Title: Wednesday, January 7th
1Wednesday, January 7th
- AGENDA
- Continue my lecture on modeling cost behavior and
answer questions - Comment on Go and Igo assignments
- Lecture, discussion, and illustration of flexible
budgeting - Lecture, discussion, and illustrations of
budgeted cost rates time permitting
2Cost Behavior
- Monday we said one of the key issues in
managerial accounting is to determine the factors
that drive the cost of an activity. We are
continuing that discussion today.
3Discontinuous Costs
- Thus far we have assumed that costs are
continuous (i.e., cost functions contain no jumps
or gaps). As a starting point, this is a useful
assumption. Even when this assumption is not
satisfied we can be as accurate as necessary.
4Segmented Linear Costs
- A common variation on strictly variable costs is
a cost function that contains multiple linear
segments. At a specific level of volume, the
variable cost per unit (the slope) changes.
There could be several such changes over the
range of possible volumes.
5Example - Segmented Cost
- Think about labor costs. At some level of
volume, a company would have to begin to pay
overtime. At an even higher level of volume, the
company would have to start a second work shift
and pay what is called a shift premium, etc.
6Total Segmented Var. Cost
Q2
Q3
0
7Total Segmented Var. Cost
Total cost
Q2
Q3
0
Activity Volume
8Segmented Variable Cost
- Total variable cost function
- TC v1 Q for 0 Q Q2 (4)
9Segmented Variable Cost
- Total variable cost function
- TC v1 Q for 0 Q Q2 (4)
- TC v1 Q v2 (Q Q2)
- for 0 Q2 Q Q3 (5)
-
10Segmented Variable Cost
- Total cost function
- TC v1 Q for 0 Q Q2 (4)
- TC v1 Q v2 (Q Q2)
- for Q2 Q Q3 (5)
- TC v1 Q v2 (Q Q2)
- v3 (Q Q3) for
- 0 Q2 Q3 Q (6)
11Total Segmented Var. Cost
- Notice that v3 is an increment to v2 and v2 is
an increment to v1
12Total Segmented Var. Cost
- In per-unit terms, the unit variable cost is
increasing in jumps at specified levels of volume
as follows - vT is v1 for 0 Q Q2
- vT is v1 v2 for Q2 Q Q3
- vT is v1 v2 v3 for Q3 Q
13Total Segmented Var. Cost
- To develop an Excel version of the above formula
for segmented variable costs that will work for
any volume level, you will need - The IF-function, and
- and the GESTEP function.
14If-Statement
- An if-statement is required to determine if the
activity volume level is above the base volume
level. The base volume is likely to be the
smallest value of the relevant volume
interval--zero or a positive number.
15Relevant Volume Interval
Relevant Interval
Total cost
Q2
Q3
Q1
Activity Volume
16Total Cost Functions
- Format of an if-statement
- IF(logical test, value if true, value if false)
Test of a condition
Value or formula if condition is true
Value or formula if condition is false
17GESTEP Function
- When there are multiple linear segments within
the relevant interval, or multiple relevant
intervals, we need multiple, nested
if-statements, or some other function. For our
purposes, the simplest approach involves the
GESTEP function.
18GESTEP Function
- The GESTEP function tests whether a number is
greater than a threshold value. - Format
- GESTEP(number, step value)
Number or formula
Threshold value number or formula
19GESTEP Function
- GESTEP(Q, Q1) returns the value of 0 if Q lt Q1,
and 1 if Q Q1 - For purposes of developing cost forecasting
formulas, one can use the GESTEP function to
determine if Q is greater than either Q2 or Q3
(slide 7).
20Excel Formulas
- Use the above information to develop the formulas
you need to complete the assigned homework.
21Semi-Fixed (Lumpy) Cost
- Next let us move to what may be the most common
situation, costs that increase in fixed amounts
with respect to increments in volume that may
range from small amounts of cost per whole unit
to very large amounts per millions of units.
22Total Semi-Fixed Cost
Total cost
Total cost curve
Activity Volume
23Semi-Fixed (stair-step) Cost
- The total amount of a semi-fixed cost increases
in stair-step fashion. To the extent that the
stair-steps take place at regular intervals of
volume, as in the following example, they can be
modeled easily.
24Example
- Suppose we employ an additional supervisor for
every 10 employees. If we must hire a minimum of
1 supervisor, and each earns 50,000 per year,
then the cost of super-vision varies with
employment volume as follows
25Total Cost for Example
- TC 50,000 ? of groups of up to 10
employees to be super- vised where 50,000 is
the size of each step increase in total
cost.
26Semi-fixed Cost Example
- Employment Supervisors Total Cost
- Case 1 1 1 50,000
- Case 2 10 1 50,000
- Case 3 11 2 100,000
- Case 4 19 2 100,000
- Case 5 20 2 100,000
- Case 6 21 3 150,000
27Computing the No. of Steps
- The problem is to compute the number of cost
steps involved for a given activity volume
level. Igo trailer Co., Yougo Trailer Co.,
Exercise 2-21, Wego Trailer Co., and Letsgo
Trailer Co. all involve the estimation of
step-fixed costs.
28Computing the No. of Steps
- While there are several approaches one might
take, the ROUNDUP function is a relatively
straight-forward approach. A description of the
ROUNDUP function follows.
29Semi-Fixed Costs
- General format of the ROUNDUP function
- ROUNDUP(number, num_digits)
No. to be rounded
No. of decimals
30ROUNDUP Function Format
- ROUNDUP(number, num_digits)
- ROUNDUP(expression, num_digits)
- ROUNDUP(Q/m, n), where
- Q the total number of units of the cost
driver and - m the number of cost driver units per step
31ROUNDUP Function Format
- Q/m is used to compute the number of step
increases, and - n tells Excel to round to n digits to the right
of the decimal point.
32Changing values of n
33ROUNDUP Function
- Since we want integers, we are going to be using
n 0 in our cost estimation equations
34Base Volumes
- Sometimes we want to start at the origin, and
other times we want to start with a different
base volume level. Is there an estimation
equation formulation that serves both purposes?
YES!
35Base Volumes
- For a step-fixed cost for which the total cost
increases in steps of FS dollars every m units
above a base volume of Q1 units, we have the
following partial formula - TC ROUNDUP((Q Q1)/m, 0)FS
36ROUNDUP Function Values
37Semi-fixed Cost Formula
- TC FS ? ROUNDUP(Q/m, 0)
- for Q gt 0 and m gt 0. (7)
38Approximating Semi-Fixed Cost
- Sometimes it may be convenient to use a linear
approximation of a semi-fixed cost for ease of
computations, or because of the preferences of a
user. - Intercept is where approximation line crosses the
y-axis - Slope is the rate of change
39Conservative
Expected
Optimistic
40Approximating Semi-Fixed Cost
- Conservative (high) estimate
- Intercept Fs
- Slope ?y / ?x
- Slope (Fs / m)
- Estimation equation
- TC Fs (Fs / m)Q
41Approximating Semi-Fixed Cost
- Expected value (unbiased) estimate
- Intercept Fs / 2
- Slope ?y / ?x
- Slope (Fs / m)
- Estimation equation TC Fs / 2 (Fs / m)Q
42Approximating Semi-Fixed Cost
- Optimistic estimate
- Intercept 0
- Slope ?y / ?x
- Slope (Fs / m)
- Estimation equation
- TC (Fs / m)Q
43Remember Economics?
- How does what we are learning relate to what we
learned in microeconomics? - Are these cost formulas the theoretically correct
versions or are they approximations?
44Total Cost (Micro)
Total cost
Total cost curve
Relevant range
Activity Volume
45Average Cost (Micro)
Average Unit Cost
Relevant range
Unit cost curve
Volume
46Cost Forecasting Formulas
- Fixed TC F (1)
- Variable TC vQ (2)
- Semi-variable (mixed)
- TC F vQ (3)
- Segmented variable
- TC v1 Q v2(Q Q2)
- v3 (Q Q3) for Q3 ? Q2 (4)
47Cost Estimation Equations
- Semi-fixed
- TC FS ? ROUNDUP(Q / m, 0) (7)
- where m represents the number of units of
activity volume associated with each increment in
cost, FS, and Q gt 0.
48Cost Estimation Equations
- For a single driver Q, the total of the five cost
behaviors can be summarized by the formula - TC FT vT Q v2 (Q Q2)
- v3 (Q Q3)
- FS ? ROUNDUP(Q/m, 0) (8)
49Multiple Measures of Activity
- Next consider two measures of activity volume, QA
and QB for a cost center. In this case, the
total cost function for both activities combined
could be of the form - TC FAT FBT vATQA vBTQB
- vA2 (Q QA2) vA3 (Q QA3)
- vB2 (Q QB2) vB3 (Q QB3)
- FAS ? ROUNDUP(QA/mA, 0)
- FBS ? ROUNDUP(QB/mB, 0) (9)
50Explanation of Terms (2)
- The amounts of the two semi-fixed cost steps are
FAS and FBS - For each semi-fixed cost, the total of that cost
equals the number of semi-fixed cost steps
involved in Qi units ? the size of each step
51Combining Terms
- If there is more than one cost driver, then the
variable cost terms cannot be combined (vT ? v1
v2). - Normally the individual fixed costs can be
combined into one amount (FAT FA1 FA2 )
52Concluding Comments
- The level of analysis will influence how a cost
is modeled. To the extent that a decision is
more focused and short-term, one can forecast
costs accurately by modeling the behavior of
total cost in the specific situation.
53Concluding Comments
- For strategic analyses, most costs would be
considered variable. The focus would be on the
opportunity for learning and cost management in
broad terms, not on the specific behavior of
costs during one operating period.
54Assignments Testing
- In the absence of additional information, assume
costs are mixed, or may be approximated as though
they are mixed. - Read problems carefully for information or hints
about the cost behavior assumed in a problem.
55Using Knowledge of Cost
- One of the primary ways we use cost projection
equations is to develop budgets, particularly
flexible budgets. A flexible budget is based on
budgeted cost equation parameters, not simply a
point estimate of cost, and the volume levels
either budgeted or achieved.
56Questions Related to Go
- Comments about Go Trailer Company
- Questions about Go Trailer Co.?
57Using Knowledge of Cost
- One of the primary ways we use cost projection
equations is to develop budgets, particularly
flexible budgets. A flexible budget is based on
budgeted cost equation parameters, not simply a
point estimate of cost, and the volume levels
either budgeted or achieved.
58Flexible Budgeting - Purpose
- The purpose of a flexible budget is to
incorporate budgeted cost behavior information to
forecast the cost to achieve a specified activity
volume. Based on the budgeted cost parameters,
we can forecast total cost for any specified
level of activity within the relevant interval.
59Flexible Budget Uses - 1
- To forecast total activity costs for budgeting
purposes.
60Flexible Budget Uses - 1
- To forecast total activity costs for budgeting
purposes. - To forecast total activity costs that, in turn,
can be used to project earnings.
61Flexible Budget Uses - 2
- To forecast activity costs to compute budgeted
activity cost rates (BACRs) to charge users
62Flexible Budget Uses - 2
- To forecast activity costs to compute budgeted
activity cost rates (BACRs) to charge users - To forecast total activity costs to compute
budgeted and standard indirect cost rates (BACRs
and SACRs) to charge products
63Flexible Budget Uses - 3
- To forecast costs to support the analysis of
proposed changes in business activities - Modifications to current activities
- Proposed new activities
- Hypothetical activities
64Flexible Budget Uses - 4
- To estimate, for performance evaluation purposes,
the amount of cost that should have been incurred
at the activity levels actually experienced.
65Flexible Budget Uses - 4
- In the context of performance measurement, a
flexible budget becomes an ex-post standard
(benchmark) of the cost that should have been
incurred for the level of activity achieved.
66Finding Cost Drivers
- Causality between the activity measure used and
the resulting cost
67Finding Cost Drivers
- Causality between the activity measure used and
the resulting cost - Independence of the activity measure from other
influences
68Finding Cost Drivers
- Causality between the activity measure used and
the resulting cost - Independence of the activity measure from other
influences - Ease of understanding
69Finding Cost Drivers
- Causality between the activity measure used and
the resulting cost - Independence of the activity measure from other
influences - Ease of understanding
- Functionality of use
70Finding Cost Drivers
- Causality between a measure of activity and the
resulting cost - Functionally related as an inherent part of the
production process (engineering) - Statistical evidence of a theoretical
relationship (regression analysis)
71Finding Cost Drivers
- Causality between a measure of activity and the
resulting cost - Experienced people, with direct knowledge of the
process, believe the relationship holds.
72Finding Cost Drivers
- Independence of the activity measure from other
influences - This concerns clarity of the relationship
- Focus on the correct target measure
- Good (unspoiled) units produced, not total units
- Hours of labor, not dollars of labor cost
- Measures unaffected by other activities
73Finding Cost Drivers
- Ease of understanding
- Managers can articulate the relationship
- No more complex than required
- May need to start simple and revise
74Finding Cost Drivers
- Functionality of use
- Use of the measure leads to believable
information - Use of the measure leads to use of the
information by managers - Use of the information leads to actions in the
best interests of the organization
75Final Thoughts on Topic
- A flexible budget is specific type of budget,
based on budgeted cost equation parameters, for
specified levels of activity volume.
76Final Thoughts on Topic
- In some situations, flexible budgets may be
relatively simple. In other situations, flexible
budgets may be based on many different cost
drivers involving complex patterns of behavior.
But the principal of flexing a budget is the
same.
77Assumptions
- When an organization, case, or problem refers to
a static budget, assume it does not change unless
you are told otherwise.
78Assumptions
- When an organization, case, or problem refers to
a flexible budget, assume it does change with
respect to activity level. The situation,
particularly in standard costing, determines
which level of activity volume to use to flex
the budget.