Transcript and Presenter's Notes

Title: Master Slide


1
PUBLIC-PRIVATE PARTNERSHIP TURKISH
EXPERIENCE Mehmet UZUNKAYA Planning Expert
Undersecretariat of SPO
 Concessions and Public-Private
Partnerships Ankara, 10-11 March 2008
2
PPP in TurkeyOTTOMAN PERIOD
  • Public service concessions
  • Railroad, Post, Telegram, Telephone,
    Lighthouse, Port, Pier, Tram, Tunnel,
    Electricity, Gas, Water, etc.
  • Manufacturing Industry Concessions
  • Food, Weaving, Quarry-terrain, Metal Objects,
    Paper, Chemistry, Rubber.

3
PPP in TurkeyRECENT HISTORY
  • Turkey is one of the first countries to apply
    PPPs since 1980s.
  • One of the leading laws in this area is the Law
    3096 on the Assignment of Institutions other than
    Turkish Electricity Administration for
    Electricity Production, Transmission,
    Distribution and Trade dated 1984.

4
PPP in TurkeyMETHODS COVERED BY THR CURRENT
LEGISLATIVE INFRASTRUCTURE
  • Build Operate - Transfer (Laws no 3996, 3465,
    3096)
  • Build - Operate (Law no 4283)
  • Build - Rent - Transfer (Law no 5396)
  • Transfer of operation rights (Law no 4046, 5335,
    3465, 3096)
  • Long term leasing (Law no 5335, 4046)

5
PPP in TurkeyLAWS AND REGULATIONS
  • BUILD OPERATE - TRANSFER LEGISLATION
  • Decision no. 94/5907 on the Law 3996 on
    Performance of Certain Investments and Services
    within the framework of Build-Operate-Transfer
  • 4 Regulations related to Law 3096 on Assignment
    of Institutions other than Turkish Electricity
    Administration for Electricity Production,
    Transmission, Distribution and Trade
  • Law no. 3465 on Assignment of Institutions other
    than General Directorate of State Highways for
    Highway (with tolls) Construction, Maintenance
    and Operation and Regulation no. 93/4186
    regarding this Law

6
PPP in TurkeyLAWS AND REGULATIONS
  • BUILD OPERATE LEGISLATION
  • Law no. 4283 on Establishment of Electricity
    Production Facilities with Build-Operate Model
    and their Operation and Regulation of Electricity
    Sales and Regulation no. 97/9853 regarding this
    Law
  • BUILD RENT TRANSFER LEGISLATION
  • Law on the Addition of an Article to the Health
    Services Law no. 5396 and Regulation no.
    2006/10655 regarding this Law
  • LEGISLATION ON TRANSFER OF OPERATION RIGHTS AND
    LONG TERM LEASING
  • Privatisation Law no. 4046
  • Law no. 5335
  • (Law authorising the State Airports Authority to
    totally or partially transfer its airports to the
    private sector through long term leasing or
    transfer of operation rights methods)

7
PPP in TurkeySECTORS COVERED BY THE CURRENT
LEGISLATIVE INFRASTRUCTURE
  • ENERGY
  • Electricity generation, transmission,
    distribution and trade
  • Dams
  • TRANSPORTATION
  • Highways, bridges, tunnels, carparks, highway
    operation facilities
  • Railroads
  • Ports and airports for civil use
  • AGRICULTURE
  • Irrigation
  • DRINKING WATER, SEWAGE
  • Drinking water
  • Water treatment facility
  • Sewage system
  • HEALTH
  • Hospitals
  • TOURISM
  • Marinas
  • GENERAL ADMINISTRATION
  • Customs
  • MINING
  • Mines and operation facilities
  • ENVIRONMENT
  • Investments on prevention of pollution
  • MANUFACTURE
  • Factories and similar facilities
  • COMMUNICATION

8
PPP in TurkeySECTORAL PRACTICES
  • ENERGY
  • BOT PROJECTS
  • Marmara Ereglisi-Trakya Natural Gas
  • Marmara Ereglisi-Unimar Natural gas
  • Gebze-Dilovasi Natural Gas
  • Esenyurt Natural Gas
  • Birecik Dam and HP
  • Berdan HP
  • Çal HP
  • Çamlica HP
  • Aksu-Çayköy HP
  • Fethiye HP
  • Tohma-Medik HP
  • Girlevik II-Mercan HP
  • Gaziler HP
  • Gönen HP
  • Kisik HP
  • Hasanlar HP
  • Suçati HP
  • Dinar II HP
  • Ahiköy I-II HP
  • Sütçüler HP
  • Bozcaada Wind Power
  • Çesme-Alaçati Wind Power
  • HP Hydroelectric Plant

9
PPP in TurkeySECTORAL PRACTICES
  • ENERGY
  • BO Projects
  • Gebze Natural Gas Combined Binary Power Plant
  • Adapazari Natural Gas Combined Binary Power Plant
  • Izmir Natural Gas Combined Binary Power Plant
  • Ankara Natural Gas Combined Binary Power Plant
  • Iskenderun Geothermal Power Plant
  • TOR Projects
  • Çayirhan Geothermal Power Plant
  • Hazar I-II HP

10
PPP in TurkeySECTORAL PRACTICES
  • TRANSPORTATION
  • AIR TRANSPORTATION
  • Antalya Airport International Terminals I and II
    (BOT)
  • Atatürk Airport International Terminal Building
    (BOT)
  • Dalaman Airport International Terminal Building
    (BOT)
  • Izmir Adnan Menderes Airport International
    Terminal Building (BOT)
  • Ankara Esenboga Airport Domestic and
    International Terminals (BOT)
  • Sabiha Gökçen Airport International Terminal
    Building and Supplementary buildings (BOT)
  • Atatürk Airport Domestic and International
    Terminals (long term leasing)
  • Antalya Airport Domestic and International
    Terminal Buildings (long term leasing)
  • Zonguldak Çaycuma Airport (long term leasing)
  • Antalya Gazipasa Airport (long term leasing)
  • LAND TRANSPORTATION
  • Göcek Tunnel (BOT)
  • Highway Service Facilities (BOT)

11
PPP in TurkeySECTORAL PRACTICES
  • TRANSPORTATION
  • SEA TRANSPORTATION
  • Çanakkale Kepez Port Superstructure Facilities
    (BOT)
  • Güllük Quay (BOT)
  • Bodrum Passenger Quay (BOT)
  • Trabzon Port (TOR)
  • RAIL TRANSPORTATION
  • Antalya-Alanya Railroad Project (BOT)
  • (no tender was submitted)
  • Reconstruction of the Kapikule Border Train
    Station ()
  • URBAN TRANSPORT
  • Istanbul Bosphorus Tunnel Road (BOT) ()
  • () HPC Authorisation was received for BOT
    contract, HPC authorisation will be taken for
    implementation contracts

12
PPP in TurkeySECTORAL PRACTICES
  • TOURISM
  • Bodrum Turgut Reis Marina (BOT)
  • Didim Marina (BOT)
  • Çesme Marina (BOT)
  • Sigacik Marina (BOT)
  • Kas Marina (BOT)
  • Alanya Marina (BOT)
  • Mersin Marina (BOT)
  • Dalaman Marina and Quay (BOT)
  • Datça Marina (BOT)
  • Tekirdag Marina (BOT) ()
  • Yalova Marina (BOT) ()
  • Afsa Island Marina (BOT) ()
  • () HPC Authorisation was received for BOT
    contract, HPC authorisation will be taken for
    implementation contracts
  • .
  • DRINKING WATER
  • Yuvacik Dam (BOT)

13
PPP in TurkeySECTORAL PRACTICES
  • GENERAL ADMINISTRATION
  • Edirne Ipsala Border Gate (BOT)
  • Igdir Gürbulak Border Gate (BOT)
  • Sirnak Habur Border Gate (BOT)
  • Edirne Kapikule Border Gate (BOT)
  • Artvin Sarp Border Gate (BOT)
  • Hatay Cilvegözü Border Gate (BOT) ()
  • Mardin Nusaybin Border Gate (BOT) ()
  • Edirne Hamzabeyli Border Gate (BOT) ()
  • Pazarkule Border Gate ()
  • Esendere Border Gate ()
  • Türkgözü Border Gate ()
  • Dilucu Border Gate ()
  • Akçakale Border Gate ()
  • Öncüpinar Border Gate ()
  • Yayladag Border Gate ()
  • Kirklareli Dereköy Border Gate (BOT) ()
  • Istanbul Halkali Border Gate (BOT) ()

14
PPP in TurkeyPROJECTS AT THE PREPARATION STAGE
PROPOSED BY THE DG STATE HIGHWAYS
  • TRANSPORTATION
  • Gebze-Orhangazi-Izmir Highway (Including the
    Izmit Körfez passage)(377 km) ()
  • Kinali-Malkara-Çanakkale-Savastepe Highway
    (Including the Çanakkale strait passage) (566
    km)
  • Ankara-Izmir Highway (503 km)
  • (Ankara-Izmir)Ayr.-Afyon-Burdur-Antalya Highway
    (345 km)
  • (Ankara-Izmir)Ayr.-Eskisehir-Bursa Highway (202
    km)
  • () HPC Authorisation was received for BOT
    contract, HPC authorisation will be taken for
    implementation contracts.
  • .

15
PPP in TurkeySOME METHODS NOT COVERED BY THE
CURRENT LEGISLATION
  • Design Build Finance - Operate
  • Build Own Operate - Transfer
  • Rehabilitate Operate - Transfer
  • Build Own Operate
  • Build Transfer Operate
  • Made additional investment - Operate
  • Establishing a company with the private sector
  • Shadow tolls

16
PPP in Turkey SOME METHODS NOT COVERED BY THE
CURRENT LEGISLATION
  • Justice Services
  • Education Services
  • Cultural Services
  • In order to set up the legal basis for the shadow
    toll application, which is not covered by the
    existing legislative infrastructure, a draft law
    on amending Law no. 3996 was prepared by the
    Ministry of Finance and was submitted to the
    Parliament. The draft was approved by the
    Planning and Budget Commission. It is expected to
    enter into force in 2008.

17
PPP in TurkeyMAIN PROBLEMS
  • Lack of Institutional Capacity and Structuring in
    PPP Applications
  • Failure to carry out preparation activities for
    PPPs in time and sufficiently to help with the
    analyses on technical, economical and financial
    feasibility of the projects, economical and
    social costs, returns and risks.
  • Lack of interest by the public sector to PPP
    projects as they are financed and operated by the
    private sector.
  • Lack of experience in the public institutions
    related to PPP projects which require more
    complex processes than the classic financing
    methods (differences of knowledge and experience
    between public and private entities)
  • Lack of a specialised unit responsible for the
    analysis, prioritisation and selection of the PPP
    Projects.
  • Lack of a sectoral standardisation related to the
    project documents (feasibility studies,
    contracts, etc).

18
PPP in TurkeyMAIN PROBLEMS
  • Unorganised structure of the existing legislation
    and its narrow scope covering few models
  • Regulation of different models by different laws
    and regulations.
  • Shortage of different models The legislation
    only covers BOT, BO, TOR, Build-Rent-Transfer and
    Long term leasing methods.

19
PPP in TurkeyPROPOSALS FOR SOLUTIONS
  • Centralised Unit
  • Establishment of a centralised unit which will
  • Identify the PPP policies in Turkey,
  • Monitor compliance of the PPP Projects to the
    development plans, programs and sectoral
    policies,
  • Be responsible for the analysis, evaluation,
    prioritisation, selection and monitoring of the
    PPP Projects,
  • Be specialised in PPP area,
  • Prepare guidelines and standard documents for the
    implementing organisations.
  • Drafting of a single framework law which covers
    applicable models and sectors
  • Establishment of a national PPP strategy
  • Raising awareness among and providing information
    to the public institutions about PPP processes

20
PPP in TurkeySTEPS TAKEN FOR SOLUTION
  • Current Situation, Problems and Analysis of Needs
  • Starting from 2005, a series of meetings was
    organised by the Undersecretariat of SPO with the
    participation of the relevant institutions and
    organisations in order to discuss realised PPP
    Projects, experiences, problems and solutions and
    new applicable models and a report was prepared
    as a result.
  • PPP Draft Framework Law
  • In light of the information acquired and the
    needs arose during those meetings, a draft PPP
    framework law, which covers all applicable models
    and sectors, was prepared by the Undersecretariat
    of SPO and submitted to the opinion of relevant
    institutions and.
  • The draft law has been sent to the Prime Ministry
    and is expected to enter into force in 2008.
    Secondary legislation regarding this law will be
    prepared until the end of 2009.

21
PPP in TurkeyINNOVATIONS INTRODUCED BY THE DRAFT
PPP LAW
  • Definition of the Public Private Partnership
    concept
  • Unification of the PPP legislation
  • Definition of PPP models and bringing flexibility
    to the models
  • Extension of the scope by adding new sectors
  • Introduction of objective criteria related to the
    PPP Process
  • Introduction of the risk concept to the PPP
    Projects and definiton of the guarantees

22
PPP in TurkeyINNOVATIONS INTRODUCED BY THE DRAFT
PPP LAW
  • Definition of the Public Private Partnership
    Concept
  • This definition helps to regulate the different
    concepts of private sector participation to
    public services under one title, Public Private
    Partnership, which is a new concept for our
    country.
  • Unification of the PPP Legislation
  • With the draft law, one single framework is
    introduced for the unorganised legislation on
    PPPs. The existing legislation is simplified and
    a single process valid for all applications is
    developed by eliminating differences.

23
PPP in TurkeyINNOVATIONS INTRODUCED BY THE DRAFT
PPP LAW
  • Definition of PPP models and bringing flexibility
    to the models
  • The current models of BOT, BO, Build-Rent and
    Transfer of Operation Rights are now defined
    under one law, which also brings a flexibility to
    implement different types of these models.

24
PPP in TurkeyINNOVATIONS INTRODUCED BY THE DRAFT
PPP LAW
Works such as completion, renovation,development,
research, restoration, maintenance, repair, etc.
are within the scope of build. Shadow tolls
implementation is also covered by the law
25
PPP in TurkeyINNOVATIONS INTRODUCED BY THE DRAFT
PPP LAW
  • Extension of the scope by adding new sectors
  • Areas such as education, culture, justice and
    general administrative infrastructure, which are
    not covered by the existing Public Private
    partnership legislation, are regulated with this
    draft law.
  • Introduction of objective criteria related to the
    PPP Process
  • Feasibility study is introduced as a requirement
    in the selection of the projects and decision
    making process is more clearly and rationally
    defined.
  • HPC (High Planning Council) process
  • Obligation of a feasibility study
  • Risk analyses

26
PPP in TurkeyINNOVATIONS INTRODUCED BY THE DRAFT
PPP LAW
  • Introduction of the risk concept to the PPP
    Projects and definiton of the guarantees
  • It is the first time with this Law that the
    efficient risk sharing concept, which is the
    basic element of successful PPP projects, is
    mentioned. Mechanisms are developed to monitor
    the financial liabilities for the public sector
    which might occur as a result of the guarantees
    and to ensure that these liabilities are in
    compliance with the the macro-economic balances.

27
  • THANK YOU...