Construction Engineering 380 - PowerPoint PPT Presentation

1 / 9
About This Presentation
Title:

Construction Engineering 380

Description:

Unforeseen conditions are most commonly found in remodeling work and subsurface ... If the contract is silent, then ONLY unforeseen conditions can arise ... – PowerPoint PPT presentation

Number of Views:56
Avg rating:3.0/5.0
Slides: 10
Provided by: civ89
Category:

less

Transcript and Presenter's Notes

Title: Construction Engineering 380


1
Construction Engineering 380
  • Subsurface Conditions

2
Unforeseen Conditions
  • Unforeseen conditions are most commonly found in
    remodeling work and subsurface work (excavation,
    retention, mining, environmental remediation)
  • Almost all construction places responsibility for
    unforeseen conditions on the owner through a
    variety of methods, most following the federal
    DSC clause guidelines. (the owner pays one way or
    another either through increased cost upfront or
    change orders)

3
Differing Unforeseen Conditions
  • Differing Site Conditions- actual conditions
    differ from the representation made in the
    contract documents (MSP airport)
  • Unforeseen Condition- unusual situation not
    reasonably anticipated based on contract documents

4
Differing Unforeseen Conditions
  • Contractor is awarded damages for differing site
    conditions
  • Contractor NOT awarded damages for unforeseen
    site conditions unless they rise to the level of
    practical impossibility, commercial
    senselessness, or there is contract language
    transferring risk (common)

5
Differing Unforeseen Conditions
  • If the contract is silent, then ONLY unforeseen
    conditions can arise
  • Unknown physical condition of an unusual nature
    that differs materially from those ordinarily
    encountered (buried tank example)
  • Doesnt cover weather, economic condition, market
    factors, etc.

6
Differing Unforeseen Conditions
  • Owner is liable only if
  • Risk transfer clause is executed a priori
  • Objective or practical impossibility
  • Tort claim arises
  • Ambiguous contract could be interpreted as
    differing (not unforeseen)

7
Differing Unforeseen Conditions
  • Unforeseen site conditions clause is standard in
    most contracts. Can be invoked if
  • Condition is unknown to contractor
  • Condition is unusual
  • Condition is materially different

8
Differing Unforeseen Conditions
  • Objective or practical impossibility was covered
    in previous lecture (commercial senselessness)
  • Nondisclosure- owner has a duty to report (widely
    recognized by most courts). Soil borings is
    example
  • Tort claim- additional contract clauses to deal
    with torts (fraud, negligence, misrepresentation)

9
Differing Unforeseen Conditions
  • Ambiguity- need interpretation of whether the
    condition is unforeseen or differing (transfer
    clause eliminates distinction in most cases)
  • Prebid site inspection- required in most
    contracts. Visible conditions cannot be later
    claimed as unforeseen or differing
Write a Comment
User Comments (0)
About PowerShow.com