Wednesday, January 7th - PowerPoint PPT Presentation

1 / 78
About This Presentation
Title:

Wednesday, January 7th

Description:

... Go and Igo assignments. Lecture, discussion, and illustration of flexible budgeting ... The total amount of a semi-fixed cost increases in stair-step fashion. ... – PowerPoint PPT presentation

Number of Views:95
Avg rating:3.0/5.0
Slides: 79
Provided by: william256
Category:
Tags: 7th | january | wednesday

less

Transcript and Presenter's Notes

Title: Wednesday, January 7th


1
Wednesday, January 7th
  • AGENDA
  • Continue my lecture on modeling cost behavior and
    answer questions
  • Comment on Go and Igo assignments
  • Lecture, discussion, and illustration of flexible
    budgeting
  • Lecture, discussion, and illustrations of
    budgeted cost rates time permitting

2
Cost Behavior
  • Monday we said one of the key issues in
    managerial accounting is to determine the factors
    that drive the cost of an activity. We are
    continuing that discussion today.

3
Discontinuous Costs
  • Thus far we have assumed that costs are
    continuous (i.e., cost functions contain no jumps
    or gaps). As a starting point, this is a useful
    assumption. Even when this assumption is not
    satisfied we can be as accurate as necessary.

4
Segmented Linear Costs
  • A common variation on strictly variable costs is
    a cost function that contains multiple linear
    segments. At a specific level of volume, the
    variable cost per unit (the slope) changes.
    There could be several such changes over the
    range of possible volumes.

5
Example - Segmented Cost
  • Think about labor costs. At some level of
    volume, a company would have to begin to pay
    overtime. At an even higher level of volume, the
    company would have to start a second work shift
    and pay what is called a shift premium, etc.

6
Total Segmented Var. Cost
Q2
Q3
0
7
Total Segmented Var. Cost
Total cost
Q2
Q3
0
Activity Volume
8
Segmented Variable Cost
  • Total variable cost function
  • TC v1 Q for 0 Q Q2 (4)

9
Segmented Variable Cost
  • Total variable cost function
  • TC v1 Q for 0 Q Q2 (4)
  • TC v1 Q v2 (Q Q2)
  • for 0 Q2 Q Q3 (5)

10
Segmented Variable Cost
  • Total cost function
  • TC v1 Q for 0 Q Q2 (4)
  • TC v1 Q v2 (Q Q2)
  • for Q2 Q Q3 (5)
  • TC v1 Q v2 (Q Q2)
  • v3 (Q Q3) for
  • 0 Q2 Q3 Q (6)

11
Total Segmented Var. Cost
  • Notice that v3 is an increment to v2 and v2 is
    an increment to v1

12
Total Segmented Var. Cost
  • In per-unit terms, the unit variable cost is
    increasing in jumps at specified levels of volume
    as follows
  • vT is v1 for 0 Q Q2
  • vT is v1 v2 for Q2 Q Q3
  • vT is v1 v2 v3 for Q3 Q

13
Total Segmented Var. Cost
  • To develop an Excel version of the above formula
    for segmented variable costs that will work for
    any volume level, you will need
  • The IF-function, and
  • and the GESTEP function.

14
If-Statement
  • An if-statement is required to determine if the
    activity volume level is above the base volume
    level. The base volume is likely to be the
    smallest value of the relevant volume
    interval--zero or a positive number.

15
Relevant Volume Interval
Relevant Interval
Total cost
Q2
Q3
Q1
Activity Volume
16
Total Cost Functions
  • Format of an if-statement
  • IF(logical test, value if true, value if false)

Test of a condition
Value or formula if condition is true
Value or formula if condition is false
17
GESTEP Function
  • When there are multiple linear segments within
    the relevant interval, or multiple relevant
    intervals, we need multiple, nested
    if-statements, or some other function. For our
    purposes, the simplest approach involves the
    GESTEP function.

18
GESTEP Function
  • The GESTEP function tests whether a number is
    greater than a threshold value.
  • Format
  • GESTEP(number, step value)

Number or formula
Threshold value number or formula
19
GESTEP Function
  • GESTEP(Q, Q1) returns the value of 0 if Q lt Q1,
    and 1 if Q Q1
  • For purposes of developing cost forecasting
    formulas, one can use the GESTEP function to
    determine if Q is greater than either Q2 or Q3
    (slide 7).

20
Excel Formulas
  • Use the above information to develop the formulas
    you need to complete the assigned homework.

21
Semi-Fixed (Lumpy) Cost
  • Next let us move to what may be the most common
    situation, costs that increase in fixed amounts
    with respect to increments in volume that may
    range from small amounts of cost per whole unit
    to very large amounts per millions of units.

22
Total Semi-Fixed Cost
Total cost
Total cost curve
Activity Volume
23
Semi-Fixed (stair-step) Cost
  • The total amount of a semi-fixed cost increases
    in stair-step fashion. To the extent that the
    stair-steps take place at regular intervals of
    volume, as in the following example, they can be
    modeled easily.

24
Example
  • Suppose we employ an additional supervisor for
    every 10 employees. If we must hire a minimum of
    1 supervisor, and each earns 50,000 per year,
    then the cost of super-vision varies with
    employment volume as follows

25
Total Cost for Example
  • TC 50,000 ? of groups of up to 10
    employees to be super- vised where 50,000 is
    the size of each step increase in total
    cost.

26
Semi-fixed Cost Example
  • Employment Supervisors Total Cost
  • Case 1 1 1 50,000
  • Case 2 10 1 50,000
  • Case 3 11 2 100,000
  • Case 4 19 2 100,000
  • Case 5 20 2 100,000
  • Case 6 21 3 150,000

27
Computing the No. of Steps
  • The problem is to compute the number of cost
    steps involved for a given activity volume
    level. Igo trailer Co., Yougo Trailer Co.,
    Exercise 2-21, Wego Trailer Co., and Letsgo
    Trailer Co. all involve the estimation of
    step-fixed costs.

28
Computing the No. of Steps
  • While there are several approaches one might
    take, the ROUNDUP function is a relatively
    straight-forward approach. A description of the
    ROUNDUP function follows.

29
Semi-Fixed Costs
  • General format of the ROUNDUP function
  • ROUNDUP(number, num_digits)

No. to be rounded
No. of decimals
30
ROUNDUP Function Format
  • ROUNDUP(number, num_digits)
  • ROUNDUP(expression, num_digits)
  • ROUNDUP(Q/m, n), where
  • Q the total number of units of the cost
    driver and
  • m the number of cost driver units per step

31
ROUNDUP Function Format
  • Q/m is used to compute the number of step
    increases, and
  • n tells Excel to round to n digits to the right
    of the decimal point.

32
Changing values of n
33
ROUNDUP Function
  • Since we want integers, we are going to be using
    n 0 in our cost estimation equations

34
Base Volumes
  • Sometimes we want to start at the origin, and
    other times we want to start with a different
    base volume level. Is there an estimation
    equation formulation that serves both purposes?

YES!
35
Base Volumes
  • For a step-fixed cost for which the total cost
    increases in steps of FS dollars every m units
    above a base volume of Q1 units, we have the
    following partial formula
  • TC ROUNDUP((Q Q1)/m, 0)FS

36
ROUNDUP Function Values
37
Semi-fixed Cost Formula
  • TC FS ? ROUNDUP(Q/m, 0)
  • for Q gt 0 and m gt 0. (7)

38
Approximating Semi-Fixed Cost
  • Sometimes it may be convenient to use a linear
    approximation of a semi-fixed cost for ease of
    computations, or because of the preferences of a
    user.
  • Intercept is where approximation line crosses the
    y-axis
  • Slope is the rate of change

39
Conservative
Expected
Optimistic
40
Approximating Semi-Fixed Cost
  • Conservative (high) estimate
  • Intercept Fs
  • Slope ?y / ?x
  • Slope (Fs / m)
  • Estimation equation
  • TC Fs (Fs / m)Q

41
Approximating Semi-Fixed Cost
  • Expected value (unbiased) estimate
  • Intercept Fs / 2
  • Slope ?y / ?x
  • Slope (Fs / m)
  • Estimation equation TC Fs / 2 (Fs / m)Q

42
Approximating Semi-Fixed Cost
  • Optimistic estimate
  • Intercept 0
  • Slope ?y / ?x
  • Slope (Fs / m)
  • Estimation equation
  • TC (Fs / m)Q

43
Remember Economics?
  • How does what we are learning relate to what we
    learned in microeconomics?
  • Are these cost formulas the theoretically correct
    versions or are they approximations?

44
Total Cost (Micro)
Total cost
Total cost curve
Relevant range
Activity Volume
45
Average Cost (Micro)
Average Unit Cost
Relevant range
Unit cost curve
Volume
46
Cost Forecasting Formulas
  • Fixed TC F (1)
  • Variable TC vQ (2)
  • Semi-variable (mixed)
  • TC F vQ (3)
  • Segmented variable
  • TC v1 Q v2(Q Q2)
  • v3 (Q Q3) for Q3 ? Q2 (4)

47
Cost Estimation Equations
  • Semi-fixed
  • TC FS ? ROUNDUP(Q / m, 0) (7)
  • where m represents the number of units of
    activity volume associated with each increment in
    cost, FS, and Q gt 0.

48
Cost Estimation Equations
  • For a single driver Q, the total of the five cost
    behaviors can be summarized by the formula
  • TC FT vT Q v2 (Q Q2)
  • v3 (Q Q3)
  • FS ? ROUNDUP(Q/m, 0) (8)

49
Multiple Measures of Activity
  • Next consider two measures of activity volume, QA
    and QB for a cost center. In this case, the
    total cost function for both activities combined
    could be of the form
  • TC FAT FBT vATQA vBTQB
  • vA2 (Q QA2) vA3 (Q QA3)
  • vB2 (Q QB2) vB3 (Q QB3)
  • FAS ? ROUNDUP(QA/mA, 0)
  • FBS ? ROUNDUP(QB/mB, 0) (9)

50
Explanation of Terms (2)
  • The amounts of the two semi-fixed cost steps are
    FAS and FBS
  • For each semi-fixed cost, the total of that cost
    equals the number of semi-fixed cost steps
    involved in Qi units ? the size of each step

51
Combining Terms
  • If there is more than one cost driver, then the
    variable cost terms cannot be combined (vT ? v1
    v2).
  • Normally the individual fixed costs can be
    combined into one amount (FAT FA1 FA2 )

52
Concluding Comments
  • The level of analysis will influence how a cost
    is modeled. To the extent that a decision is
    more focused and short-term, one can forecast
    costs accurately by modeling the behavior of
    total cost in the specific situation.

53
Concluding Comments
  • For strategic analyses, most costs would be
    considered variable. The focus would be on the
    opportunity for learning and cost management in
    broad terms, not on the specific behavior of
    costs during one operating period.

54
Assignments Testing
  • In the absence of additional information, assume
    costs are mixed, or may be approximated as though
    they are mixed.
  • Read problems carefully for information or hints
    about the cost behavior assumed in a problem.

55
Using Knowledge of Cost
  • One of the primary ways we use cost projection
    equations is to develop budgets, particularly
    flexible budgets. A flexible budget is based on
    budgeted cost equation parameters, not simply a
    point estimate of cost, and the volume levels
    either budgeted or achieved.

56
Questions Related to Go
  • Comments about Go Trailer Company
  • Questions about Go Trailer Co.?

57
Using Knowledge of Cost
  • One of the primary ways we use cost projection
    equations is to develop budgets, particularly
    flexible budgets. A flexible budget is based on
    budgeted cost equation parameters, not simply a
    point estimate of cost, and the volume levels
    either budgeted or achieved.

58
Flexible Budgeting - Purpose
  • The purpose of a flexible budget is to
    incorporate budgeted cost behavior information to
    forecast the cost to achieve a specified activity
    volume. Based on the budgeted cost parameters,
    we can forecast total cost for any specified
    level of activity within the relevant interval.

59
Flexible Budget Uses - 1
  • To forecast total activity costs for budgeting
    purposes.

60
Flexible Budget Uses - 1
  • To forecast total activity costs for budgeting
    purposes.
  • To forecast total activity costs that, in turn,
    can be used to project earnings.

61
Flexible Budget Uses - 2
  • To forecast activity costs to compute budgeted
    activity cost rates (BACRs) to charge users

62
Flexible Budget Uses - 2
  • To forecast activity costs to compute budgeted
    activity cost rates (BACRs) to charge users
  • To forecast total activity costs to compute
    budgeted and standard indirect cost rates (BACRs
    and SACRs) to charge products

63
Flexible Budget Uses - 3
  • To forecast costs to support the analysis of
    proposed changes in business activities
  • Modifications to current activities
  • Proposed new activities
  • Hypothetical activities

64
Flexible Budget Uses - 4
  • To estimate, for performance evaluation purposes,
    the amount of cost that should have been incurred
    at the activity levels actually experienced.

65
Flexible Budget Uses - 4
  • In the context of performance measurement, a
    flexible budget becomes an ex-post standard
    (benchmark) of the cost that should have been
    incurred for the level of activity achieved.

66
Finding Cost Drivers
  • Causality between the activity measure used and
    the resulting cost

67
Finding Cost Drivers
  • Causality between the activity measure used and
    the resulting cost
  • Independence of the activity measure from other
    influences

68
Finding Cost Drivers
  • Causality between the activity measure used and
    the resulting cost
  • Independence of the activity measure from other
    influences
  • Ease of understanding

69
Finding Cost Drivers
  • Causality between the activity measure used and
    the resulting cost
  • Independence of the activity measure from other
    influences
  • Ease of understanding
  • Functionality of use

70
Finding Cost Drivers
  • Causality between a measure of activity and the
    resulting cost
  • Functionally related as an inherent part of the
    production process (engineering)
  • Statistical evidence of a theoretical
    relationship (regression analysis)

71
Finding Cost Drivers
  • Causality between a measure of activity and the
    resulting cost
  • Experienced people, with direct knowledge of the
    process, believe the relationship holds.

72
Finding Cost Drivers
  • Independence of the activity measure from other
    influences
  • This concerns clarity of the relationship
  • Focus on the correct target measure
  • Good (unspoiled) units produced, not total units
  • Hours of labor, not dollars of labor cost
  • Measures unaffected by other activities

73
Finding Cost Drivers
  • Ease of understanding
  • Managers can articulate the relationship
  • No more complex than required
  • May need to start simple and revise

74
Finding Cost Drivers
  • Functionality of use
  • Use of the measure leads to believable
    information
  • Use of the measure leads to use of the
    information by managers
  • Use of the information leads to actions in the
    best interests of the organization

75
Final Thoughts on Topic
  • A flexible budget is specific type of budget,
    based on budgeted cost equation parameters, for
    specified levels of activity volume.

76
Final Thoughts on Topic
  • In some situations, flexible budgets may be
    relatively simple. In other situations, flexible
    budgets may be based on many different cost
    drivers involving complex patterns of behavior.
    But the principal of flexing a budget is the
    same.

77
Assumptions
  • When an organization, case, or problem refers to
    a static budget, assume it does not change unless
    you are told otherwise.

78
Assumptions
  • When an organization, case, or problem refers to
    a flexible budget, assume it does change with
    respect to activity level. The situation,
    particularly in standard costing, determines
    which level of activity volume to use to flex
    the budget.
Write a Comment
User Comments (0)
About PowerShow.com