Title: 12ID Upgrade to Two Independent Beamlines Monthly Update
112-ID Upgrade to Two Independent Beamlines -
Monthly Update
May 23, 2008
- Randall Winans
- Charles Kurtz, Byeongdu Lee, Soenke Seifert
- Chemistry, Environmental, and Polymer Science
Group - X-ray Science Division
- Oliver Schmidt and Soon-Hong Lee
- Mechanical Engineering and Design
- APS Engineering Support Division
Advanced Photon Source
212 - ID Upgrade to Two Beamlines with Canted
Undulators
- Versatile Anomalous and time resolved
SAXS/WAXS/GISAXS/USAXS beamline 12-ID-C - Technically complicated experiments which takes
full advantage of insertion device capabilities - Pink beam high flux for fast experiments
- Wide Q range 0.001 5.0
- Wide energy range 4.5 36 Kev
- Combined experiments XANES, MS, DSC
- Surface Scattering 12-ID-D
- MOCVD
- Diffractometer (from 12-ID-B)
- Wide energy range 4.5 36 Kev
- 40 cm mirror in 12-ID-C
- Dedicated (6.9 - 13 Kev) SAXS beamline
12-ID-B - Easily adjustable Q range (0.006 2.0) in
vacuum detector - Rapid access
- Regular access (set aside time)
3Selection of an Undulator for 12-ID-B
C/D - U33S B - U30S in Sep 08 In one year
U27
B
4(No Transcript)
5A Hutch
6C/D Line
A Hutch
Upgrade horizontal Mirror with bender
The outboard x-ray beam, originating from the
first insertion device will supply beam to
12-ID-C. Initially at an outboard trajectory of
0.5 mrad of the centerline, this beam will be
deflected by the existing 1200 mm long mirror,
located at 31.4 meters from the straight section,
by 4mrad, to a total of 3.5 mrad inboard
7 8 A design for indirect cooling of the first
crystal already implemented in 20-ID is planned
along with modifications to the 1st crystal
Compton shielding
9B Line
Horizontal Mirror
A Hutch
1012-ID-B Beamline with a large offset Monochromator
1704.1 mm
1025.4mm
678.4 mm
860 mm
51.8 (2?B1)
26.8 (2?B2)
C 111
Schematic diagram of both crystals during
operation with a nominal take-off angle (2?) of
26 52 from the centerline
1112-ID-B Beamline with a large offset Monochromator
January 2008 Accepted bid from ACCEL for
550.2K Ordered May 2008 600K
12New Mini-hutch Ordered - Installed Sep 08
13New Mini-hutch
Vertical Mirror
USAXS Mirrors
14C
B
USAXS
SAXS Chamber
D
TRSAXS
Huber
MOCVD
15Proposed 12-ID Beamlines
B Branch
C/D Branch
D
C
16(No Transcript)
17(No Transcript)
18 Air Handling
- The hutches will be connected directly to the air
system to maintain a more constant temperature. - It has been observed that the 12-ID-C and B
hutches can become very much warmer than the
experimental hall which results in wide
temperature swings when the doors are opened.
19- - Vacuum chamber and one shorten Undulator A
installed - and some canted front end parts ordered
- 2007 - Funding for mini-hutch and remaining
canted front end parts - PDR approved for mini-hutch
- 2008 Order large offset mono
- September long shutdown
- Construction of mini-hutch
- Installation of canted front end
- Installation of second undulator (U30s
in-line) - 2009 May Shutdown Installations (depending on
funding) - Cant the two undulators
- Large offset mono
- SAXS vacuum chamber in 12-ID-B
2012 ID Horizontal Mirror
- In April 2006 the mirror overheated to 190 C when
the cooling water was turned off but the heaters
remained on(heaters are used to focus the beam).
Indium metal (mp 157 C) which is which is used to
ensure contact with the copper cooling blocks and
the heaters melted. From visual inspection the
mirror appeared to be free of metal particles - However, there appeared to be some degradation in
performance. - Over this long shut-down the mirror has been
removed, inspected and characterized for slope
error and roughness. - A roughness on average of 5 A was measured
- The mirror is being re-installed
21(No Transcript)
22(No Transcript)
23(No Transcript)
2412 -ID Upgrade to Two Beamlines with Canted
Undulators
- APS Strategic Plan calls for 12-ID to become a
dedicated Small angle X-ray scattering (SAXS)
facility. - The 12-ID SAXS facility (FY 1996 DOE Scientific
Facilities Initiative) is 50 of the GUP
beamtime with x2 oversubscription. - SAXS publications - 124 and users - 291
- The increasing demand for SAXS beam time has been
driven by - Research into the structure and dynamics of
nanoscale materials - Increased interest in soft matter
- Time-dependent structural investigations
- Plan was endorsed by the SAC review of Sector 12
in March, 2005
25Ancillary Equipment
- Flow cells, stop flow capability
- Environmental control (heating, cooling) for in
situ experiments - Sample changers for high throughput experiments
- Gas flow control system for multiple and reactive
gases - Other complementary techniques such as mass
spectrometry