Title: ggies gainst pophis
1 ggies gainst pophis
A
A
A
- System Design Review
- Introduction
- December 9, 2008
2Agenda
- Project Background
- Mission Overview
- Mitigation, Payload, Telecom, and Instruments
- Trajectory, Propulsion, and ACS
- Structures, Thermal, and Power
- Budget and Scheduling
- Summary
3Apophis 99942 Background Information
Project Background
- Discovered on June 19th, 2004 by R. A. Tucker, D.
J. Tholen and F. Bernardi at Kitt Peak - Orbital models have identified several close
Earth approaches, occurring roughly every 7
years. When Apophis passes by in 2029 it could
pass through a gravitational keyhole which would
swing Apophis into a collision path with Earth in
2036 - As an Aten class NEA, Apophis rated as high as 4
on the Torino scale but has been downgraded to a
0 as its probability of impact has been commonly
accepted at 1/45,000
Source http//neo.jpl.nasa.gov/apophis
December 9, 2008
4APEP
Project Background
- Agencies from around the world, including
NASA/JPL, Caltech, and Arecibo, have analyzed and
identified Apophis orbital elements and physical
properties with limited levels of accuracy - Uncertainty in the effects from albedo and
gravitational forces over time are again causing
concern about a potential impact with Earth - The Fall 07 426, Spring 08 401 and Fall 08 402
classes started the design of the Apophis
Preliminary Exploration Platform (APEP) mission.
Objectives were - Rendezvous with Apophis in 2013, act as a beacon
to enable precise tracking, - Measure physical characteristics most relevant to
improved accuracy of orbit prediction. - If Apophis is on a collision course with Earth
and planning of a mitigation mission is started
after APEP discovers this fact, changing the
course of the asteroid may be impossible.
AAA System Design Review
4
December 9, 2008
5Current Mission
Project Background
- The challenge facing this team is to develop a
system that can sufficiently modify the
trajectory of Apophis such that it will not
impact the Earth in 2036. - A subsidiary goal is to design the spacecraft
such that it can be fabricated and tested in the
AggieSat Laboratory. - The class was originally split into four teams.
Each team examined multiple methods of
deflection, including but not limited to - Gravity Tractor
- Solar Sublimation
- Kinetic Impactor
- Electric Propulsion Devices
- Albedo Modification Systems
- Nuclear Burst
- Each team then investigated one method in depth
and presented the method to the rest of the
class. The best design was chosen as the system
that would be developed by the whole class as a
unified team. - The Gravity Tractor was chosen as the best design
and therefore is the focus of this presentation. - Albedo modification is being investigated as a
secondary mitigation technique.
AAA System Design Review
5
December 9, 2008
6Apophis 99942 Physical Data
Project Background
- LL-chondrite composition
- Estimated rotational period of 30.57 h
- Keyhole Event - April 2029
- Results in resonant return and impact in April
2036
Sources http//ssd.jpl.nasa.gov/sbdb.cgi?sstr999
42orb1cov0log0discovery
Chesley, Milani, Vokrouhlicky, Icarus 148,
118138 (2000)
6
AAA System Design Review
December 9, 2008
7Rationale for Exploration and Mitigation Mission
Launch Dates
Project Background
2015
2010
2020
2025
2040
2035
2030
December 9, 2008
8 ggies gainst pophis
A
A
A
- System Design Review
- Mission Overview
- December 9, 2008
9Deflect Apophis System(DAS) Mission Statement
Mission Overview
- The DAS mission is to intercept the near-Earth
asteroid Apophis 99942 and perturb its orbit to
prevent an Earth impact in 2036.
December 9, 2008
10Mission Requirements
Mission Overview
- Withstand launch environment associated with an
Atlas V class launch vehicle and space
environment associated with proposed mission
profile - Have a launch date and travel time to Apophis
that permits mitigation to begin no later than
2022 - Be capable of rendezvous with Apophis
- Carry enough consumables to complete the
mitigation mission - Be capable of communications with a ground
station from post-deployment through
end-of-mission - Deflect Apophis by at least 3 Earth radii
- Comply with all US and International laws
10
AAA System Design Review
December 9, 2008
11Mission Overview
Top-Level Mission Profile
Maintain 400 m standoff distance from Apophis
for 4 years
Deploy albedo altering experiment during
mitigation
Launch DAS mission by 2022
Rendezvous with Apophis after 5 month travel
time
Relay data to ground stations on Earth to
determine mitigation effectiveness
AAA System Design Review
12 ggies gainst pophis
A
A
A
- System Design Review
- Mitigation, Payload, Telecom, and Instruments
- December 9, 2008
13Design Requirements
Mitigation, Payload, Telecom, and Instruments
- Mitigation
- Deflect the course of Apophis by a minimum of 3
Earth Radii by 2036 - Telecommunications
- Establish and maintain communication with Earth
- Provide ability to track trajectory of Apophis
- Instruments
- Provide images of Apophis
- Provide ability to track trajectory of Apophis
14Design Assumptions
Mitigation, Payload, Telecom, and Instruments
- Mitigation
- Primary method is gravity tractor
- Mass of Apophis is 2.78?1010 kg
- Apophis diameter is 270 m
- Payload
- Deployment of the albedo change material takes
place near end of primary mitigation - Telecommunications
- Maximum distance from spacecraft to Earth is 2 AU
15Design Approach
Mitigation, Payload, Telecom, and Instruments
- Achieve a balance of reasonable standoff distance
and system mass - Limit the mitigation time period to the lifetime
of the electrical propulsion system - Use telecommunications equipment with deep space
flight heritage - Deploy an experimental albedo change package
16Gravity Tractor Concept
Mitigation, Payload, Telecom, and Instruments
- Use Newtons Law of Universal Gravitation
- Use a spacecraft to impart a gravitational force
upon Apophis to gently move Apophis to a
non-Earth impacting orbit - Utilize the 2029 flyby to enhance mitigation
efforts - Small changes pre-flyby result in large changes
in Apophis trajectory post-flyby
17Standoff Distance and Deflection Results
Mitigation, Payload, Telecom, and Instruments
- Nominal Thrusting Case
- 12 mN of thrust from each of 2 EP thrusters
- 38 canting angle for each thruster
- Total duration of mitigation 4 years
- Resulting nominal standoff distance 222 m from
Apophis CG - Resulting Deflection 60 Earth Radii
Standoff distance is too close to Apophis surface
18Standoff Distance and Deflection Results
Mitigation, Payload, Telecom, and Instruments
The selected standoff distance is shown here
- Upper Bounding Case for standoff distance
- 4 mN of thrust from each of 2 EP thrusters
(minimum case) - 38 canting angle for each thruster
- Total duration of mitigation 4 years
- Resulting maximum standoff distance 385 m from
Apophis CG - Resulting Deflection 25 Earth Radii
19Albedo Change
Mitigation, Payload, Telecom, and Instruments
- Any change in albedo alters solar pressure and
the Yarkovsky effect - Fmax 0.70 N from solar pressure and Yarkovsky
effect - Orbit Deviation (assuming 25 kg coating)
- By 2036, a 4 change in albedo (beginning in
2018) will deflect Apophis between 17 and 45
Earth radii - Model based on comparison with results of Chesley
paper
20Albedo Treatment Options
Mitigation, Payload, Telecom, and Instruments
- Paint
- Heavy
- Difficult to apply
- Freezing possible
- Chalk
- Lightweight
- May coat unevenly
- Reflective Sheet
- Very large
- Difficult to open and deploy onto surface
- Glass Beads
- Heavy
- May be covered by dusty surface
- Easy to carry and release
21Albedo Change Mechanism
Clam-shell release near the asteroid
Spring-Loaded cassette ejector
Pressurized clam-shell cassette containing a cake
of hydrolyzed Nano Titanium Dioxide Powder
(cosmetic powder)
Explosive decompression disburses powder and
ionizes the solid matrix
Electrostatic force attracts and binds the powder
to the asteroid surface
21
AAA System Design Review
December 9, 2008
22Baseline Design
Mitigation, Payload, Telecom, and Instruments
- Telecom subsystem is a dual string design
- Support two-way X-Band plus Ka-Band downlink
- Equipment includes X/X/Ka SDST transponders, 17W
X-Band SSPA, 3.5 W Ka-Band SSPA, 1 m HGA, 2
X-Band LGAs, waveguide transfer switches, X-Band
diplexers, filters, waveguide and coax cabling
Design Rationale
- Dual string design due to mission duration
- Ka-Band downlink added for improved navigational
accuracy
23Tracking Apophis
Mitigation, Payload, Telecom, and Instruments
- The instruments in conjunction with the telecom
subsystem need to be capable of tracking the
deflected trajectory of Apophis - Tracking will use the same method as APEP mission
- Uses 2 Laser Range Finders and an optical
navigation imaging camera - Uses telecom subsystem as either a transponder or
a beacon with the DSN to relay position of Apophis
24Navigation Camera
Mitigation, Payload, Telecom, and Instruments
- The camera will serve as an imaging camera to
collect science data - The data will include high-resolution color
images of the asteroid - The nav camera will provide images taken through
different filters - These images will provide information on gas
composition, gas and dust dynamics, and jet
phenomena, if they exist.
25Mitigation, Payload, Telecom, and Instruments
- Laser Range Finder (LRF)
- The laser range finder will be used to measure
the distance between the spacecraft and Apophis
surface. It is also possible to use Doppler
effect techniques to measure the relative
velocity between the spacecraft and Apophis. - In order to make a stereoscopic
- measurement of the asteroid surface
- to determine whether it's rigid or rubble
- pile, two LRFs will be used.
26Laser Range Finder
Mitigation, Payload, Telecom, and Instruments
- A conceptual design of the laser range finder is
shown. It consists of - A solid-state laser transmitter with optical
diverger - A reflective telescope that functions as an
optical receiver - An Analog/Digital conversion unit and digital
processing unit
27 ggies gainst pophis
A
A
A
- System Design Review
- Trajectory, Propulsion, and ACS
- December 9, 2008
28Requirements and Assumptions
Trajectory, Propulsion, and ACS
- Trajectory
- Launch to Earth escape
- Transfer orbit for rendezvous with Apophis
- Maintain tractor position at Apophis
- Propulsion
- Use chemical rocket for launch/transfer to
Apophis - Use electric engine for mitigation
station-keeping - Attitude Control System (ACS)
- Maintain desired orbital position and orientation
relative to Apophis
28
AAA System Design Review
December 9, 2008
29Lambert Problem Setup
Trajectory, Propulsion, and ACS
Source Dr. John Junkins
30Solution to Lambert Problem
Trajectory, Propulsion, and ACS
Depart Feb 19, 2022 Time of Flight 144 days
Minimum ?v Solution (4.276 km/s)
30
AAA System Design Review
December 9, 2008
31Launch Window
Trajectory, Propulsion, and ACS
Departure Date February 19, 2022 (/- 25
days) Time of Flight 144 Days
32Launch Vehicle
Trajectory, Propulsion, and ACS
- The launch vehicle will be an expendable launch
vehicle from the Atlas V class - The Atlas V 401 is a 2 stage rocket capable of
launching up to 2400 kg to Earth escape. - Notable payloads to Earth escape
- Mars Reconnaissance Orbiter
- New Horizons
33Transfer Orbit
Trajectory, Propulsion, and ACS
- Assume an Isp329 sec
- In order to arrive at Apophis with a 500 kg
spacecraft, 1381 kg of chemical fuel is required - Mass at launch (to Earth escape) is 1881 kg
33
AAA System Design Review
December 9, 2008
34Engine Selection
Trajectory, Propulsion, and ACS
- Aerojet 445
- Chemical Rocket used for transfer to Apophis and
rendezvous
- Busek BHT-200 (x2)
- Electric Engine used to perform gravity tractor
operation - Each engine is installed at a 38º canting angle
to avoid exhaust impingement on Apophis
35Aerojet 445 Hi-PAT Specifications
Trajectory, Propulsion, and ACS
- Specific Impulse 329 s
- Thrust/Steady State 445 N
- Mass 5.44 kg
- Propellant Type Hydrazine/NTO
- Propellant Mass 1381 kg
- Flow Rate 141 g/s
- Currently in use
36Busek BHT-200 Specifications
Trajectory, Propulsion, and ACS
- Input Power 50W-300W, 200Wnominal
- Voltage 250V
- Current 800 mA
- Propellant Flowrate 0.94 mg/sec
- Xenon Propellant Mass 250 kg
- Thrust 4-17 mN, 12 mNnominal
- Specific Impulse 1390 sec
- Efficiency 43.5
- Successfully used by the TacSat-2 experimental
satellite launched on December 16, 2006
Source http//www.busek.com/index.html
37Attitude Determination
Trajectory, Propulsion, and ACS
- 2 Star Trackers
- For improved accuracy and redundancy
- 8 Sun Sensors
- Adcole coarse 1-axis
- 1 Inertial Measurement Unit
- Northrop Grumman LN-200
37
AAA System Design Review
December 9, 2008
38Attitude Control and Manuevering
Trajectory, Propulsion, and ACS
- 4 Reaction Wheels
- Teldix RSI 02 0.2-1.6 Nms momentum capacity
- For stability and slewing
- Pyramid formation
- Hydrazine Thrusters
- 8 MR-103C 1 N (0.2-lbf) by Aerojet
- Pointing and momentum dumping
- 4 MR-106E 22 N (5-lbf) by Aerojet
- Thrust vector control
39 ggies gainst pophis
A
A
A
- System Design Review
- Structure, Thermal, and Power
- December 9, 2008
40Design Requirements
Structure, Thermal, and Power
- Structures
- Structure should withstand launch loads,
frequencies, and pressures - Satellite bus should provide support for all
instruments - Thermal
- Maintain all instruments and components within
survivable temperatures - Power
- Provide enough power to operate necessary systems
through all phases of the mission
41Design Assumptions
Structure, Thermal, and Power
- Spacecraft mass at Apophis 500 kg
- Optimal angle of Hall thrusters 38
- Assume worst case hot and cold are at periapse
and apoapse of Apophis orbit, respectively - Spacecraft modeled as a conductive sphere for
thermal analysis
42Conceptual Bus Design
Structure, Thermal, and Power
- Utilize body mounted solar arrays
- All fuel tanks and components housed internally
for thermal control - Material of main structure 6061T6 Al
43Thermal
Structure, Thermal, and Power
Approximate spacecraft as a sphere of equivalent
surface area.
Model does not identify hot/cold spots Internal
satellite configuration currently unknown
44Thermal
Structure, Thermal, and Power
45Power Requirements
Structure, Thermal, and Power
- Provide enough power and storage to operate the
spacecraft in all modes throughout the mission - Provide power switching and power regulation
- Redundancy as necessary
- Solar array is primary power source
46Power Assumptions
Structure, Thermal, and Power
- Battery Assumptions
- Rechargeable batteries will be used for secondary
power - Battery will provide high A-h per unit mass
- Bus voltage of at least 28 Volts
- Array Assumptions
- Array is large enough to charge the batteries
while supplying power to spacecraft - Array must provide 1100 Watts
47UTJ GaAs Solar Array
Structure, Thermal, and Power
- Gallium Arsenide has a high absorptivity
- Requires few microns of thickness to absorb
sunlight - GaAs cells are relatively insensitive to heat
- Gallium arsenide is very resistant to radiation
damage
48Lithium Ion Battery
Structure, Thermal, and Power
- Li-ion batteries are lighter than other
equivalent batteries - They have a higher energy density than most
batteries - They operate at higher voltages compared to most
batteries - They have a lower self discharge rate (Retain
charge for long time)
49 ggies gainst pophis
A
A
A
- System Design Review
- Budget and Scheduling
- December 9, 2008
50Timeline
Budget and Scheduling
2010 Finalize preliminary design
2022 Rendezvous complete. Begin mitigation
2011 Begin prelim. testing analysis
2027 Mission Ends
2022 LAUNCH
2012 Begin major testing analysis
2018 Make adjustments, Continue testing
2015 Prototypes assembled for testing
Albedo Mitigation Study
AAA System Design Review
51Work Breakdown Example
Budget and Scheduling
from Space Mission Analysis Design
52Key Funding Assumptions
Budget and Scheduling
- For the purposes of this study, it should be
assumed that the total funding available for
development of a 2022 Apophis deflection mission
will be - Between 100-200 million dollars
- Excluding Launch vehicle, mission operations
system, technology development, flight validation
demonstrations, mission operations
53Cost Estimation Method
Budget and Scheduling
- Parametric Estimating- Use math relations between
design parameters and cost that are compiled from
statistics of previous programs. These relations
are called CERs (Cost Estimating
Relationships). - CERs only applicable to the range of historical
data - Parametric estimating unsatisfactory for items
involving major technological advancements or
fundamental paradigm shifts. The current mission
does not fall into this category so this
estimation method is sufficient.
Space Mission Analysis Design
54Terms
Budget and Scheduling
from Space Mission Analysis Design
55Breakdown of Small Satellite Costs
Budget and Scheduling
from Space Mission Analysis Design
43 contingency , then multiply by factor of 3
56Comm CDH Subsystems
Budget and Scheduling
57Sensors and Telecom
Budget and Scheduling
58ACS Subsystem
Budget and Scheduling
59Structures and Mechanisms
Budget and Scheduling
60Thermal Management Subsystem
Budget and Scheduling
61Power Subsystem
Budget and Scheduling
62Propulsion Subsystem
Budget and Scheduling
63Educational Outreach
Budget and Scheduling
- Target audience
- Educational institutions
- Classroom presentations
- Introduce students to
- space technology
- Design competition
- Opportunities for students to do research
- Development of creative solutions for the mission
- Opportunities for interested parties to
participate in modification of albedo studies
64Trajectory, Propulsion
Structures, Thermal, Power
- Launch Window 1/28/22-3/16/22
- Flight Time 144 Days
- Total Delta V 4.28 km/s
- Launch Vehicle Atlas V class
- BUSEK BHT 200 4-17 mN
- Chemical transfer, EP for mitigation
- Dry Mass 250 kg
- Primary Material 6061-T6 Al
- Worst Case Hot 61 C
- Worst Case Cold -25 C
- Array GaAs to supply 1100 Watts, 4.8 m2
- Batteries Saft Li-Ion
Mitigation, Payload, Telecom
Budget and Scheduling
- Gravity Tractor Duration 4 Years (total)
- Standoff 385 m
- Albedo treatment experiment
- Overall Budget 100-200 million
- Initial Projected Cost - 80.2 million
- Preliminary Design Complete 2010
- Testing and Analysis 2010-2018
- Launch 2022
AAA System Design Review