EE 369 POWER SYSTEM ANALYSIS - PowerPoint PPT Presentation

About This Presentation
Title:

EE 369 POWER SYSTEM ANALYSIS

Description:

A typical market has two settlement periods: day ahead and real-time ... Real-time: Modifies the conditions from the day ahead market based upon real-time conditions. ... – PowerPoint PPT presentation

Number of Views:413
Avg rating:3.0/5.0
Slides: 30
Provided by: ecep7
Category:
Tags: analysis | power | system

less

Transcript and Presenter's Notes

Title: EE 369 POWER SYSTEM ANALYSIS


1
EE 369POWER SYSTEM ANALYSIS
  • Lecture 17
  • Optimal Power Flow, LMPs
  • Tom Overbye and Ross Baldick

2
Announcements
  • Read Chapter 7 (sections 7.1 to 7.3).
  • Homework 12 is 6.62, 6.63, 6.67 (calculate
    economic dispatch for values of load from 55 MW
    to 350 MW) due Tuesday, 11/29.
  • Class review and course evaluation on Tuesday,
    11/29.
  • Midterm III on Thursday, 12/1, including material
    through Homework 12.

3
Electricity Markets
  • Over last 20 years electricity markets have moved
    from bilateral contracts between utilities to
    also include centralized markets operated by
    Independent System Operators/Regional
    Transmission Operators
  • Day-ahead market that establishes unit commitment
    and forward financial positions,
  • Real-time market, run every 5 or 15 minutes that
    arranges for physical dispatch, the spot
    market.
  • Basic engine for operating centralized markets
    is Optimal Power Flow (OPF).

4
Electricity Markets
  • OPF is used as basis for day-ahead and real-time
    dispatch pricing in US ISO/RTO electricity
    markets
  • MISO, PJM, ISO-NE, NYISO, SPP, CA, and ERCOT.
  • Electricity (MWh) is treated as a commodity (like
    corn, coffee, natural gas) but with the extent of
    the market limited by transmission system
    constraints.
  • Tools of commodity trading have been widely
    adopted (options, forwards, hedges, swaps).

5
Electricity Futures Example
Source Wall Street Journal Online, 10/30/08
6
Ideal Power Market
  • Ideal power market is analogous to a lake.
    Generators supply energy to lake and loads remove
    energy.
  • Ideal power market has no transmission
    constraints
  • Single marginal cost associated with enforcing
    constraint that supply demand
  • buy from the least cost unit that is not at a
    limit
  • this price is the marginal cost.
  • This solution is identical to the economic
    dispatch problem solution.

7
Two Bus ED Example
8
Market Marginal (Incremental) Cost
Below are some graphs associated with this two
bus system. The graph on left shows the marginal
cost for each of the generators. The graph on
the right shows the system supply curve, assuming
the system is optimally dispatched.
Current generator operating point
9
Real Power Markets
  • Different operating regions impose constraints
    may limit ability to achieve economic dispatch
    globally.
  • Transmission system imposes constraints on the
    market
  • Marginal costs differ at different buses.
  • Optimal dispatch solution requires solution by an
    optimal power flow
  • Charging for energy based on marginal costs at
    different buses is called locational marginal
    pricing (LMP) or nodal pricing.

10
Pricing Electricity
  • LMP indicates the additional cost to supply an
    additional amount of electricity to bus.
  • All North American ISO/RTO electricicity markets
    price wholesale energy at LMP.
  • If there were no transmission limitations then
    the LMPs would be the same at all buses
  • Equal to value of lambda from economic dispatch.
  • Transmission constraints result in differing LMPs
    at buses.
  • Determination of LMPs requires the solution of an
    Optimal Power Flow (OPF).

11
Optimal Power Flow (OPF)
  • OPF functionally combines the power flow with
    economic dispatch.
  • Minimize cost function, such as operating cost,
    taking into account realistic equality and
    inequality constraints.
  • Equality constraints
  • bus real and reactive power balance
  • generator voltage setpoints
  • area MW interchange

12
OPF, contd
  • Inequality constraints
  • transmission line/transformer/interface flow
    limits
  • generator MW limits
  • generator reactive power capability curves
  • bus voltage magnitudes (not yet implemented in
    Simulator OPF)
  • Available Controls
  • generator MW outputs
  • transformer taps and phase angles

13
OPF Solution Methods
  • Non-linear approach using Newtons method
  • handles marginal losses well, but is relatively
    slow and has problems determining binding
    constraints
  • Linear Programming (LP)
  • fast and efficient in determining binding
    constraints, but can have difficulty with
    marginal losses.
  • used in PowerWorld Simulator

14
LP OPF Solution Method
  • Solution iterates between
  • solving a full ac power flow solution
  • enforces real/reactive power balance at each bus
  • enforces generator reactive limits
  • system controls are assumed fixed
  • takes into account non-linearities
  • solving an LP
  • changes system controls to enforce linearized
    constraints while minimizing cost

15
Two Bus with Unconstrained Line
With no overloads the OPF matches the
economic dispatch
Transmission line is not overloaded
Marginal cost of supplying power to each bus
(locational marginal costs) This would be price
paid by load and paid to the generators.
16
Two Bus with Constrained Line
With the line loaded to its limit, additional
load at Bus A must be supplied locally, causing
the marginal costs to diverge. Similarly,
prices paid by load and paid to generators will
differ bus by bus. (In practice, some markets
such as ERCOT charge zonal averaged price to
load.)
17
Three Bus (B3) Example
  • Consider a three bus case (bus 1 is system
    slack), with all buses connected through 0.1 pu
    reactance lines, each with a 100 MVA limit.
  • Let the generator marginal costs be
  • Bus 1 10 / MWhr Range 0 to 400 MW,
  • Bus 2 12 / MWhr Range 0 to 400 MW,
  • Bus 3 20 / MWhr Range 0 to 400 MW,
  • Assume a single 180 MW load at bus 2.

18
B3 with Line Limits NOT Enforced
Line from Bus 1 to Bus 3 is over- loaded all
buses have same marginal cost (but not allowed
to dispatch to overload line!)
19
B3 with Line Limits Enforced
LP OPF redispatches to remove violation. Bus
marginal costs are now different. Prices will
be different at each bus.
20
Verify Bus 3 Marginal Cost
One additional MW of load at bus 3 raised total
cost by 14 /hr, as G2 went up by 2 MW and
G1 went down by 1MW.
21
Why is bus 3 LMP 14 /MWh ?
  • All lines have equal impedance. Power flow in a
    simple network distributes inversely to impedance
    of path.
  • For bus 1 to supply 1 MW to bus 3, 2/3 MW would
    take direct path from 1 to 3, while 1/3 MW would
    loop around from 1 to 2 to 3.
  • Likewise, for bus 2 to supply 1 MW to bus 3,
    2/3MW would go from 2 to 3, while 1/3 MW would go
    from 2 to 1to 3.

22
Why is bus 3 LMP 14 / MWh, contd
  • With the line from 1 to 3 limited, no additional
    power flows are allowed on it.
  • To supply 1 more MW to bus 3 we need
  • Extra production of 1MW Pg1 Pg2 1 MW
  • No more flow on line 1 to 3 2/3 Pg1 1/3 Pg2
    0
  • Solving requires we increase Pg2 by 2 MW and
    decrease Pg1 by 1 MW for a net increase of
    14/h for the 1 MW increase.
  • That is, the marginal cost of delivering power to
    bus 3 is 14/MWh.

23
Both lines into Bus 3 Congested
For bus 3 loads above 200 MW, the load must
be supplied locally. Then what if the bus 3
generator breaker opens?
24
Typical Electricity Markets
  • Electricity markets trade various commodities,
    with MWh being the most important.
  • A typical market has two settlement periods day
    ahead and real-time
  • Day Ahead Generators (and possibly loads) submit
    offers for the next day (offer roughly represents
    marginal costs) OPF is used to determine who
    gets dispatched based upon forecasted conditions.
    Results are financially binding either
    generate or pay for someone else.
  • Real-time Modifies the conditions from the day
    ahead market based upon real-time conditions.

25
Payment
  • Generators are not paid their offer, rather they
    are paid the LMP at their bus, while the loads
    pay the LMP
  • In most systems, loads are charged based on a
    zonal weighted average of LMPs.
  • At the residential/small commercial level the LMP
    costs are usually not passed on directly to the
    end consumer. Rather, these consumers typically
    pay a fixed rate that reflects time and
    geographical average of LMPs.
  • LMPs differ across the system due to transmission
    system congestion.

26
LMPs at 855 AM on one day in Midwest.
Source www.midwestmarket.org
27
LMPs at 930 AM on same day
28
MISO LMP Contours 10/30/08
29
Limiting Carbon Dioxide Emissions
  • There is growing concern about the need to limit
    carbon dioxide emissions.
  • The two main approaches are 1) a carbon tax, or
    2) a cap-and-trade system (emissions trading)
  • The tax approach involves setting a price and
    emitter of CO2 pays based upon how much CO2 is
    emitted.
  • A cap-and-trade system limits emissions by
    requiring permits (allowances) to emit CO2. The
    government sets the number of allowances,
    allocates them initially, and then private
    markets set their prices and allow trade.
Write a Comment
User Comments (0)
About PowerShow.com