Title: Electric Line Extension Policy Review
1Electric Line Extension Policy Review
November 8, 2001
2Presentation Summary
- Line Extension Assumptions
- Administrative Guidelines
- Implementation
- Questions
3Line Extension Assumptions
- Least cost design
- Overhead service on wood poles
- Cleared Right-of-Way
- Permanent facilities
4Types of Extensions - Small Loads
- Under 20 kW single phase - single customer
- Overhead
- Underground
- Under 20 kW single phase - multiple customers
- Overhead
- Underground
- Methodology for calculating extension allowance
is based on footage or equivalent cost.
5Types of Extensions - All Other
- Larger and Non-Standard Loads
- Over 20 kW and all three phase
- Larger Commercial/Industrial
- Multi-Family
- Specific Cost Study
- Added load to existing facilities
- Methodology for calculating extension allowance
is based on revenue justification. - Temporary Facilities
- Removal and Relocation
6 Overhead Extensions for Small Loads
- 6.1.2.2.5.1 Overhead Extensions For Small Loads
- Single phase permanent retail customers having an
estimated maximum demand of less than 20 kW - Allows for up to 300 of facilities extension,
including primary, secondary and service - Extensions typically for residential subdivision,
single family residential and smaller commercial
loads.
7Overhead Extension - Single Phase less than 20 kW
Existing Facilities
New Facilities
Overhead Transformer
Total distance 300 feet or less (Primary
Secondary Service) Any CIAC amount due from
the retail customer will have Federal Income Tax
added at the rate of 28 percent.
8 Underground Extensions for Small Loads
- 6.1.2.2.5.2 Underground Extensions For Small
Loads - Single phase permanent retail customers having an
estimated maximum demand of less than 20 kW - Allows for an amount of underground facilities
equivalent to 300 of overhead single phase
facilities, including primary, secondary and
service - Extensions typically for residential subdivision,
single family residential and smaller commercial
loads. - The Retail Customer may at their option elect to
provide the civil construction required for TXU
Electric facilities to reduce any CIAC amount
owed and/or to improve overall project
coordination.
9Underground Extension - Single Phase less than 20
kW
Existing Facilities
New Facilities
Pad Mount Transformer
Retail Single Customer - 132 ft Total Equivalent
Distance in dirt or chunk rock soil, 96 feet in
solid rock, or up to 2,730 per location or meter
(Primary Secondary Service) Retail
Multi-Customer - 119 ft Total Equivalent
Distance in dirt or chunk rock soil, 86 feet in
solid rock, or up to 2,445 per location or meter
(Primary Secondary Service)
10Calculation of Contribution in Aid of
Construction All Other Extensions
- 6.1.2.2.5.3 Calculation Of Contribution In Aid
Of Construction (CIAC) For All Other Extensions - Applies to any three phase permanent retail
customer or any permanent retail customer with an
estimated maximum demand of 20 kW or greater
(larger commercial/industrial and multi-family) - Any CIAC requirements are calculated utilizing
the following formula -
- CIAC amount Direct Cost - (Standard Allowance
Factor x Maximum kW Demand) - Direct cost is the current average cost of the
delivery system facilities necessary to provide
delivery service to retail customer - Standard Allowance Factors are 27/kW -
Secondary voltage retail customers - 19/kW - Primary voltage retail customers
- 3/kW - High voltage retail customers
- Maximum kW demand is the estimate of customer's
max 15-minute kW demand. - No CIAC is required if the amount calculated in
the formula is zero or negative. - Any CIAC amount due will have Federal Income Tax
added at the rate of 28 percent. - The Retail Customer may at their option elect to
provide the civil construction required for TXU
Electric facilities to reduce any CIAC amount
owed and/or to improve overall project
coordination.
11Underground Extension - Greater Than 20 kW
1000 kW Demand Load
Pad Mount Transformer
Allowable Expenditure Secondary POD 1000 kW x
27/kW 27,000 Primary POD 1000 kW x 19/kW
19,000
12Retail Customer Requested Facility Upgrades
- 6.1.2.2.5.4 Retail Customer Requested Facility
Upgrades - Applies to existing retail customer that is
adding load that will exceed the capacity of the
Companys existing facilities - Company will upgrade its existing facilities to
accommodate the added load and any CIAC
requirement will be calculated in accordance with
6.1.2.2.5.3 - Only those costs associated with upgrading the
existing facilities are included in the CIAC
calculation. - The additional kW requirements will be used to
determine the Standard Allowance Factor in
accordance with 6.1.2.2.5.3.
13Non-Standard Facility Extensions
- 6.1.2.2.6 Non-Standard Facility Extensions
Distribution - Non-standard facilities include but are not
limited to a two-way feed, automatic or manual
transfer switches, service through more than one
point of delivery, redundant facilities,facilities
in excess of those normally required for
service, or facilities necessary to provide
service at a non-standard voltage. - Company shall collect any amount for the
installation of retail retail customer requested
non-standard facilities prior to construction of
these facilities. - Any CIAC amount due from the developer /retail
customer will have Federal Income Tax added at
the rate of 28 percent.
14Excess Facilities Overhead Extension
Overhead Transformer
30 ft
Overhead Transformer
200 ft
- - - Least Cost design - 1,500 Retail
customer requested design - 2,500 CIAC
1,000
15Excess Facilities Underground Extension
30 ft
80 ft UG Service
Overhead Transformer
Pad Mount Transformer
150 ft
- - - Least Cost design - 2,000 Retail
customer requested design - 3,400 CIAC
1,400
16Temporary Delivery System Facilities
- 6.1.2.2.7 Temporary Delivery System Facilities
Distribution - Retail customer requested distribution service
for a single, continuous period of time which is
less than twelve consecutive months or for any
construction power request - Retail customer shall pay to TXU Electric, the
estimated installation and removal cost including
non-salvageable materials of temporary facilities
required by retail customer for the provision of
temporary electric service. - Retail customer shall pay this cost prior to
construction of these facilities.
17Removal and Relocation of Facilities
- 6.1.2.2.8 Removal And Relocation Of Company's
Facilities Distribution - Retail customer is requesting the removal or
relocation of Companys existing facilities from
retail customers premise. - If a retail customer requests relocation or
removal of existing TXU Electric facilities due
to added or new load resulting in added revenue
and requiring a change in retail customers
existing distribution requirements, such
relocation cost will be included as a direct cost
in the calculation of CIAC requirements as
outlined in 6.1.2.2.5.3. - An exception to this provision are those
relocations that are performed at the request of
municipalities for the limited purpose of street
widening and street straightening. Pursuant to
PURA, the utility bears the relocation cost in
these cases.
18Facilities Relocation
New Building or Expansion
- - - - Existing Facilities Relocated
Facilities These existing facilities must be
situated such that the relocation of these
facilities is necessary for the construction of
or to maintain clearance from a new building or
building expansion.
19Implementation Guidelines
- TXU Electric Gas will provide a 90-day
transition period for all bonafide projects that
are truly in the development pipeline. - Qualifying transitional projects will be
administered under the 2001 policy.
20Effective Dates for Installation Requirements -
Residential Subdivisions
- In order to qualify as a transitional project
and have the project served utilizing 2001 policy
the project - Must have project plans/plats in the TXU Electric
Gas design process by February 1, 2002. - Must be engaged in active, continuous site
development with ongoing discussions with TXU
Electric Gas project management. - Must be sufficiently completed such that TXU
Electric Gas has begun - or can begin - the
installation of its facilities by June 1, 2002,
including - Plans/plats approved by governing body
- Property at final grade, (where TXU Electric
Gas facilities are to be installed), for the
specific phase being developed such that TXU
Electric Gas facilities are being or can be
installed in conjunction with other utilities
serving this phase - ROW cleared
- Roads cut to grade or paved
21Effective Dates for Installation Requirements -
All Others
- In order to qualify as a transitional project
and have the project served utilizing 2001 policy
the project - Must have service required date on or before
January 31, 2002 - Must be engaged in active, continuous discussions
with TXU Electric Gas project management. - Must be sufficiently completed such that TXU
Electric Gas can provide permanent service on
or before January 31, 2002 - Agreement exists that commits TXU Electric Gas
to provide service under the 2001 line extension
policy