did it adhere to the EIA Notification
of 2006. - The majority of the builders and the developers
association opine that getting an environment
clearance is an unavoidable problem for the
builders and is the main reason for the delays in
completing the projects. - The majority of the builders and the developers
association opine that getting an environment
clearance is an unavoidable problem for the
builders and is the main reason for the delays in
completing the projects.
http//gruhakalyan.com
9Phone - 080 40155666, 8494 9301 72 Email -
contact_at_gruhakalyan.com
Property Buying Tips
- Pre-launch Flats Vs. Ready-to-move Apartments
- Now is the right time to buy a house or property
in Bangalore - How to buy a flat being Cautious to avoid Problems
Real Estate Marketing News
- Increase of Smaller Homes in Indian Realty Market
- Overview of Bangalore Real Estate Market at a
Glance - The accentuating prospects of Devenahalli
http//gruhakalyan.com