Title: Vegetated Treatment Systems Field Experience
1Vegetated Treatment Systems Field Experience
ISU Project Update 04/05/06
- Robert Burns Lara Moody
- Iowa State University
- Agricultural Biosystems Engineering
2Presentation Outline
- Introduction of Project Systems
- Planned Monitoring
- System Descriptions
- Construction Issues
- Monitoring Issues
3VTS Options in Research Project
1
Vegetated Treatment Area (VTA)
Settling Basin
Beef Feedlot
2
VIB
VTA
Settling Basin
Beef Feedlot
4VTS Options in Research Project
3
Settling Bench
Vegetated Treatment Area (VTA)
Beef Feedlot
5Research Site Locations
Northwest IA 2
Northwest IA 1
Central IA 1
Central IA 2
Southwest IA 2
Southwest IA 1
6Project VTS System Types
7Project Site Status
8PermitMonitoring Requirements
- Vegetated Treatment System
- Effluent from settling basin, VIB, VTA
- Event based sampling (quality quantity)
- Analyze for TKN, NH3-N, NO3-N, Total P, PO4
(DRP), TSS, TDS, COD, BOD5, Cl, Fecal Coliform,
and PH - Monitor flow rates
9PermitMonitoring Requirements
- Surface Water Quality Sampling
- Initial background and annually each spring
- Upstream, at source, and downstream
- Analyze for TKN, NH3-N, NO3-N, Total P, PO4
(DRP), TSS, TDS, COD, BOD5, Cl, Fecal Coliform,
and PH
10Permit Monitoring Requirements
- Ground Water
- Quality Sampling
- Background monthly
- Up-gradient, at system, down-gradient
- Analyze for NH4-N, NO3-N, Fecal Coliform, Cl
11Permit Monitoring Requirements
- Soil Sampling in Vegetated Treatment Systems
- Background annual surface (0-6)
- Background biennial deep (0-4)
- 0-6, 6-12, 12-24, 24-36, 36-48
- Analyze for NH4-N, NO3-N, P, K, pH
12Other Permit Monitoring Requirements
- Vegetative Cover
- Submit photos 3 times per year
- Rainfall and Temperature
- Record daily
13Continuous Monitoring Equipment Components
- Flume sampling and flow monitoring
- In-pipe sampling and flow monitoring
- Rainfall data collection and data transfer
- Monitoring equipment power sources
14Flume Monitoring
- Primary Components
- ISCO Sampler 6712 (2515)
- 1.5 H-flume stilling well (1100)
- ISCO Submerged Level Probe 720 (1390)
- Total 5005
- Require battery backed up by either a solar
or an AC power source
15In-Pipe Monitoring
- Primary Components
- ISCO Sampler 6712 (2515)
- ISCO Velocity Meter 720 (2695)
- Total 5210
- Require either a solar or an AC power source
16Weather Data and Data Transfer
- Measure and log rainfall and temperature
- data at settling basin sampling locations
- Primary Components
- ISCO Cell Phone Pkg. (1620)
- ISCO Rain Gauge 674 (625)
- ISCO Data Transfer Device 581 (562)
- Hobo Temperature Logger (50)
- Total 2857
17Power Sources
- 120V Power Source
- AC Battery Charger (95)
- 12V Deep Cycle Battery (150)
- Monitor unit housing (200)
- Total 445
- Solar Power Source
- Solar Panel (150)
- 12V Deep Cycle Battery (150)
- Monitor unit housing (200)
- Total 500
18System Descriptions
19Central IA 11400 Head feedlot, 1000 head on
research site
Beef Feedlot
Settling Basin
Settling Basin
VTA
VTA
VTA
Engineering Design Firm Curry-Wille Associates
Drawing not to scale
20Central IA 1 Research Section
- Research Section
- Feedlot 333,000 ft2
- Settling Basin 14,000 ft2
- VTAs 122,000 ft2
- VTA Feedlot Ratio 0.371
- VTS Feedlot Ratio 0.411
Settling Basin
Pipe
1
VTA
VTA
2
Flume
Drawing not to scale
21Settling Basin
22 Settling Basin Outlet and Distribution Box
23Distribution Channel from Settling Basin to
Initial Concrete Spreader
24Initial Concrete Spreader at Top of VTA
25Geotextile Spreaders
26System Status
- Major construction completed, vegetation planted
fall 2005 - Spreaders installed
- Monitoring equipment has been selected
- Planned as second site ISU will instrument for
monitoring - Monitoring equipment will be installed prior to
July 1, 2006
27Central IA 2 2400 Head feedlot, 800 head on
research site
VIB
VIB
VIB
VTA
Settling Basin
VIB
VTA
VTA
Beef Feedlot
Beef Feedlot
Settling Basin
Beef Feedlot
Beef Feedlot
Settling Basin
VIB
Drawing not to scale
Engineering Design Firm Curry-Wille Associates
28Central IA 2
29Central IA 2 Research Section
- Research Section
- Feedlot 115,000 ft2
- Settling Basin 8,000 ft2
- VIB 35,000 ft2
- VTA 27,000 ft2
- VIB Feedlot Ratio 0.311
- VTA Feedlot Ratio 0.231
- VIB/VTA Feedlot Ratio 0.541
- VTS Feedlot Ratio 0.601
Flume
3
VIB
VTA
1
2
Pipe
Settling Basin
Pipe
Drawing not to scale
30 Settling Basin Outlet to Central VIB / VTA
31Central VIB / VTA
VTA
VIB
32 Lift Sump from Center VIB to Center VTA
33System Status
- Major construction completed, vegetated fall 2005
- Spreaders not installed, will be gated pipe
- Will be first location that ISU will install
monitoring equipment
34Additional Study
- Study of crop system VTA vs. reed grass VTA
- High level of producer interest
- Would allow them to take less crop ground out of
production - Need research to determine feasibility
- Central IA 2 site has ability to test a cropped
VTA - Need additional funds to perform that study
35Northwest IA 11400 Head feedlot, 800 head
included in research portion
Beef Feedlot
Beef Feedlot
Settling Basin
Settling Basin
VTA
VTA
VTA
VTA
Engineering Design Firm Curry-Wille Associates
VTA
Drawing not to scale
36Northwest IA 1 Research Section
- Research Section
- Feedlot 314,000 ft2
- Settling Basin 16,000 ft2
- VTA 181,000 ft2
- VTA Feedlot Ratio 0.581
- VTS Feedlot Ratio 0.631
Pipe
1
Flume
2
Drawing not to scale
37Settling Basin and Outlet into VTA
38Settling Basin Outlet into VTA
39Research VTA
40System Status
- Major construction completed, no vegetation
- Spreaders not installed, will be gated pipe
- Monitoring equipment has been selected
- Monitoring equipment will be installed prior to
July 1, 2006
41Northwest IA 2
4000 head feed lot with 1 VIB and 1 VTA operating
as a recycle system
Beef Feedlot
Settling Basin
VIB
VTA
Engineering Design Firm Curry-Wille Associates
Drawing not to scale
42Northwest IA 2 Research Section
Pipe
- Research Section
- Feedlot 319,000 ft2
- Settling Basin 10,000 ft2
- VIB 106,000 ft2
- VTA 65,000 ft2
- VIB Feedlot Ratio 0.331
- VTA Feedlot Ratio 0.201
- VIB/VTA Feedlot Ratio 0.531
- VTS Feedlot Ratio 0.571
2
Settling Basin
Flume
1
VIB
VTA
3
Pipe
Drawing not to scale
43Settling Basin Outlet to VIB
44Flume to go here
Settling Basin Outlet to VIB
45From Settling Basin Across VIB
46Top of VTA
Lift Sump from VIB to VTA
47Research VTA
48VIB and VTA Discharge Return Pipe
49Southwest IA 1
2240 head feedlot, whole system within research
portion
Beef Feedlot
Beef Feedlot
Proposed Design
Settling Basin
VTA
Engineering Design Firm Curry-Wille Associates
Drawing not to scale
50Southwest IA 1 Research Section
Settling Basin
1
Pipe
VTA
2
Flume
Drawing not to scale
51System Status
- No construction completed
- Monitoring equipment has been considered
- Planned as fifth site ISU will instrument for
monitoring - Permit effective date not yet established
52Southwest IA 2
5500 head feedlot, 1000 head within the research
portion
Beef Feedlot
Settling Bench
Bench or Basin
Settling Bench
VTA
VTA
VTA
VTA
VTA
VTA
Drawing not to scale
Engineering Design Firm Agricultural
Engineering Associates
53Southwest IA 2 Research Section
Flume
1
Settling Bench
VTA
2
Pipe
Drawing not to scale
54Southwest IA 2
- Unique to the project
- Settling benches instead of settling basins
- Settling benches less expensive to install
- Permit in process
- Effective date set when final permit is issued
55Southwest IA 2
56(No Transcript)
57System Status
- No construction completed
- Engineer has requested June 1, 2007 effective
permit date - Draft permit has been issued
58Construction Issues
- Diversion of run-off during construction and
vegetation phase - Discharge of VTA run-off into crop systems
- Adequate fall to install flumes
59Runoff Diversion around VTS
60Monitoring Issues
- How to handle VTA discharge not related to basin
discharges - Adequate fall to operate flumes
- Monitoring on non-research sites
61Questions Comments