Title: Distributed Energy Resources Site Visits
1Distributed Energy Resources Site Visits
- Presented by
- Bevan R. Smith Jr., Director
- Virgin Islands Energy Office
- September 23, 2006
2A Presentation for the Decisionmakers
- Virgin Islands Water and Power Authority
- and the
- Virgin Islands Energy Office
3Distributed Generation
- small scale environmentally friendly technologies
- installed on and designed primarily to serve a
single end-users site - any generation built near to a consumers load
regardless of size or energy source
4Virgin Islands DG Public Policy Goals
- Secure Partnership with WAPA
- Research utilization of renewable/alternative
energy resources as Distributed Energy Resources - Conduct workshops for WAPA governing Board, the
PSC and general public - Development and Implementation of an
interconnection policy for the Territory
5Formation of DG TEAM
- Jim Gibson May Cornwall, Guy Lacombe
Bevan Smith Greg Willocks Melton Smith - Park Service WAPA FPL
VIEO WAPA
WAPA
6USDOE funds and participates
- David Waldrop (USDOE)
- Joins team at utility sponsored sites
7- Leroy Prentice (WAPA)
- joins DG Team after volcanic ash delays flight.
8Virgin Islands DG Public Policy Goals
- Research utilization of renewable/alternative
energy resources as Distributed Energy Resources
9Viable DG Technologies
- FUEL CELLS
- MICROTURBINES
- PHOTOVOLTAIC SYSTEMS
- WIND
10Birch State Park
- 5 kW grid tied fuel cell
- Unit contains two major components
- The fuel processor and power conditioner
11Findings on the Fuel Cell unit
Plug Power Model SU-1
- the fuel reformer processes a hydrocarbon fuel
into a hydrogen rich gas - the power conditioner converts the low voltage
current produced by the fuel cell to a high
voltage DC - An inverter transforms the high voltage DC to 120
or 240 volts AC - Batteries in the power conditioner ensure
sufficient coverage for power surges - consider the more cost effective 200 kW model
that uses a phosphoric acid membrane
12Findings on the Fuel Cell unit
Plug Power Model SU-1
- Provides 5 kW to park operations office
- Utilizes natural gas as an energy source (model
Genesis 5C utilizes propane gas) - H electrons and protons separate through PEM the
(membrane) system - Power produced per unit of energy has an
efficiency rating between 30 55 - An interconnection policy exists
- Grid tied utilizing dual metering system
13Problems within Fuel Cell unit
- system is only about 25 efficient
- water purification problems caused by algae
- rodents/insects have chewed wiring
- costs upwards of 100,000.00
- operating cost is 7.00/mbtu
- inverter trips on power output efficiency,
unstable or loss of grid power,low gas flow, high
temperature and low water
14DG TEAM VISITSSt. Thomas University
- A stand-alone PV power system provides 5kW to
the University. - The Florida Power and Light and St. Thomas
University have a Cooperative Fuel Cell and a
Solar PV Project
15Hillsborough Landfill
- Tampa Electric Company maintains a 30 kW Capstone
microturbine at this condemned landfill site
16(No Transcript)
17Hillsborough Landfill
18Noteworthy Findings on microturbine on landfill
- site is UL approved for interconnection
- process takes 2-3 of methane gas from the
ground - filters remove large particulates
- refrigerator gas dryer adjusts the temperature
- gas equipment is 70,000 and 30,000 for the
microturbine
1918 kW grid-tied photovoltaic system
- TECO
- Subsidizes this system that utilizes 100 of
solar energy produced
20Findings at Tampa Electric CompanySponsored DG
projects
- TECO is 3rd largest investor-owned utility
- Produces 4000 MW daily using 99 coal
- Believes economics for DG systems are
unjustifiable - Established an interconnection policy for small
systems 10kWlt - Enforces dual metering arrangement
- Disallows net metering
21One hundred fifty 120-watt panels
2220 kW grid tied PV array at University of South
Florida
23University of South FloridasParking/Electric
Car Charging Station
- Provides power for charging station
- Includes a switching system that allows batteries
to be charge according to their need - Excess is fed to the campus grid only
- USF conduct experiments on three semiconductors
for pv cells silicon, copper indium gallium
di-selenide and cadmium telluride. - Seeks to get Hydrogen from non-fossil fuel source
such as a by-product of fertilizer
24(No Transcript)
25(No Transcript)
26Cape Eleuthera Island School 23.5 kW hybrid
PV/Wind power system.
27(No Transcript)
28Findings at the Island School
- 16 kW solar array and a 7.5 kW wind turbine
provides 100 of schools power - Solar water heaters assist in keeping school
within its consumption limits - Hybrid system operates the same as pv except you
have a wind component - A constructed wetland, camouflaged as a floral
garden, aids in water resource management
29(No Transcript)
30Florida Solar Energy Center
- Review Industry-accepted Standards
- Photovoltaics Economics
- PV Sytems design review program
- Inverter non-islanding
- feature Tests
31Development of an interconnection policy
- Investigate interconnection standards
- UNDERWRITERS LABORATORY (UL) 1741
- INSTITUTE OF ELECTRONICS AND ELECTRICAL
ENGINEERS (IEEE) 929 1547 - Investigate site permitting and design
- Investigate building energy codes
32Florida Solar Energy Center
33(No Transcript)
34(No Transcript)
35Inverter non-islanding Test
36Meter turns in reverse
37Inverter can start up generator
38Back-up Battery Bank provides power during outages
39IMPORTANCE OF DG RESEARCH
- Implementation of Act No. 5006 which amended
Section 1, Title 30, of the Virgin Islands Code.
This allows small power production facilities to
interconnect with the local electric utility and
sell excess generated electric energy to that
utility. - To pilot ten photovoltaic grid-interconnected
small power production systems for grantees who
submitted innovative renewable energy proposals
40IMPORTANCE OF DG RESEARCH
- Assist the PSC determining such requirements
relative to the minimum size, fuel use and
efficiency of a Qualifying Cogeneration
Facility. - Assist WAPA in addressing safety issues
pertaining to interconnectivity to the utility
grid
41Piloting Grid-tied PV Power Systems of VIEO
Grantees/Partners
- Innovative Renewable Energy Grant recipients
10kW - Nature Conservancy 8 kW
- Stefan Larsen 6.5 kW (hybrid)
- Estate Concordia Eco 5kW
42BAMBOULA HAVEN
- 1 KW PV SYSTEM OPERATES EQUIPMENT IN THE
MULTI-PURPOSE ROOM OF THE CENTER
43WERNER WERNICKE S INVERTER CONSOLE
- Sharp 165W (24 V nominal) 2Sx3P
- Xantrex 5548 with GTI
- Xantrex Combiner box
- Xantrex C40 Charge Controller
- Outback mounting panel
- Rolls 4 V, 546 Ah, 12Sx1P
44LlOYD WILLIAMS BATTERY BANK
- Batteries provided 26 kWh of energy storage
45EDWIN HATCHETTES RACK MOUNTED PV PANELS
- Sharp 175W (24 V nominal)
- 2Sx3P
- Xantrex 5548 with GTI
- Xantrex Combiner box
- Outback mounting panel
- Rolls 4 CS 17PS 4 V, 546 Ah, 12Sx1P
-
46ROOF MOUNTED PV PANELS
47BRIAN EMERICHS TILTED ARRAY
- Sharp 175W (24 V nominal) 2Sx3P
- Xantrex 5548 with GTI
- Xantrex Combiner box
- Outback mounting panel
- MK 8G4DLTP 12 V, 183 Ah, 4Sx1P
48INSIDE THE OUTBACK INTEGRATED SUB-PANEL
49DUAL METERS INCREASE COSTS
- Electricity drawn from WAPA appears on the IN
meter and Electricity sent to WAPAs grid appears
on the OUT meter
50MT. VICTORY CAMP
- PV Module Kyocera KC-50
- PV Array 4S x 5P
51INVERTER CONSOLE AND BATTERY BANK
- Battery Deka Marine Master
- Battery Bank 4S x 3P
- Inverter Xantrex 4048 w/ GTI
52CURTIS JOHNSON
- Mobile 1 kW unit with Grid Tie capabilities
53Solar Water Heater Collector
- Solar thermal energy for water heating is
commercially viable - WAPA look into the bulk purchase of solar water
heaters and market them as a replacement for
electric water heaters
54WIND ENERGY CASE STUDY
- St. Thomas diurnal wind speed range from 14.5
mph to 16.9 - St. Johns is 12.3 mph to 13.2 mph
- St. Croixs is 15.8 to 16.9 mph
55Tilt-down type machines or fixed machines
- A determination of the added cost of hurricane
risk mitigation for wind power development needs
to be conducted
56Stand Alone Hybrid System on St. Croixs East End
- Stefan Larsen and Jan Mitchell anxiously awaits
Net Metering to store renewable energy on the
grid and run A/C units at nighttime
57DG Teams Next Steps
- Coordinate workshops for WAPA governing Board and
the PSC on behalf of the Executive Director - Identify and conduct training for local Building
Inspectors - Immediate approval for the Implementation of an
interconnection agreement for the Territory - Produce videos, reports, and workshop packages
for distribution
58THANK YOU
- U.S. VIRGIN ISLANDS DISTRIBUTED GENERATION
- Team Member
- Bevan Smith Jr.
- Director
- VI Energy Office