Fitter Snacker Module 10 - PowerPoint PPT Presentation

1 / 41
About This Presentation
Title:

Fitter Snacker Module 10

Description:

... via Material Requirements Planning (MRP), is used to create planned orders ... cannot be created unless all raw materials (oats, wheat germ, cinnamon, etc. are ... – PowerPoint PPT presentation

Number of Views:626
Avg rating:3.0/5.0
Slides: 42
Provided by: busi210
Category:
Tags: fitter | module | snacker

less

Transcript and Presenter's Notes

Title: Fitter Snacker Module 10


1
Fitter Snacker Module 10
  • Setup for Production

2
Fitter Snacker Configuration
3
Plant Parameters
  • Configuring the SAP R/3 system for production is
    one of the most challenging tasks in R/3
    configuration
  • CO will not be configured for production in this
    exercise
  • Configuring the CO module to accurately track
    manufacturing costs is extremely challenging
  • Requires balance between accurate cost
    allocations and data collection requirements. To
    much detail can make the SAP system difficult to
    use, which means it is not likely to be used
    correctly.

4
Planning vs. Scheduling
  • Configuring the production planning (PP) module
    is complicated by the fact that planning and
    scheduling are two separate, but highly related,
    activities.
  • Planning, typically implemented via Material
    Requirements Planning (MRP), is used to create
    planned orders and purchase requisitionssuggestio
    ns by the SAP system as to what should be
    produced on the shop floor or procured from
    suppliers (vendors), respectively.

5
Planning vs. Scheduling
  • Scheduling is the process of converting planned
    orders into production orders and purchase
    requisitions into purchase orders, then managing
    these orders in detail.

Planned
Scheduled
Planned Order
Production Order
Internal Procurement
External Procurement
Purchase Requisition
Purchase Order
6
Floats
  • In both planning and scheduling, floats can be
    added to planning times to provide for a buffer
    against uncertainty. The production lead time
    for a material might be 12 days. Of that 12
    days, 10 days might be the expected production
    time with a float of 2 days added to allow for
    production disruptions.
  • Floats are organized in the SAP R/3 system using
    Schedule Margin Keys.

7
Floats
  • Four floats are defined in a schedule/margin key
  • Opening period Workdays prior to order start.
  • Float Before Production Workdays between order
    start and scheduled start.
  • Float after Production Workdays between order
    due date and scheduled finish date.
  • Release Period Workdays in release period.

8
Planning Parameters
  • The MRP 2 view of the material master gives
  • In-house production time
  • Goods Receipt (GR) processing time
  • Schedule Margin Key, which gives
  • Opening period
  • Float Before Production
  • Float After Production
  • Release Period

9
Planning Parameters
Material Master MRP 2 View
Schedule Margin Key
10
MRP
  • Planning, which is done by the MRP process,
    needs
  • In-house production time
  • GR processing time
  • Opening Period
  • The MRP process will determine the order start
    and order finish date, as well as the planned
    opening date
  • The planned opening date can be used by planners
    to convert planned orders to production orders by
    groups rather than individually. The MRP planner
    can convert groups of planned orders based on the
    planned opening date.

11
Material Requirements Planning
Demand
GR process
In-house production
Opening Period
Available for Planning
Order Start
Planned Opening Date
Order Finish
12
Example in SAP
Demand (Independent Requirement)
Available for Planning
Order start Order finish Planned opening date
Planned Order Detail
13
Production Order Scheduling
  • The float before production and float are used to
    calculated the scheduled start and scheduled
    finish dates when the planned order is converted
    into a production order.
  • The float before production is a start float. It
    has two functions
  • It can compensate for delays in the staging of
    the material components.
  • If there is a capacity bottleneck at the work
    centers involved, the production dates can be
    moved forward in the future. In this way it
    serves as a float for capacity leveling.

14
Production Order Scheduling
  • The float after production is a finish float. It
    is used to compensate for unexpected disturbances
    in the production process, so that they do not
    delay the scheduled finish date.
  • The system calculates the scheduled start of the
    order by adding the float before production to
    the order start date. It calculates the scheduled
    finish of the order by subtracting the float
    after production from the order finish date.

15
Production Order Scheduling
In-house production
Float before Production
Float after Production
Release Period
Scheduled Start
Scheduled Finish
Scheduled Release
Order Start
Order Finish
16
Production Order Scheduling
  • Note how the float before production and float
    after production are used to calculate the
    scheduled start and scheduled finish time. The
    in-house production time specified on the MRP 2
    View of the material master should be the sum of
    the expected processing time plus the float
    before production plus the float after production.

17
Release Period
  • The SAP system can be configured so that a
    production order is released as soon as it is
    created. This means that the production facility
    can begin production.
  • The SAP system can also be configured to make the
    release of the production order a separate step.
    In this case, the SAP system deducts the number
    of days defined in the release period from the
    scheduled start of the order to determine the
    scheduled release date of the order. This date
    can be used by the production scheduler to
    perform collective release, i.e., release a group
    of production orders based on the scheduled
    release date.

18
Number Ranges
  • Every transaction in SAP is numbered. Some
    companies are very interested in the format of
    numbers assigned to different objects. The SAP
    R/3 system gives the user the ability to define
    different number ranges (number of digits,
    numeric or alphanumeric, starting number, etc.)
    and then assign them to different objects.

19
Number Ranges
  • In defining plant parameters, number ranges must
    be defined and assigned to
  • Planned orders
  • Reservations/Dependent requirements
  • Purchase requisitions
  • MRP lists
  • Simulated dependent requirement

20
MRP Controllers
  • In the SAP system, the person designated to
    manage the production and inventory levels for a
    material is called the MRP Controller.
  • Each material can be assigned to a particular MRP
    Controller.
  • The MRP Controller is used to select materials
    for reports like the Stock/requirements list.
  • The Stock/requirements list, is an interactive
    transaction for managing the production and
    inventory levels for a material

21
Production Scheduling Profile
  • The production scheduling profile determines how
    production scheduling is to be carried out in the
    plant. Settings in the production scheduling
    profile control things like
  • When production orders are released for
    production (upon creation, for example).
  • When production orders are scheduled (on release,
    for example).

22
Production Scheduler
  • Similar to the MRP Controller, a Production
    Scheduler must be defined in the SAP system to
    control detailed production scheduling for a
    material. A production scheduling profile is
    assigned to the Production Scheduler, and the
    Production Schedule is defined in the Work
    Scheduling view of the Material Master.

23
Material Availability Check
  • When the MRP system creates a planned order, it
    can also check whether the components and
    sub-assemblies required to complete the planned
    order will be available.

24
Bill of Material
  • The Bill of Material (BOM) defines the
    relationship between materials that make up an
    assembled product
  • It is the recipe for
  • a material

25
Routings
  • Routings define the relationship between a
    material and the sequence of workcenters
    (operations) that are required to produce the
    material. Routings determine
  • The operations (work steps) to be carried out
    during production of a material
  • The activities to be performed in the operations
    as a basis for determining dates (start, finish,
    available, etc.), capacity requirements, and
    costs for a production order
  • The use of materials during production
  • The use of work centers
  • The quality checks to be carried out during
    production

26
BOM and Routing Selection ID
  • Different routings and BOMs may be defined for a
    material. These routings may be applicable for
    different production quantities, for example.
    When products change, the BOM and/or routing may
    change, so BOMs and routings can have validity
    periods to define when the changes occur.
  • BOM and Routing Selection IDs determine how the
    SAP system will find the correct BOM and routing
    for a production order.

27
BOM and Routing Selection ID
  • With the routing selection ID 01, when an order
    is created, the system looks for a routing that
    is valid for the date the production order is
    being created and the lot size of the production
    order. If more than one routing is valid for a
    production order, the SAP system selects the
    first valid routing.
  • Similarly, with BOM selection ID 01, the system
    looks for a BOM for the material with the correct
    status (active), lot size and validity date.

28
Creating Production Orders
29
Planning Horizon
  • The planning horizon (measured in days)
    determines how far in the future the MRP planning
    process looks to create production orders.
  • A production scheduler can structure the MRP
    process to create production orders for all
    demand (forecast demand, customer orders)
    recorded in the system, or only that demand that
    is within the number of days in the planning
    horizon into the future.

30
Production Order Availability Checks
  • For standard production order type PP01,
    availability checks can be specified on a
    plant-by-plant basis.
  • Availability checks can be performed for
  • Materials availability of component materials
  • Production Resources and Tools (PRT)
  • Production Capacity
  • Checks can be specified to be determined when a
    production order is created, a production order
    is released, or both times.

31
Production Order Availability Checks
  • If availability checks are specified, then
    production orders cannot be created if the
    availability check is not passed.
  • For example, if a material availability check is
    specified at order creation, then a production
    order for a batch of snack bar dough cannot be
    created unless all raw materials (oats, wheat
    germ, cinnamon, etc. are in stock in sufficient
    quantities.

Dough NRGA (lb)
Oats (lb)
Wheat Germ (lb)
Cinnamon (lb)
Nutmeg (lb)
Cloves (lb)
Honey (gal)
Vit/Min Powder (lb)
Carob Chips (lb)
Raisins (lb)
Canola (gal)
32
Forward and Backward Scheduling
  • Two basic methods of production order scheduling
    are available
  • Forward Scheduling, where a production order is
    scheduled to start immediately and finish as soon
    as possible
  • Backward Scheduling, where the scheduling begins
    at the due date and works backward.
  • Most students use backward scheduling
  • Backward scheduling can lead to problems if there
    is not enough float time in the schedule to
    account for disruptions

33
Backward Scheduling
Planned Finish
Scheduled Finish
Scheduled Start
Planned Start
Today
Float after production
In-house production time
Float before production
34
Forward Scheduling
Planned Finish
Scheduled Finish
Scheduled Start
Today
Planned Start
Float after production
In-house production time
Float before production
35
Material Master Views for Production
  • The MRP views in the Material Master define a
    range of parameters for planning.
  • There are four MRP views (MRP 1, MRP 2, MRP 3 and
    MRP 4) that contain Production Planning
    Parameters
  • Production scheduling parameters are entered in
    the Work Scheduling View

36
MRP 1 View
MRP Type How the material is planned PDUsing
MRP logic VBConsumption-based planning Lot
Size How many units to make in a production
order FXFixed, make the fixed lot
size EXLot-for-lot, make exactly the quantity
required MRP Controller Controller responsible
for this material
37
MRP 2 View
In-house production Number of days required
to produce the material GR processing time
Number of days required to process the
material after production before it can
be used. May allow for quality inspection,
for example. Schedule margin key Set of floats
used.
38
MRP 3 View
Strategy group setting for how
inventory, forecasts and customer orders
affect the MRP planning process. Tot. repl.
lead time Total replenishment lead time. This
is used in the sales order process. If there is
no stock on hand for this material, then
the sales order process will assume the
material will be available in this number of
days if an order is placed. The SAP system
will calculate a promised delivery date using
the total replenishment lead time as well as a
delivery time calculated from other system
settings.
39
Work Scheduling View
Production Scheduler Production
scheduler responsible for this material. Prod.
Sched. Profile Production scheduling profile
for this material. As described previously, the
production scheduler and production
scheduling profile determines the way
production orders are created and managed.
40
MRP Run
  • In Single-item, Single-level planning, only the
    material is planned, not other materials that may
    be required to make the material
  • For example, if single-item, single-level
    planning is used on the dough material, then only
    the dough is planned and not the materials needed
    to make dough, like oats, wheat germ, etc.

A number of parameters are set that in MRP
planning to determine how planning is to proceed
and what it is to produce (planned orders
vs. purchase requisitions, for example).
41
Stock/Requirements List
  • The Stock/requirements list is an interactive
    report that provides a comprehensive set of
    information about a material, including
    inventory, planned orders, forecast demand,
    customer orders.
  • In addition, by double-clicking on specific
    items, the user can access a variety of data like
    material masters, detailed stock overviews,
    production order details, etc.
  • The Stock/requirements list is the primary tool
    used by planners and schedulers.
Write a Comment
User Comments (0)
About PowerShow.com