Title: Ontarios Electricity Restructuring: An Evolutionary Perspective
1Ontarios Electricity Restructuring An
Evolutionary Perspective
- School of Policy Studies
- Queens University
- Bryne Purchase
2PRESENTATION OBJECTIVES
- Look back at the changing governance structure of
Ontarios electricity sector - Structure of old Ontario Hydro
- Reasons for Change
- New Market Governance Structure (1999 and 2002)
- Errors in Execution and Design.
3PRESENTATION OBJECTIVES
- Focus on the Hybrid Market, its economic
rationale, and its possible evolution - Reminder of supply and demand fundamentals to
2020 - The need for a capacity market
- Outline some market limiting factors.
- Concluding observations
4Ontario Electricity Sector Old Governance
- Ontario Hydro (1906 1999)
- corporation centrally planned, built and operated
Ontarios electricity supply - vertically integrated monopoly
- generation
- (high voltage) transmission and,
- (rural) distribution.
- non-profit, providing power at cost
- largely self-regulated
- engineering dominated culture.
5Ontario Electricity Sector Old Governance
- Ontario Hydro (1906 1999)
- Relationship to Ontario government
- no formal ownership of Ontario Hydro
- Province guaranteed OH debt
- Premier selects Chairman and the Board.
- Local Distribution Utilities
- in 1995 there were over 300
- primarily non-profit
- owned by municipalities
- OH involved in rural distribution.
6Why Restructure?
- Confluence of three forces for change
- poor monopoly performance (Darlington and
industrial consumers) - ideas and circumstance (economic theory, CCGT
technology and natural gas prices) - ideological politics and money (Premier Harris
and Bay Street).
7The New Governance (1999 2002)
- Separate monopoly wires (transmission and
distribution) from generation. - Give Ontario Energy Board rate regulating
responsibilities in monopoly wires. - Create a competitive market in generation.
8Restructuring Ontario Hydro
9The New Governance
- Ontario Government
- takes ownership of OPG and Hydro One in debt for
equity swap with OEFC - makes all companies, including municipal
utilities, for profit corporations - creates corporate income tax regime for the
electricity sectorand, - creates a Debt Retirement Charge.
10Competitive Markets and Stranded Debt
11Second Thoughts The California Question
- Market opening in 2000 delayed by IMO software
development problems. - In 2001, an electricity pricing crisis in
California market raises caution flag in Ontario. - But Ontario was not California
- Adequacy of supply, Pickering A units (2000MW)
would begin return to service in 2001 - Customers could buy a fixed price hedging
contract from a retailer (25 did)
12Second Thoughts The California Question
- But Ontario was not California
- Dominant OPG (75 of market) is government owned
and owners should be enriched - OPG already had a price mitigating rebate (MPMA)
in place - Customers could enjoy a fixed price throughout
year with only a year- end true-up (eg Toronto
Hydro) - Some price pressure released pre market opening.
13Electricity Market Short Run Supply Demand
MC
Price /kwh
D (off-peak)
Peak Hydro
Oil/Natural Gas Peaking plant
Hydroelectric/Nuclear
Coal Intermediate
Baseload
D (peak)
Quantity Kwh
14Implementation The Perfect Storm
- May 2002. Market opens. But
- Pickering A is an engineering and financial Black
Hole - OEB puts all default customers on spot market
price - Government/bureaucrats endlessly debate a
contingency mitigation strategy - New Premier an election is near
- Weather is a scorcher.
- November, 2002. Government fixes the price for
small consumers.
15In Retrospect Key Flaws
- Errors of judgment
- Exposing small customers to spot market price as
default option. - Not developing additional contingency measures.
- Errors of design
- Not immediately breaking up OPG
- Not taking nuclear problems seriously by creating
a separate OPG nuclear company. - However, Bruce lease was a design success.
16New Hybrid Governance(2004)
- Hybrid of regulated and market prices.
- Ontario Energy Board to
- rate regulate OPG nuclear and base-load
hydroelectric production - to set annual fixed price plan for default
customers with true-up in next year (to become
more frequent in future) - price to reflect true costs but not really
yet! - Spot and contract markets continue for all other
OPG or non-OPG production.
17Need For A Capacity Mechanism
- Electricity is expensive to store.
- Installed capacity is not always available ( low
water, equipment failure, maintenance etc) - But we have a high consumer regulatory standard
for reliability. - Therefore, we knowingly need to build excess
capacity. Planning reserve of 15 to 18
percent. - Private markets will not willingly build excess
capacity must be rewarded to do so.
18A Capacity Mechanism
- Electricity markets typically have various
administered restraints on price for example, a
maximum market clearing price. - Capital intensive industries typically exhibit
sharp up or down price spikes (short run
inelastic supply and demand) coinciding with
boom- bust investment cycles. Neither
economically nor politically desirable. - Therefore, electricity energy markets need some
complementary capacity market mechanism. - Usually hotly contested politically and required
only to meet modest load growth plus retirements.
19Demand Supply Outlook A Unique Ontario Problem
- Over 20,000 MW of existing capacity to be
retired, refurbished or converted by 2018 - All existing on-line nuclear capacity (10,900 MW)
by 2018 - Lennox (2140 MW) (oil/gas) by 2016
- Coal plants (7560 MW) by 2009 by Government
decree. - Dual Summer and Winter Peak Demand
- System peak grows by 250 - 300 MW per year. This
summers all time record peak was 26,160 MW.
20Projected Ontario Supply/Demand Normal Weather,
Medium Demand Growth All coal retired by 2010,
nuclear retired when major refurbishment required.
21High Perceived Political Risk
- In addition, political risk is perceived to be
extremely high - Would the wholesale spot market be closed
completely? - Would the Province really exit coal?
- Would the nuclear plants be refurbished or
decommissioned? - Will the Province do special deals with
Manitoba and Newfoundland? - Cannot assume these investor risks away. They
must be dealt with by any new governance
structure!
22Capacity Mechanism
- A new Ontario Power Authority (OPA), will
- assess system needs
- procure new long term supplyand
- be regulated by OEB.
- Key governance change
- Minister (Cabinet) responsible for choosing the
technology mix not the old Ontario Hydro or
the market.
23The Hybrid Markets Capacity Mechanism and Risk
Assignment
- In principle, the Ontario Power Authority
- Eliminates political risk by assigning it
collectively to ratepayers through long term
contracts with generators. - BUT, it can minimize the risk transfer to
ratepayers through competition for the new or
replacement supply (as per 2500MW CES RFP). - In short, an efficient market solution to a
real problem!
24The Hybrid Markets Capacity Mechanism and Risk
Assignment
- The OPA owns no generation and it is empowered to
work on demand management. So, in principle - Eliminates incentive to overbuild and,
- Eliminates technology bias.
- The contract structure of the 2500 MW CES RFP is
a good model for the OPA in that it - Maintains the independence of the OPA
- Transfers technology and construction risk to the
proponent and also, - Provides incentives for operating cost efficiency
and availability.
25Hybrid Governance Structure
- Ministry of Energy
- Determines generation technology mix and
conservation goals
- Ontario Energy Board
- Approves rates for transmission, distribution and
regulated generators - Oversees OPA contracts for new supply and market
rules
SmallConsumers
AnnualRatePlan
CompetitiveGenerators
Independent Electricity System Operator (IESO)
EnergyRetailers
- Ontario Power Authority
- Prepares system plan
- Contracts for new supply, DSM and conservation
Fixed-PriceGenerators (OPG Nuclear and Baseload
Hydro)
LargeConsumers
26Choice of Technologies A Cabinet Decision
- The technology mix must meet the following
general conditions - Widespread public acceptance
- Resource adequacy and reliability
- Competitive in terms of price and reliability
with Great Lakes states - Cost efficient re environmental impacts
- Security of supply through diversification.
27ONTARIOS GENERATION CAPACITYMarch 2004 (30,500
MW)
Hydro 25.2
Nuclear 35.5
Other 0.2
Oil/Gas 14.3
Coal 24.8
Note Does not include 4000MW of import capacity.
28Technology Options Cost Structures
Variable Fuel O M Costs /kwh
CCGT
Clean Coal
Nuclear
Hydro
Fixed Capital Costs /kw
29The Hybrids Rate Regulated Assets
- In the short run, rate regulating OPGs existing
nuclear fleet and base-load hydro was simply a
way to - retain government ownership of OPG
- not break up OPG
- exit the MPMA and yet
- keep the wholesale market alive!
- But the real issue is the future of nuclear
generation.
30Security of Supply and Nuclear Generation
- The underlying problem is that all nuclear
capacity in Ontario needs to be replaced or
refurbished by 2018 - huge capital requirements
- significant political /regulatory risks
- technology risks
- construction risks
- operating risks and,
- a huge logistical problem.
- Refurbishment, let alone new-build, is highly
unlikely to be financed under any pure market
model.
31Security of Supply and Nuclear Generation
- The creation of new markets in pollution rights
would enhance nuclear powers competitive
viability. - In long run, nuclear may be viable in a market
setting. But the market would still go gas in a
very dramatic way in the short run. - Why should we care?
- Security of supply (fuel diversity).
32Nuclear Governance Minimizing Risks to Consumers
- But how do we minimize the risks to consumers?
- Create a separate OPG nuclear company and/or
lease. - Maintain two operating companies.
- Put all nuclear generation under a form of
incentive or performance based regulation by
the OEB. - The regulatory contract itself should
- put construction, technology, operating and
availability risk on the proponents - use the information in the wholesale spot market
and, - have incentives for achieving high capacity
factors.
33A Recap on Structural Imperatives
- We should
- continue wholesale market development ( day ahead
market) - break up OPG
- deregulate base-load hydro
- retain the CES contract model for new supply
and, - add environmental markets under IESO direction.
- Nuclear should remain in the fuel mix. But we
should - create a separate nuclear company or lease
Pickering and Darlington - Maintain two separate operating companies and,
- develop an incentive based regulatory contract
for all nuclear under OEB direction.
34The Hybrid Market Reprise
- The Hybrid market design can potentially
- Utilize the cost efficiency attributes of a
wholesale energy market - Rationally integrate environmental costs into
consumer decisions - Accommodate an enormous and immediate
re-investment requirement - Deal with a large perceived political risk for
investors - Eliminate a bias to over-capacity or a particular
technology and - Keep nuclear in the supply mix for now, while
minimizing consumer risk.