Title: R. Garoby for the SPL
1SPL development status
- OUTLINE
- 1. Introduction
- 2. Up-to-date characteristics
- 3. On-going work
- 4. Planning and needs
2SPL Working Group
31. Introduction
CERN baseline scenario for a Neutrino Factory
4Other applications of the proton driver
- Approved physics experiments
- CERN Neutrinos to Gran Sasso (CNGS) increased
flux ( 2) - Anti-proton Decelerator increased flux
- Neutrons Time Of Flight (TOF) experiments
increased flux - ISOLDE increased flux, higher duty factor,
multiple energies... - LHC faster filling time, increased operational
margin... - Future potential users
- Conventional neutrino beam from the SPL
super-beam - Second generation ISOLDE facility (EURISOL
-like) - ???
52. Up-to-date SPL characteristics
H- source, 25 mA 14 duty cycle
CCDTL
new SC cavities b0.52,0.7,0.8
Fast chopper (2 ns transition time)
- RF system
- freq. 352 MHz
- ampli. tetrodes and LEP klystrons
6Improvements w.r.t. the reference design
- Improved transitions between sections ? better
beam stability - Doubled period length above 1.1 GeV ? save 25
doublets, 8m, 3 MCHF - Improved error studies ? 100 beam radius lt 20
mm, even for large error case (30 ) ? quad.
radius reduced from 100 mm to 60 mm, (17rms) ?
save 2 - 3 MCHF - Reduced longitudinal emittance 0.6 ? 0.3 ?ºMeV
? improved design of the transfer line (drift
length 230 ? 175 m, bunch length 180 ? 130 ps) - Use of beta0.8 cavities up to the highest energy
? shorter tunnel (- 100 m), less cavities per
klystron, better control of mechanical resonances
7 Revised SPL beam specifications
8Accumulator-Compressor scheme for a Neutrino
Factory
9Proton beam characteristics influence on the
rest of the complex
p production
Cycling rate of all the facility
m burst length
Distance between m bunches
10SPL sequencing and beam delivery
Fast deflection kickers
113. On-going work
12Study of RT structures for the SPL front-end
bl
Alvarez Drift Tube Linac unsurpassable lt20
MeV good but expensive for 20-120 MeV
bl
Cell Coupled Drift Tube Linac attractive solution
for 20-150 MeV (a cold model is being designed)
bl/2
Coupled-Cell Cavity (LEP1) better efficiency
gt110 MeV
quadrupole
quadrupole
The final choice will depend on preferred
apertures, RT final energy, etc.
13Intensity increase programme possible location
of the SPL front-end in the PS South Hall
Þ 1.8 the flux to CNGS (provided upgrades are
made to PSB, PS SPS) Þ cheap installation,
giving benefits from SPL related hardware before
the full machine is operational shortening the
final setting-up
144. Final comments
- Planning (guesses ...) and consequences
- 2009 SPL commissioning with beam
- 2005 Start of construction (civil engineering,
preparation and test of SC cavities in SM18,
etc.) - beginning of 2004 land acquisition and
authorisation of construction - end 2003 decision
- Þ detailed design report for 2004
- Þ increase the design effort at CERN in
interested laboratories by an order of magnitude
before 2004 !