Activity-on-Node Network Fundamentals - PowerPoint PPT Presentation

About This Presentation
Title:

Activity-on-Node Network Fundamentals

Description:

Network-Planning Models ... LS=14. LF=15. Duration = 15 weeks. Example 1: Determine late starts and late finish times ... Time-Cost Models ... – PowerPoint PPT presentation

Number of Views:130
Avg rating:3.0/5.0
Slides: 32
Provided by: angel9
Category:

less

Transcript and Presenter's Notes

Title: Activity-on-Node Network Fundamentals


1
Chapter 10
2
Activity-on-Node Network Fundamentals
3
Network-Planning Models
  • A project is made up of a sequence of activities
    that form a network representing a project.
  • The path taking longest time through this network
    of activities is called the critical path.
  • The critical path provides a wide range of
    scheduling information useful in managing a
    project.
  • Critical Path Method (CPM) helps to identify the
    critical path(s) in the project networks.

4
Prerequisites for Critical Path Methodology
  • A project must have
  • well-defined jobs or tasks whose completion
    marks the end of the project
  • independent jobs or tasks
  • and tasks that follow a given sequence.

5
Types of Critical Path Methods
  • CPM with a Single Time Estimate
  • Used when activity times are known with
    certainty.
  • Used to determine timing estimates for the
    project, each activity in the project, and slack
    time for activities.
  • CPM with Three Activity Time Estimates
  • Used when activity times are uncertain.
  • Used to obtain the same information as the Single
    Time Estimate model and probability information.
  • Time-Cost Models
  • Used when cost trade-off information is a major
    consideration in planning.
  • Used to determine the least cost in reducing
    total project time.

6
Steps in the CPM with Single Time Estimate
  • 1. Activity Identification.
  • 2. Activity Sequencing and Network Construction.
  • 3. Determine the critical path.
  • From the critical path all of the project and
    activity timing information can be obtained.

7
Example 1. CPM with Single Time Estimate
Consider the following consulting project
Develop a critical path diagram and determine the
duration of the critical path and slack times for
all activities
8
Example 1 First draw the network
Act. Imed. Pred. Time
A None 2
B A 1
C B 1
D C 2
E C 5
F D,E 5
G F 1
C(1)
9
Example 1 Determine early starts and early
finish times
ES4 EF6
ES0 EF2
ES2 EF3
ES3 EF4
C(1)
ES4 EF9
10
Example 1 Determine early starts and early
finish times
ES4 EF6
ES0 EF2
ES2 EF3
ES3 EF4
C(1)
ES4 EF9
WHAT IS EF OF THE PROJECT?
11
Example 1 Determine late starts and late finish
times
C(1)
LS14 LF15
Duration 15 weeks
12
Example 1 Determine late starts and late finish
times
C(1)
LS14 LF15
Duration 15 weeks
13
Example 1 Determine late starts and late finish
times
LS7 LF9
C(1)
LS14 LF15
LS9 LF14
LS ? LF ?
LS4 LF9
14
Example 1 Determine late starts and late finish
times
LS7 LF9
C(1)
LS14 LF15
LS9 LF14
LS4 LF9
15
Example 1 DONT WRITE DOWN, JUST TO SHOW ALL
NUMBERS
ES4 EF6
D(2)
ES0 EF2
ES2 EF3
ES3 EF4
LS7 LF9
C(1)
ES4 EF9
LS14 LF15
LS9 LF14
E(5)
LS4 LF9
16
NOW
  • FOR CRITICAL PATH

17
Example 1 Critical Path Slack
ALL THAT IS NEEDED ES LS or EF LF I
PREFER ES LS
D(2)
C(1)
E(5)
18
Example 1 Critical Path Slack
ES4
D(2)
ES0
ES2
ES3
LS7
C(1)
ES4
LS14
LS9
E(5)
LS4
Duration 15 weeks
19
Example 1 Critical Path Slack
ES4
D(2)
ES0
ES2
ES3
LS7
C(1)
F(5)
ES4
LS14
LS9
A CHECK TASK LS - ES CP A 0 - 0
YES B 2 - 2 YES C 3
- 3 YES D 7 - 4 NO E
4 - 4 YES F 9 - 9
YES G 14 - 14 YES
E(5)
LS4
THEREFORE CP A-B-C-E-F-G
20
Example 2. CPM with Three Activity Time Estimates
b
a
m
21
Example 2. Expected Time Calculations
ET(A) 34(6)15 6
ET(A)42/67
22
Example 2. Network
23
Example 2. Network
ES7
ES21
Duration 54 Days
LS21
LS7
C(14)
E(11)
ES32
ES0
LS32
LS0
H(4)
A(7)
ES36
D(5)
F(7)
LS36
I(18)
ES12
ES7
LS25
LS20
B (5.333)
G(11)
ES0
ES5.333
LS25
LS19.667
24
THEREFORE
  • CRITICAL PATH IS
  • A-C-E-H-I

25
Example 2. Probability Exercise
What is the probability of finishing this project
in less than 53 days?
p(t lt D)
t
TE 54
26
(Sum the variance along the critical path.)
27
p(t lt D)
t
TE 54
D53
or - .16
p(Z lt -.16) .5 - .0636 .436, or 43.6
(Appendix D)
Std Normal Dist.
There is a 43.6 probability that this project
will be completed in less than 53 weeks.
28
Example 2. Additional Probability Exercise
  • What is the probability that the project duration
    will exceed 56 weeks?

29
Example 2. Additional Exercise Solution
or .31
p(Z gt.31) .5 - .1217 .378, or 37.8
(Appendix D)
Std Normal Dist.
30
Time-Cost Models
  • Basic Assumption Relationship between activity
    completion time and project cost.
  • Time Cost Models Determine the optimum point in
    time-cost tradeoffs.
  • Activity direct costs.
  • Project indirect costs.
  • Activity completion times.

31
CPM Assumptions/Limitations
  • Project activities can be identified as entities.
    (There is a clear beginning and ending point for
    each activity.)
  • Project activity sequence relationships can be
    specified and networked.
  • Project control should focus on the critical
    path.
  • The activity times follow the beta distribution,
    with the variance of the project assumed to equal
    the sum of the variances along the critical path.
    Project control should focus on the critical
    path.
Write a Comment
User Comments (0)
About PowerShow.com