Title: EE 369 POWER SYSTEM ANALYSIS
1EE 369POWER SYSTEM ANALYSIS
- Lecture 14Power Flow
- Tom Overbye and Ross Baldick
2Announcements
- Read Chapter 12, concentrating on sections 12.4
and 12.5. - Homework 12 is 6.43, 6.48, 6.59, 6.61, 12.19,
12.22, 12.20, 12.24, 12.26, 12.28, 12.29 due
Tuesday Nov. 25.
3The N-R Power Flow 5-bus Example
Single-line diagram
4The N-R Power Flow 5-bus Example
Bus Type V per unit ? degrees PG per unit QG per unit PL per unit QL per unit QGmax per unit QGmin per unit
1 Slack 1.0 0 ? ? 0 0 ? ?
2 Load ? ? 0 0 8.0 2.8 ? ?
3 Constant voltage 1.05 ? 5.2 ? 0.8 0.4 4.0 -2.8
4 Load ? ? 0 0 0 0 ? ?
5 Load ? ? 0 0 0 0 ? ?
Table 1. Bus input data
Bus-to-Bus R per unit X per unit G per unit B per unit Maximum MVA per unit
2-4 0.0090 0.100 0 1.72 12.0
2-5 0.0045 0.050 0 0.88 12.0
4-5 0.00225 0.025 0 0.44 12.0
Table 2. Line input data
5The N-R Power Flow 5-bus Example
Bus-to-Bus R per unit X per unit Gc per unit Bm per unit Maximum MVA per unit Maximum TAP Setting per unit
1-5 0.00150 0.02 0 0 6.0
3-4 0.00075 0.01 0 0 10.0
Table 3. Transformer input data
Bus Input Data Unknowns
1 V1 1.0, ?1 0 P1, Q1
2 P2 PG2-PL2 -8 Q2 QG2-QL2 -2.8 V2, ?2
3 V3 1.05 P3 PG3-PL3 4.4 Q3, ?3
4 P4 0, Q4 0 V4, ?4
5 P5 0, Q5 0 V5, ?5
Table 4. Input data and unknowns
6Let the Computer Do the Calculations! (Ybus Shown)
7Ybus Details
8Here are the Initial Bus Mismatches
9And the Initial Power Flow Jacobian
10Five Bus Power System Solved
1137 Bus Example Design Case
12Good Power System Operation
- Good power system operation requires that there
be no reliability violations (needing to shed
load, have cascading outages, or other
unacceptable conditions) for either the current
condition or in the event of statistically likely
contingencies - Reliability requires as a minimum that there be
no transmission line/transformer limit violations
and that bus voltages be within acceptable limits
(perhaps 0.95 to 1.08) - Example contingencies are the loss of any single
device. This is known as n-1 reliability.
13Good Power System Operation
- North American Electric Reliability Corporation
now has legal authority to enforce reliability
standards (and there are now lots of them). - See http//www.nerc.com for details (click on
Standards)
14Looking at the Impact of Line Outages
Opening one line (Tim69- Hannah69) causes
overloads. This would not be Allowed.
15Contingency Analysis
Contingencyanalysis providesan automaticway of
lookingat all the statisticallylikely
contingencies. Inthis example thecontingency
set is all the single line/transformeroutages
16Power Flow And Design
- One common usage of the power flow is to
determine how the system should be modified to
remove contingencies problems or serve new load - In an operational context this requires working
with the existing electric grid, typically
involving re-dispatch of generation. - In a planning context additions to the grid can
be considered as well as re-dispatch. - In the next example we look at how to remove the
existing contingency violations while serving new
load.
17An Unreliable Solutionsome line outages result
in overloads
Case now has nine separate contingencies
having reliability violations (overloads in
post-contingency system).
18A Reliable Solutionno line outages result in
overloads
Previous case was augmented with the addition
of a 138 kV Transmission Line
19Generation Changes and The Slack Bus
- The power flow is a steady-state analysis tool,
so the assumption is total load plus losses is
always equal to total generation - Generation mismatch is made up at the slack bus
- When doing generation change power flow studies
one always needs to be cognizant of where the
generation is being made up - Common options include distributed slack, where
the mismatch is distributed across multiple
generators by participation factors or by
economics.
20Generation Change Example 1
Display shows Difference Flows between
original 37 bus case, and case with a BLT138
generation outage note all the power change
is picked up at the slack
Slack bus
21Generation Change Example 2
Display repeats previous case except now the
change in generation is picked up by other
generators using a participation factor
(change is shared amongst generators) approach.
22Voltage Regulation Example 37 Buses
Automatic voltage regulation system controls
voltages.
Display shows voltage contour of the power system
23Real-sized Power Flow Cases
- Real power flow studies are usually done with
cases with many thousands of buses - Outside of ERCOT, buses are usually grouped into
various balancing authority areas, with each area
doing its own interchange control. - Cases also model a variety of different automatic
control devices, such as generator reactive power
limits, load tap changing transformers, phase
shifting transformers, switched capacitors, HVDC
transmission lines, and (potentially) FACTS
devices.
24Sparse Matrices and Large Systems
- Since for realistic power systems the model sizes
are quite large, this means the Ybus and Jacobian
matrices are also large. - However, most elements in these matrices are
zero, therefore special techniques, sparse
matrix/vector methods, are used to store the
values and solve the power flow - Without these techniques large systems would be
essentially unsolvable.
25Eastern Interconnect Example
Example, which models the Eastern
Interconnectcontains about 43,000 buses.
26Solution Log for 1200 MW Outage
In this example thelosss of a 1200 MWgenerator
in NorthernIllinois was simulated. This caused
a generation imbalancein the associated
balancing authorityarea, which wascorrected by
a redispatch of localgeneration.
27Interconnected Operation
- Power systems are interconnected across large
distances. - For example most of North America east of the
Rockies is one system, most of North America west
of the Rockies is another. - Most of Texas and Quebec are each interconnected
systems.
28Balancing Authority Areas
- A balancing authority area (previously called a
control area) has traditionally represented the
portion of the interconnected electric grid
operated by a single utility or transmission
entity. - Transmission lines that join two areas are known
as tie-lines. - The net power out of an area is the sum of the
flow on its tie-lines. - The flow out of an area is equal to total gen -
total load - total losses tie-line flow
29Area Control Error (ACE)
- The area control error is a combination of
- the deviation of frequency from nominal, and
- the difference between the actual flow out of an
area and the scheduled (agreed) flow. - That is, the area control error (ACE) is the
difference between the actual flow out of an area
minus the scheduled flow, plus a frequency
deviation component - ACE provides a measure of whether an area is
producing more or less than it should to satisfy
schedules and to contribute to controlling
frequency.
30Area Control Error (ACE)
- The ideal is for ACE to be zero.
- Because the load is constantly changing, each
area must constantly change its generation to
drive the ACE towards zero. - For ERCOT, the historical ten control areas were
amalgamated into one in 2001, so the actual and
scheduled interchange are essentially the same
(both small compared to total demand in ERCOT). - In ERCOT, ACE is predominantly due to frequency
deviations from nominal since there is very
little scheduled flow to or from other areas.
31Automatic Generation Control
- Most systems use automatic generation control
(AGC) to automatically change generation to keep
their ACE close to zero. - Usually the control center (either ISO or
utility) calculates ACE based upon tie-line flows
and frequency then the AGC module sends control
signals out to the generators every four seconds
or so.
32Power Transactions
- Power transactions are contracts between
generators and (representatives of) loads. - Contracts can be for any amount of time at any
price for any amount of power. - Scheduled power transactions between balancing
areas are called interchange and implemented by
setting the value of Psched used in the ACE
calculation - ACE Pactual tie-line flow Psched 10ß ?f
- and then controlling the generation to bring ACE
towards zero.
33Physical power Transactions
- For ERCOT, interchange is only relevant over
asynchronous connections between ERCOT and
Eastern Interconnection or Mexico. - In Eastern and Western Interconnection,
interchange occurs between areas connected by AC
lines.
34Three Bus Case on AGCno interchange.
Generation is automatically changed to
match change in load
Net tie-line flow is close to zero
35100 MW Transaction between areas in Eastern or
Western
Scheduled 100 MW Transaction from Left to Right
Net tie-line flow is now 100 MW
36PTDFs
- Power transfer distribution factors (PTDFs) show
the linearized impact of a transfer of power. - PTDFs calculated using the fast decoupled power
flow B matrix
37Nine Bus PTDF Example
Figure shows initial flows for a nine bus power
system
38Nine Bus PTDF Example, cont'd
Figure now shows percentage PTDF flows for a
change in transaction from A to I
39Nine Bus PTDF Example, cont'd
Figure now shows percentage PTDF flows for a
change in transaction from G to F
40WE to TVA PTDFs
41Line Outage Distribution Factors (LODFs)
- LODFs are used to approximate the change in the
flow on one line caused by the outage of a second
line - typically they are only used to determine the
change in the MW flow compared to the
pre-contingency flow if a contingency were to
occur, - LODFs are used extensively in real-time
operations, - LODFs are approximately independent of flows but
do depend on the assumed network topology.
42Line Outage Distribution Factors (LODFs)
43Line Outage Distribution Factors (LODFs)
44Flowgates
- The real-time loading of the power grid can be
assessed via flowgates. - A flowgate flow is the real power flow on one
or more transmission elements for either base
case conditions or a single contingency - Flows in the event of a contingency are
approximated in terms of pre-contingency flows
using LODFs. - Elements are chosen so that total flow has a
relation to an underlying physical limit.
45Flowgates
- Limits due to voltage or stability limits are
often represented by effective flowgate limits,
which are acting as proxies for these other
types of limits. - Flowgate limits are also often used to represent
thermal constraints on corridors of multiple
lines between zones or areas. - The inter-zonal constraints that were used in
ERCOT until December 2010 are flowgates that
represent inter-zonal corridors of lines.