Title: Fitter Snacker Module 10
1Fitter Snacker Module 10
2Fitter Snacker Configuration
3Plant Parameters
- Configuring the SAP R/3 system for production is
one of the most challenging tasks in R/3
configuration - CO will not be configured for production in this
exercise - Configuring the CO module to accurately track
manufacturing costs is extremely challenging - Requires balance between accurate cost
allocations and data collection requirements. To
much detail can make the SAP system difficult to
use, which means it is not likely to be used
correctly.
4Planning vs. Scheduling
- Configuring the production planning (PP) module
is complicated by the fact that planning and
scheduling are two separate, but highly related,
activities. - Planning, typically implemented via Material
Requirements Planning (MRP), is used to create
planned orders and purchase requisitionssuggestio
ns by the SAP system as to what should be
produced on the shop floor or procured from
suppliers (vendors), respectively.
5Planning vs. Scheduling
- Scheduling is the process of converting planned
orders into production orders and purchase
requisitions into purchase orders, then managing
these orders in detail.
Planned
Scheduled
Planned Order
Production Order
Internal Procurement
External Procurement
Purchase Requisition
Purchase Order
6Floats
- In both planning and scheduling, floats can be
added to planning times to provide for a buffer
against uncertainty. The production lead time
for a material might be 12 days. Of that 12
days, 10 days might be the expected production
time with a float of 2 days added to allow for
production disruptions. - Floats are organized in the SAP R/3 system using
Schedule Margin Keys.
7Floats
- Four floats are defined in a schedule/margin key
- Opening period Workdays prior to order start.
- Float Before Production Workdays between order
start and scheduled start. - Float after Production Workdays between order
due date and scheduled finish date. - Release Period Workdays in release period.
8Planning Parameters
- The MRP 2 view of the material master gives
- In-house production time
- Goods Receipt (GR) processing time
- Schedule Margin Key, which gives
- Opening period
- Float Before Production
- Float After Production
- Release Period
9Planning Parameters
Material Master MRP 2 View
Schedule Margin Key
10MRP
- Planning, which is done by the MRP process,
needs - In-house production time
- GR processing time
- Opening Period
- The MRP process will determine the order start
and order finish date, as well as the planned
opening date - The planned opening date can be used by planners
to convert planned orders to production orders by
groups rather than individually. The MRP planner
can convert groups of planned orders based on the
planned opening date.
11Material Requirements Planning
Demand
GR process
In-house production
Opening Period
Available for Planning
Order Start
Planned Opening Date
Order Finish
12Example in SAP
Demand (Independent Requirement)
Available for Planning
Order start Order finish Planned opening date
Planned Order Detail
13Production Order Scheduling
- The float before production and float are used to
calculated the scheduled start and scheduled
finish dates when the planned order is converted
into a production order. - The float before production is a start float. It
has two functions - It can compensate for delays in the staging of
the material components. - If there is a capacity bottleneck at the work
centers involved, the production dates can be
moved forward in the future. In this way it
serves as a float for capacity leveling.
14Production Order Scheduling
- The float after production is a finish float. It
is used to compensate for unexpected disturbances
in the production process, so that they do not
delay the scheduled finish date. - The system calculates the scheduled start of the
order by adding the float before production to
the order start date. It calculates the scheduled
finish of the order by subtracting the float
after production from the order finish date.
15Production Order Scheduling
In-house production
Float before Production
Float after Production
Release Period
Scheduled Start
Scheduled Finish
Scheduled Release
Order Start
Order Finish
16Production Order Scheduling
- Note how the float before production and float
after production are used to calculate the
scheduled start and scheduled finish time. The
in-house production time specified on the MRP 2
View of the material master should be the sum of
the expected processing time plus the float
before production plus the float after production.
17Release Period
- The SAP system can be configured so that a
production order is released as soon as it is
created. This means that the production facility
can begin production. - The SAP system can also be configured to make the
release of the production order a separate step.
In this case, the SAP system deducts the number
of days defined in the release period from the
scheduled start of the order to determine the
scheduled release date of the order. This date
can be used by the production scheduler to
perform collective release, i.e., release a group
of production orders based on the scheduled
release date.
18Number Ranges
- Every transaction in SAP is numbered. Some
companies are very interested in the format of
numbers assigned to different objects. The SAP
R/3 system gives the user the ability to define
different number ranges (number of digits,
numeric or alphanumeric, starting number, etc.)
and then assign them to different objects.
19Number Ranges
- In defining plant parameters, number ranges must
be defined and assigned to - Planned orders
- Reservations/Dependent requirements
- Purchase requisitions
- MRP lists
- Simulated dependent requirement
20MRP Controllers
- In the SAP system, the person designated to
manage the production and inventory levels for a
material is called the MRP Controller. - Each material can be assigned to a particular MRP
Controller. - The MRP Controller is used to select materials
for reports like the Stock/requirements list. - The Stock/requirements list, is an interactive
transaction for managing the production and
inventory levels for a material
21Production Scheduling Profile
- The production scheduling profile determines how
production scheduling is to be carried out in the
plant. Settings in the production scheduling
profile control things like - When production orders are released for
production (upon creation, for example). - When production orders are scheduled (on release,
for example).
22Production Scheduler
- Similar to the MRP Controller, a Production
Scheduler must be defined in the SAP system to
control detailed production scheduling for a
material. A production scheduling profile is
assigned to the Production Scheduler, and the
Production Schedule is defined in the Work
Scheduling view of the Material Master.
23Material Availability Check
- When the MRP system creates a planned order, it
can also check whether the components and
sub-assemblies required to complete the planned
order will be available.
24Bill of Material
- The Bill of Material (BOM) defines the
relationship between materials that make up an
assembled product - It is the recipe for
- a material
25Routings
- Routings define the relationship between a
material and the sequence of workcenters
(operations) that are required to produce the
material. Routings determine - The operations (work steps) to be carried out
during production of a material - The activities to be performed in the operations
as a basis for determining dates (start, finish,
available, etc.), capacity requirements, and
costs for a production order - The use of materials during production
- The use of work centers
- The quality checks to be carried out during
production
26BOM and Routing Selection ID
- Different routings and BOMs may be defined for a
material. These routings may be applicable for
different production quantities, for example.
When products change, the BOM and/or routing may
change, so BOMs and routings can have validity
periods to define when the changes occur. - BOM and Routing Selection IDs determine how the
SAP system will find the correct BOM and routing
for a production order.
27BOM and Routing Selection ID
- With the routing selection ID 01, when an order
is created, the system looks for a routing that
is valid for the date the production order is
being created and the lot size of the production
order. If more than one routing is valid for a
production order, the SAP system selects the
first valid routing. - Similarly, with BOM selection ID 01, the system
looks for a BOM for the material with the correct
status (active), lot size and validity date.
28Creating Production Orders
29Planning Horizon
- The planning horizon (measured in days)
determines how far in the future the MRP planning
process looks to create production orders. - A production scheduler can structure the MRP
process to create production orders for all
demand (forecast demand, customer orders)
recorded in the system, or only that demand that
is within the number of days in the planning
horizon into the future.
30Production Order Availability Checks
- For standard production order type PP01,
availability checks can be specified on a
plant-by-plant basis. - Availability checks can be performed for
- Materials availability of component materials
- Production Resources and Tools (PRT)
- Production Capacity
- Checks can be specified to be determined when a
production order is created, a production order
is released, or both times.
31Production Order Availability Checks
- If availability checks are specified, then
production orders cannot be created if the
availability check is not passed. - For example, if a material availability check is
specified at order creation, then a production
order for a batch of snack bar dough cannot be
created unless all raw materials (oats, wheat
germ, cinnamon, etc. are in stock in sufficient
quantities.
Dough NRGA (lb)
Oats (lb)
Wheat Germ (lb)
Cinnamon (lb)
Nutmeg (lb)
Cloves (lb)
Honey (gal)
Vit/Min Powder (lb)
Carob Chips (lb)
Raisins (lb)
Canola (gal)
32Forward and Backward Scheduling
- Two basic methods of production order scheduling
are available - Forward Scheduling, where a production order is
scheduled to start immediately and finish as soon
as possible - Backward Scheduling, where the scheduling begins
at the due date and works backward. - Most students use backward scheduling
- Backward scheduling can lead to problems if there
is not enough float time in the schedule to
account for disruptions
33Backward Scheduling
Planned Finish
Scheduled Finish
Scheduled Start
Planned Start
Today
Float after production
In-house production time
Float before production
34Forward Scheduling
Planned Finish
Scheduled Finish
Scheduled Start
Today
Planned Start
Float after production
In-house production time
Float before production
35Material Master Views for Production
- The MRP views in the Material Master define a
range of parameters for planning. - There are four MRP views (MRP 1, MRP 2, MRP 3 and
MRP 4) that contain Production Planning
Parameters - Production scheduling parameters are entered in
the Work Scheduling View
36MRP 1 View
MRP Type How the material is planned PDUsing
MRP logic VBConsumption-based planning Lot
Size How many units to make in a production
order FXFixed, make the fixed lot
size EXLot-for-lot, make exactly the quantity
required MRP Controller Controller responsible
for this material
37MRP 2 View
In-house production Number of days required
to produce the material GR processing time
Number of days required to process the
material after production before it can
be used. May allow for quality inspection,
for example. Schedule margin key Set of floats
used.
38MRP 3 View
Strategy group setting for how
inventory, forecasts and customer orders
affect the MRP planning process. Tot. repl.
lead time Total replenishment lead time. This
is used in the sales order process. If there is
no stock on hand for this material, then
the sales order process will assume the
material will be available in this number of
days if an order is placed. The SAP system
will calculate a promised delivery date using
the total replenishment lead time as well as a
delivery time calculated from other system
settings.
39Work Scheduling View
Production Scheduler Production
scheduler responsible for this material. Prod.
Sched. Profile Production scheduling profile
for this material. As described previously, the
production scheduler and production
scheduling profile determines the way
production orders are created and managed.
40MRP Run
- In Single-item, Single-level planning, only the
material is planned, not other materials that may
be required to make the material - For example, if single-item, single-level
planning is used on the dough material, then only
the dough is planned and not the materials needed
to make dough, like oats, wheat germ, etc.
A number of parameters are set that in MRP
planning to determine how planning is to proceed
and what it is to produce (planned orders
vs. purchase requisitions, for example).
41Stock/Requirements List
- The Stock/requirements list is an interactive
report that provides a comprehensive set of
information about a material, including
inventory, planned orders, forecast demand,
customer orders. - In addition, by double-clicking on specific
items, the user can access a variety of data like
material masters, detailed stock overviews,
production order details, etc. - The Stock/requirements list is the primary tool
used by planners and schedulers.