Title: ARE WE ALONE
1ARE WE ALONE?
- Osinanna Okonkwo
- Vinay Prasad
- Ugochukwu Anyaorah
- Daniel Reed
2PROBLEM STATEMENTS
- Our Goal as experts in HVAC
- systems was to respond to a RFQ
- (Request For Quotation)
- issued by NASA, for the
- creation of a housing heating
- system in the North pole.
- The house in question is required to
- support 4 scientists for 4 months,
- delivering functionality and comfort
3CONSTRAINTS
- Inside temperature of 25 C
- Outside temperature of -40 C
- Maintain oxygen at a rate of 32L/min.
- Minimize flow rate variation between all
registers
4PROJECT MANAGEMENT - RACI
5THE HOUSE
6REQUEST FOR QUOTATION
- To win the contract we had to
- achieve the following
- Lowest blower cost
- Lowest material cost
- Least Labor
- Operating Cost
- Client Satisfaction
7LEAST BLOWER COST
8LEAST BLOWER COST
- Achieving this goal required minimization
- of the system pressure drop. To do this we used
- Flowmaster software to create a Housing
- Heating System.
- A network was created but due to
- insufficient technical support however the
- results of this part of the project were
- inconclusive.
9THE NETWORK
FLOWMASTER
DUCT PLAN
10LEAST MATERIAL COST
11LEAST MATERIAL COST
- Achieving this goal required the
- minimization of rubber coated
- sheet metal used in making the
- duct system.
-
12OPTIMIZING MATERIAL USE
- In order to reduce waste we had to
- optimize the diameter of the cylindrical straight
- pipes used in the duct-work.
- Optimization process
- 90in side of sheet ? four 22.25in Circumference
pipes ? 7.08in Diameter - This minimized cost as none of the coated sheet
- material was wasted, while still allowing us a
good - enough pipe diameter for a good flow rate.
13TOTAL MATERIAL COST
Cost per sheet - 250 Diameter of pipe
7.08in Circumference of pipe 22.25in ? 4 per
sheet
TOTAL MATERIAL COST - 7,750
14LEAST LABOR COST
15LEAST LABOR COST
- To obtain this goal we had to
- minimize shearing of sheets as
- well as the use of 90 degree
- bends and branches due to
- the high cost of producing
- them.
16TOTAL LABOR COST
TOTAL LABOR COST - 2,800
17OPERATING COST
18OPERATING COST
- This required the minimization of
- Energy costs. The cost of
- maintenance items includes
- monthly natural gas costs
- oxygen costs
- Electricity costs.
19Natural Gas Cost- Heat Requirement
- Based on an inside temperature of 25 C
- Using peak heat requirement
- We Assumed
- No heat transfer by radiation
- No heat loss from basement to ground
- Inside wall dimensions were used for heat
transfer surface area
20Natural Gas Cost- Heat Requirement
- Convection coefficients differed due to
orientation and outside or inside location - hin for vertical walls was 8.29 W/m2C (still
air) - hin for roof was 9.26 W/m2C (still air)
- hout for vertical walls and roof was 34 W/m2C
(air at 15 mph and any orientation of wall)
Cengel, Yunus A. Heat Transfer A Practical
Approach. pp 175, Table 3-7. McGraw-Hill
Companies, Inc. 2003.
21Natural Gas Heating Cost
- Heat Requirement Q 41655.21 W
22Oxygen Costs
- OXYGEN SUPPLY OPTION I
- To supply oxygen to the 4 scientists (each
- scientist breathes air at 8L/min ? 32L/min),
- we decided to utilize PHOTOSYNTHESIS.
- Name of Plant Leucaena leucocephala
- (Pronounced Loo-Say-Na)
23Leucaena leucocephala Plant Facts
- One plant is estimated to produce about 0.22L of
oxygen per minute. - 32L/min required ? 0.22L/min per plant ? 145
plants - Applying a factor of safety of 1.1 we agreed on
160 plants. - Planted at 6in intervals, the plants will occupy
approximately a 7ft. X 7ft. Area in the basement. - Total Cost 10c a plant x 160 ? 16.00
- As opposed to
- 32L/min x 60min/hr x 24hr/day x 120 days
5529600L - 5529600L / 3000L/tank 1844 tanks
- 1844 tanks x 1050 per tank 1,936,200
24LEAST FLOW RATE VARIATION
25LEAST FLOW RATE VARIATION
- Again due to lack of technical
- Support the results of this part of
- the project were inconclusive.
- This is due to an incompatibility
- between software and project.
26FINAL COST SHEET
- Blower cost - INCONCLUSIVE
- Material Cost - 7,750
- Labor Cost - 2,800
- Heating Cost - 21,813.60
- Oxygen Replenishment - 16.00
- TOTAL COST - 32,380
27CONCLUSION
- Designed a heating network using Flowmaster
- Successfully determined heating cost
- Successfully determined oxygen replenishment cost
28QUESTIONS