Title: Work Zone
1(No Transcript)
2Work Zone Sign Support Design in accordance
with 2001 AASHTO Standard Specifications
3http//www.dot.state.fl.us/rddesign/DesignStandard
s/Standards.htm
July 2007 to July 2008 Standards
Modifications Interim Index
July 2008 2008 Design Standards
4New IndexEffective Date July 2007
5GENERAL NOTES All signs shall be post mounted
when work operations exceed one day except as
noted in the standards.
6New IndexEffective Date July 2007
7TEMPORARY SIGN SUPPORT NOTES 1. Signs mounted
on temporary supports or barricades, and
barricade/sign combination shall be
crashworthy in accordance with NCHRP-350
requirements and included on the Qualified
Products List (QPL).
8Crashworthy ???
NCHRP-350 Approved Listed on the Q P L
9New IndexEffective Date July 2007
10Post Mounted Sign Notes
- On the QPL
- Sign Support System
- Post Only
- 3 lb/ft
- May be driven
- Post on Breakaway Splice
- 3 lb/ft
- May be on approved breakaway splice
- 4 lb/ft
- Shall be on approved breakaway splice
11Typical Splice Detail
- Must go to QPL Website to get all the details
!!!! - Each Manufacturer has different design that has
been crash tested.
12Typical Splice Detail
- Top Bolt
- 1 Inch Min. From Top of Stub
13Typical Splice Detail
- Top Bolt
- 1 Inch Min. From Top of Stub
- Stub Height
- 4 Inch Max. From Existing Ground
- Most Common Alignment
- Base Post in Front
- (traffic approaching).
- Sign Post in Back
14New IndexEffective Date July 2007
15Mounting Height Min 7-0
Bottom of Sign
Edge of Travelway Elevation
16Clear Height Max.
Bottom of Sign
Ground line at Centerline of Sign
17Criteria
- Number of Post
- Sign Shape
- Sign Size
- Weight of Post
- 3 lb/ft up to 10 feet Clear Height
- 4 lb/ft up to 12 feet Clear Height
- Foundation Depth
- 4.5 feet for 3 lb/ft
- 5.0 feet for 4 lb/ft
18New IndexEffective Date July 2007
19Sign Attachment Detail
Front Side 5/16 Steel Hex Head Bolt And 5/16
Flat Washer
Back Side (not shown) 5/16 Steel Hex Nut And
5/16 Lock Washer
1 min. 6 max. (_at_ CL of Post)
20Check for Appropriate Message Correct Spacing
(Not Hidden) Retroreflective Clean
21Contacts
Stefanie Maxwell Construction 850-414-4314
Dongming White Structures Design 850-414-4308
22BS (Base/Sign) Work Zone Sign Support
23Specification Changes
- Implemented Modifications to the 2007 Standard
Specifications For Lettings - Effective - July 2007
24Worksite Traffic Supervisor
102-3.2
- Ensure that the Worksite Traffic Supervisor
performs the following duties - Is on site during all set up and take down, and
- performs a drive through inspection immediately
- after set up.
25Vehicle and Equipment Visibility
102-5.9
- Equip all pickups and automobiles used on the
- project with a minimum of one Class 2 amber or
- white warning light
Equip all other vehicles and equipment with a
minimum of 4 Sq. ft of reflective sheeting or
flashing lights.
26QPL Submittals
102-9
- Category 2 and 3 Devices
- QPL Submittals must include
- FHWA WZ numbered acceptance letter with
attachments and vendor drawings
27Temporary Vehicular Impact Attenuator
102-13.12
- Payment for restoring damaged attenuators will be
the - manufacturers/distributors invoice price for
the - new materials/parts plus 20 markup. The 20
markup is - compensation for all necessary work, including
but not - limited to labor, equipment, supplies and profit,
as - authorized by the Engineer.
28?