ARE WE ALONE - PowerPoint PPT Presentation

1 / 28
About This Presentation
Title:

ARE WE ALONE

Description:

Our Goal as experts in HVAC. systems was to respond to a RFQ (Request For Quotation) ... REQUEST FOR QUOTATION. To win the contract we had to. achieve the ... – PowerPoint PPT presentation

Number of Views:88
Avg rating:3.0/5.0
Slides: 29
Provided by: IUP9
Category:
Tags: alone | are | quotation

less

Transcript and Presenter's Notes

Title: ARE WE ALONE


1
ARE WE ALONE?
  • Osinanna Okonkwo
  • Vinay Prasad
  • Ugochukwu Anyaorah
  • Daniel Reed

2
PROBLEM STATEMENTS
  • Our Goal as experts in HVAC
  • systems was to respond to a RFQ
  • (Request For Quotation)
  • issued by NASA, for the
  • creation of a housing heating
  • system in the North pole.
  • The house in question is required to
  • support 4 scientists for 4 months,
  • delivering functionality and comfort

3
CONSTRAINTS
  • Inside temperature of 25 C
  • Outside temperature of -40 C
  • Maintain oxygen at a rate of 32L/min.
  • Minimize flow rate variation between all
    registers

4
PROJECT MANAGEMENT - RACI
5
THE HOUSE
6
REQUEST FOR QUOTATION
  • To win the contract we had to
  • achieve the following
  • Lowest blower cost
  • Lowest material cost
  • Least Labor
  • Operating Cost
  • Client Satisfaction

7
LEAST BLOWER COST
8
LEAST BLOWER COST
  • Achieving this goal required minimization
  • of the system pressure drop. To do this we used
  • Flowmaster software to create a Housing
  • Heating System.
  • A network was created but due to
  • insufficient technical support however the
  • results of this part of the project were
  • inconclusive.

9
THE NETWORK
FLOWMASTER
DUCT PLAN
10
LEAST MATERIAL COST
11
LEAST MATERIAL COST
  • Achieving this goal required the
  • minimization of rubber coated
  • sheet metal used in making the
  • duct system.

12
OPTIMIZING MATERIAL USE
  • In order to reduce waste we had to
  • optimize the diameter of the cylindrical straight
  • pipes used in the duct-work.
  • Optimization process
  • 90in side of sheet ? four 22.25in Circumference
    pipes ? 7.08in Diameter
  • This minimized cost as none of the coated sheet
  • material was wasted, while still allowing us a
    good
  • enough pipe diameter for a good flow rate.

13
TOTAL MATERIAL COST
Cost per sheet - 250 Diameter of pipe
7.08in Circumference of pipe 22.25in ? 4 per
sheet
TOTAL MATERIAL COST - 7,750
14
LEAST LABOR COST
15
LEAST LABOR COST
  • To obtain this goal we had to
  • minimize shearing of sheets as
  • well as the use of 90 degree
  • bends and branches due to
  • the high cost of producing
  • them.

16
TOTAL LABOR COST
TOTAL LABOR COST - 2,800
17
OPERATING COST
18
OPERATING COST
  • This required the minimization of
  • Energy costs. The cost of
  • maintenance items includes
  • monthly natural gas costs
  • oxygen costs
  • Electricity costs.

19
Natural Gas Cost- Heat Requirement
  • Based on an inside temperature of 25 C
  • Using peak heat requirement
  • We Assumed
  • No heat transfer by radiation
  • No heat loss from basement to ground
  • Inside wall dimensions were used for heat
    transfer surface area

20
Natural Gas Cost- Heat Requirement
  • Convection coefficients differed due to
    orientation and outside or inside location
  • hin for vertical walls was 8.29 W/m2C (still
    air)
  • hin for roof was 9.26 W/m2C (still air)
  • hout for vertical walls and roof was 34 W/m2C
    (air at 15 mph and any orientation of wall)

Cengel, Yunus A. Heat Transfer A Practical
Approach. pp 175, Table 3-7. McGraw-Hill
Companies, Inc. 2003.
21
Natural Gas Heating Cost
  • Heat Requirement Q 41655.21 W

22
Oxygen Costs
  • OXYGEN SUPPLY OPTION I
  • To supply oxygen to the 4 scientists (each
  • scientist breathes air at 8L/min ? 32L/min),
  • we decided to utilize PHOTOSYNTHESIS.
  • Name of Plant Leucaena leucocephala
  • (Pronounced Loo-Say-Na)

23
Leucaena leucocephala Plant Facts
  • One plant is estimated to produce about 0.22L of
    oxygen per minute.
  • 32L/min required ? 0.22L/min per plant ? 145
    plants
  • Applying a factor of safety of 1.1 we agreed on
    160 plants.
  • Planted at 6in intervals, the plants will occupy
    approximately a 7ft. X 7ft. Area in the basement.
  • Total Cost 10c a plant x 160 ? 16.00
  • As opposed to
  • 32L/min x 60min/hr x 24hr/day x 120 days
    5529600L
  • 5529600L / 3000L/tank 1844 tanks
  • 1844 tanks x 1050 per tank 1,936,200

24
LEAST FLOW RATE VARIATION
25
LEAST FLOW RATE VARIATION
  • Again due to lack of technical
  • Support the results of this part of
  • the project were inconclusive.
  • This is due to an incompatibility
  • between software and project.

26
FINAL COST SHEET
  • Blower cost - INCONCLUSIVE
  • Material Cost - 7,750
  • Labor Cost - 2,800
  • Heating Cost - 21,813.60
  • Oxygen Replenishment - 16.00
  • TOTAL COST - 32,380

27
CONCLUSION
  • Designed a heating network using Flowmaster
  • Successfully determined heating cost
  • Successfully determined oxygen replenishment cost

28
QUESTIONS
Write a Comment
User Comments (0)
About PowerShow.com