Title: EMgt 4110 Engineering Professionalism and Practice
1EMgt 4110 Engineering Professionalism and Practice
2Project
- A temporary endeavor undertaken to create a
unique product or service
PMI (Project Management Institute) Standards
Committee, A Guide to the Project Management
Body of Knowledge (PMBOK) Upper Darby, PA PMI,
1996, p.167
3Three Dimensions of Project Goals
Cost
Target
Performance
Time
Adapted from Milton Rosenau, Successful Project
Management (Belmont, Ca. Lifetime Learning
Publications, 1981), 16.)
4Stages
- Project Definition
- Project Selection (financial aspects,
non-financial or intangible aspects) - Project Planning
- Project Execution (control)
- Project Termination (evaluation)
5Time Distribution of Project Effort
Peak Effort Level
Level of Effort
Time
Evaluation And Termination
Planning, Scheduling, Monitoring, Control
Conception
Selection
6Relative Uncertainty of Ultimate Time and Cost by
Life-Cycle Phase
From Russell D. Archibald, Managing
High-Technology Programs and Projects, Wiley, New
York, 1976, p.23
7Project Planning
8Project Plan - Contents
- Objectives
- Benefits
- Scope of Work
- Project Team Organization
- Schedule (Network, Milestones)
- Resources (equipment, labor, contractors)
- Budget (detail, controls)
9Project Plan - Purpose
- Baseline for Evaluating and Controlling Progress
- Highlight Critical Issues
- Coordinate with External Parties
- Communicate to Affected Parties
10Action Plan
Deliverables
Measure(s) of accomplishment
Key constraints and assumptions
Immediate predecessor tasks
Estimated time duration
Estimated resources
Assigned to
Tasks
11Work Breakdown Structure
- Hierarchy of Tasks
- Higher levels contain summary tasks
- Lowest level tasks represent actual work
- Divide along Physical or Specialty Boundaries?
- Use a Coherent Numbering System
- Tie Numbering into Schedule, Budget
12Example of WBS for Building a House
13Responsibility Interface Matrix (RIM)
Persons or Positions Responsible
Project Engineer
Basic Design
A
Project Element or Work Package
Responsibility Code P Primary Responsibility S Sec
ondary Responsibility N Must be Notified A Must
Give Approval
Structure of a Responsibility Matrix
14Sample of Responsibility Interface Matrix (RIM)
From Kocaoglu, D.F. and Cleland, D.I. RIM
Process, Management Review 1982
15Reporting Relationship Matrix
16Remember...
- Obtaining Permits/Licenses
- Generating Reports
- Get a Second Opinion!
- Identify Key Milestones
- Identify and Address All Deliverables
- FOCUS ON THE OBJECTIVES
17Project Scheduling
18Project Scheduling
- Core of project management
- Time dimension of project plan
- Shows logical relationships between tasks
- Determines completion date and milestone dates
- Identifies critical items
19Schedule Elements
- Tasks/activities (have duration)
- Milestones (no duration, important events)
- Relationships
- Time line (hours, days, weeks, months)
20Network Techniques
- CPM (Critical Path Method)
- Designed for construction projects
- Activity-on-arrow vs. Activity-on-node
- Converted from action plan
- PERT (Program Evaluation and Review Technique)
- Time oriented
- Use probabilistic activity time estimates
- PERT/CPM
21Network Techniques
- Network The arrangement of all activities (Arcs)
and events (nodes at the beginning and end of an
arc), defining the project and the
predecessor-successor relationships among
activities. - Path Series of connected activities or
intermediate events between any two events in a
network.
22Project Scheduling Definitions
- Critical Activities/Events Activities/Events
which, if delayed, will delay the completion of
the project. - Critical Path
- Sequence of critical activities and
critical events that connect the projects start
event and finish event.
23Gantt Chart
Week
24A Hierarchy of Bar Charts
Top Level
Intermediate Level
Bottom Level
25Project Management Software
- Professional Packages
- Over 2000 cost
- Very flexible, multi-project capability
- Primavera Project Planner (P3)
- Personal Packages
- Under 500 cost
- Canned views, reports, graphics
- Microsoft Project
26Resources Allocation and Budget
27Resource Allocation
- Standard PERT/CPM methods assume project is time
constrained - Resource constrained projects are common
- Resources
- People
- Equipment
- Space
28Project Budget
- Budget is also a control mechanism
- Top-Down Budgeting
- Bottom-Up Budgeting
- Combined
29Estimating
- Total Cost Estimate
- Target Accuracy (5-15)
- Follow the WBS and Schedule
- The Cost of Estimating Time Accuracy
30Elements of an Estimate
- Material Cost
- Get quotes on big-dollar items
- Estimate other items
- Remember tax and freight (11)
- Labor Cost
- Hours per task
- Hourly rates
- Overhead (Overtime, meals, sick pay, holiday pay,
etc.)
31The Other Costs
- Design, engineering
- Permits, fees
- Interest expense
- Equipment rental, leases
- Secretarial, administration, document
reproduction, phone calls, fax - Overhead
- Contingency/Escalation
32Spending Plan
- Budget Meets Schedule
- Month-by-Month Spending
- Budget Tied to Achievement
- Cumulative Spending Curve
- Distribute Indirect/Other Costs
33Project Monitoring and Control
34Planning vs. Control
- Planning concentrates on setting goals and
directions Control guides the work toward those
goals - Planning allocates resources Control ensures
effective, ongoing utilization of those resources - Planning anticipates problems Control corrects
the problems - Planning motivates participants to achieve goals
Control rewards achievement of goals
35Controlling
- Plan
- Review of the Plans Previously Instituted for
the Objectives in Question - Measuring
- Determining the Current Level of Accomplishment
or Progress toward the Given Objectives - Comparison
- Comparing the Measured Actual Performance to
Planned Performance at the Current Stage of
Events - Evaluating
- Identifying Significantly Unfavorable Deviations
from Planned Performance - Re-planning
- Determining What Courses of Action are Needed to
Bring Performance Up to or Beyond Previously
Planned Level to What Defined Objectives can be
Achieved to Exceeded - Correcting
- Implementing the Corrective Actions as
Determined above
36Project Control Cycle
Measure
Take Corrective Action
Compare and Evaluate
37Gantt Chart Showing Work Status as of Week 20
38Corrective ActionCrashing
- Compute a cost/time slope for each activity that
can be expedited (crashed) - Focus on the critical path(s)
- Crash activities one at a time to decrease
project duration at the minimum additional cost.
39Trend Projection