ggies gainst pophis - PowerPoint PPT Presentation

1 / 64
About This Presentation
Title:

ggies gainst pophis

Description:

AAA. System Design Review. Project Background ... AAA. System Design Review. 7. Rationale for Exploration and Mitigation Mission Launch Dates ... – PowerPoint PPT presentation

Number of Views:209
Avg rating:3.0/5.0
Slides: 65
Provided by: keh
Category:
Tags: aaa | gainst | ggies | pophis

less

Transcript and Presenter's Notes

Title: ggies gainst pophis


1
ggies gainst pophis
A
A
A
  • System Design Review
  • Introduction
  • December 9, 2008

2
Agenda
  • Project Background
  • Mission Overview
  • Mitigation, Payload, Telecom, and Instruments
  • Trajectory, Propulsion, and ACS
  • Structures, Thermal, and Power
  • Budget and Scheduling
  • Summary

3
Apophis 99942 Background Information
Project Background
  • Discovered on June 19th, 2004 by R. A. Tucker, D.
    J. Tholen and F. Bernardi at Kitt Peak
  • Orbital models have identified several close
    Earth approaches, occurring roughly every 7
    years. When Apophis passes by in 2029 it could
    pass through a gravitational keyhole which would
    swing Apophis into a collision path with Earth in
    2036
  • As an Aten class NEA, Apophis rated as high as 4
    on the Torino scale but has been downgraded to a
    0 as its probability of impact has been commonly
    accepted at 1/45,000

Source http//neo.jpl.nasa.gov/apophis
December 9, 2008
4
APEP
Project Background
  • Agencies from around the world, including
    NASA/JPL, Caltech, and Arecibo, have analyzed and
    identified Apophis orbital elements and physical
    properties with limited levels of accuracy
  • Uncertainty in the effects from albedo and
    gravitational forces over time are again causing
    concern about a potential impact with Earth
  • The Fall 07 426, Spring 08 401 and Fall 08 402
    classes started the design of the Apophis
    Preliminary Exploration Platform (APEP) mission.
    Objectives were
  • Rendezvous with Apophis in 2013, act as a beacon
    to enable precise tracking,
  • Measure physical characteristics most relevant to
    improved accuracy of orbit prediction.
  • If Apophis is on a collision course with Earth
    and planning of a mitigation mission is started
    after APEP discovers this fact, changing the
    course of the asteroid may be impossible.

AAA System Design Review
4
December 9, 2008
5
Current Mission
Project Background
  • The challenge facing this team is to develop a
    system that can sufficiently modify the
    trajectory of Apophis such that it will not
    impact the Earth in 2036.
  • A subsidiary goal is to design the spacecraft
    such that it can be fabricated and tested in the
    AggieSat Laboratory.
  • The class was originally split into four teams.
    Each team examined multiple methods of
    deflection, including but not limited to
  • Gravity Tractor
  • Solar Sublimation
  • Kinetic Impactor
  • Electric Propulsion Devices
  • Albedo Modification Systems
  • Nuclear Burst
  • Each team then investigated one method in depth
    and presented the method to the rest of the
    class. The best design was chosen as the system
    that would be developed by the whole class as a
    unified team.
  • The Gravity Tractor was chosen as the best design
    and therefore is the focus of this presentation.
  • Albedo modification is being investigated as a
    secondary mitigation technique.

AAA System Design Review
5
December 9, 2008
6
Apophis 99942 Physical Data
Project Background
  • LL-chondrite composition
  • Estimated rotational period of 30.57 h
  • Keyhole Event - April 2029
  • Results in resonant return and impact in April
    2036

Sources http//ssd.jpl.nasa.gov/sbdb.cgi?sstr999
42orb1cov0log0discovery
Chesley, Milani, Vokrouhlicky, Icarus 148,
118138 (2000)
6
AAA System Design Review
December 9, 2008
7
Rationale for Exploration and Mitigation Mission
Launch Dates
Project Background
2015
2010
2020
2025
2040
2035
2030
December 9, 2008
8
ggies gainst pophis
A
A
A
  • System Design Review
  • Mission Overview
  • December 9, 2008

9
Deflect Apophis System(DAS) Mission Statement
Mission Overview
  • The DAS mission is to intercept the near-Earth
    asteroid Apophis 99942 and perturb its orbit to
    prevent an Earth impact in 2036.

December 9, 2008
10
Mission Requirements
Mission Overview
  • Withstand launch environment associated with an
    Atlas V class launch vehicle and space
    environment associated with proposed mission
    profile
  • Have a launch date and travel time to Apophis
    that permits mitigation to begin no later than
    2022
  • Be capable of rendezvous with Apophis
  • Carry enough consumables to complete the
    mitigation mission
  • Be capable of communications with a ground
    station from post-deployment through
    end-of-mission
  • Deflect Apophis by at least 3 Earth radii
  • Comply with all US and International laws

10
AAA System Design Review
December 9, 2008
11
Mission Overview
Top-Level Mission Profile
Maintain 400 m standoff distance from Apophis
for 4 years
Deploy albedo altering experiment during
mitigation
Launch DAS mission by 2022
Rendezvous with Apophis after 5 month travel
time
Relay data to ground stations on Earth to
determine mitigation effectiveness
AAA System Design Review
12
ggies gainst pophis
A
A
A
  • System Design Review
  • Mitigation, Payload, Telecom, and Instruments
  • December 9, 2008

13
Design Requirements
Mitigation, Payload, Telecom, and Instruments
  • Mitigation
  • Deflect the course of Apophis by a minimum of 3
    Earth Radii by 2036
  • Telecommunications
  • Establish and maintain communication with Earth
  • Provide ability to track trajectory of Apophis
  • Instruments
  • Provide images of Apophis
  • Provide ability to track trajectory of Apophis

14
Design Assumptions
Mitigation, Payload, Telecom, and Instruments
  • Mitigation
  • Primary method is gravity tractor
  • Mass of Apophis is 2.78?1010 kg
  • Apophis diameter is 270 m
  • Payload
  • Deployment of the albedo change material takes
    place near end of primary mitigation
  • Telecommunications
  • Maximum distance from spacecraft to Earth is 2 AU

15
Design Approach
Mitigation, Payload, Telecom, and Instruments
  • Achieve a balance of reasonable standoff distance
    and system mass
  • Limit the mitigation time period to the lifetime
    of the electrical propulsion system
  • Use telecommunications equipment with deep space
    flight heritage
  • Deploy an experimental albedo change package

16
Gravity Tractor Concept
Mitigation, Payload, Telecom, and Instruments
  • Use Newtons Law of Universal Gravitation
  • Use a spacecraft to impart a gravitational force
    upon Apophis to gently move Apophis to a
    non-Earth impacting orbit
  • Utilize the 2029 flyby to enhance mitigation
    efforts
  • Small changes pre-flyby result in large changes
    in Apophis trajectory post-flyby

17
Standoff Distance and Deflection Results
Mitigation, Payload, Telecom, and Instruments
  • Nominal Thrusting Case
  • 12 mN of thrust from each of 2 EP thrusters
  • 38 canting angle for each thruster
  • Total duration of mitigation 4 years
  • Resulting nominal standoff distance 222 m from
    Apophis CG
  • Resulting Deflection 60 Earth Radii

Standoff distance is too close to Apophis surface
18
Standoff Distance and Deflection Results
Mitigation, Payload, Telecom, and Instruments
The selected standoff distance is shown here
  • Upper Bounding Case for standoff distance
  • 4 mN of thrust from each of 2 EP thrusters
    (minimum case)
  • 38 canting angle for each thruster
  • Total duration of mitigation 4 years
  • Resulting maximum standoff distance 385 m from
    Apophis CG
  • Resulting Deflection 25 Earth Radii

19
Albedo Change
Mitigation, Payload, Telecom, and Instruments
  • Any change in albedo alters solar pressure and
    the Yarkovsky effect
  • Fmax 0.70 N from solar pressure and Yarkovsky
    effect
  • Orbit Deviation (assuming 25 kg coating)
  • By 2036, a 4 change in albedo (beginning in
    2018) will deflect Apophis between 17 and 45
    Earth radii
  • Model based on comparison with results of Chesley
    paper

20
Albedo Treatment Options
Mitigation, Payload, Telecom, and Instruments
  • Paint
  • Heavy
  • Difficult to apply
  • Freezing possible
  • Chalk
  • Lightweight
  • May coat unevenly
  • Reflective Sheet
  • Very large
  • Difficult to open and deploy onto surface
  • Glass Beads
  • Heavy
  • May be covered by dusty surface
  • Easy to carry and release

21
Albedo Change Mechanism
Clam-shell release near the asteroid
Spring-Loaded cassette ejector
Pressurized clam-shell cassette containing a cake
of hydrolyzed Nano Titanium Dioxide Powder
(cosmetic powder)
Explosive decompression disburses powder and
ionizes the solid matrix
Electrostatic force attracts and binds the powder
to the asteroid surface
21
AAA System Design Review
December 9, 2008
22
Baseline Design
Mitigation, Payload, Telecom, and Instruments
  • Telecom subsystem is a dual string design
  • Support two-way X-Band plus Ka-Band downlink
  • Equipment includes X/X/Ka SDST transponders, 17W
    X-Band SSPA, 3.5 W Ka-Band SSPA, 1 m HGA, 2
    X-Band LGAs, waveguide transfer switches, X-Band
    diplexers, filters, waveguide and coax cabling

Design Rationale
  • Dual string design due to mission duration
  • Ka-Band downlink added for improved navigational
    accuracy

23
Tracking Apophis
Mitigation, Payload, Telecom, and Instruments
  • The instruments in conjunction with the telecom
    subsystem need to be capable of tracking the
    deflected trajectory of Apophis
  • Tracking will use the same method as APEP mission
  • Uses 2 Laser Range Finders and an optical
    navigation imaging camera
  • Uses telecom subsystem as either a transponder or
    a beacon with the DSN to relay position of Apophis

24
Navigation Camera
Mitigation, Payload, Telecom, and Instruments
  • The camera will serve as an imaging camera to
    collect science data
  • The data will include high-resolution color
    images of the asteroid
  • The nav camera will provide images taken through
    different filters
  • These images will provide information on gas
    composition, gas and dust dynamics, and jet
    phenomena, if they exist.

25
Mitigation, Payload, Telecom, and Instruments
  • Laser Range Finder (LRF)
  • The laser range finder will be used to measure
    the distance between the spacecraft and Apophis
    surface. It is also possible to use Doppler
    effect techniques to measure the relative
    velocity between the spacecraft and Apophis.
  • In order to make a stereoscopic
  • measurement of the asteroid surface
  • to determine whether it's rigid or rubble
  • pile, two LRFs will be used.

26
Laser Range Finder
Mitigation, Payload, Telecom, and Instruments
  • A conceptual design of the laser range finder is
    shown. It consists of
  • A solid-state laser transmitter with optical
    diverger
  • A reflective telescope that functions as an
    optical receiver
  • An Analog/Digital conversion unit and digital
    processing unit

27
ggies gainst pophis
A
A
A
  • System Design Review
  • Trajectory, Propulsion, and ACS
  • December 9, 2008

28
Requirements and Assumptions
Trajectory, Propulsion, and ACS
  • Trajectory
  • Launch to Earth escape
  • Transfer orbit for rendezvous with Apophis
  • Maintain tractor position at Apophis
  • Propulsion
  • Use chemical rocket for launch/transfer to
    Apophis
  • Use electric engine for mitigation
    station-keeping
  • Attitude Control System (ACS)
  • Maintain desired orbital position and orientation
    relative to Apophis

28
AAA System Design Review
December 9, 2008
29
Lambert Problem Setup
Trajectory, Propulsion, and ACS
Source Dr. John Junkins
30
Solution to Lambert Problem
Trajectory, Propulsion, and ACS
Depart Feb 19, 2022 Time of Flight 144 days
Minimum ?v Solution (4.276 km/s)
30
AAA System Design Review
December 9, 2008
31
Launch Window
Trajectory, Propulsion, and ACS
Departure Date February 19, 2022 (/- 25
days) Time of Flight 144 Days
32
Launch Vehicle
Trajectory, Propulsion, and ACS
  • The launch vehicle will be an expendable launch
    vehicle from the Atlas V class
  • The Atlas V 401 is a 2 stage rocket capable of
    launching up to 2400 kg to Earth escape.
  • Notable payloads to Earth escape
  • Mars Reconnaissance Orbiter
  • New Horizons

33
Transfer Orbit
Trajectory, Propulsion, and ACS
  • Assume an Isp329 sec
  • In order to arrive at Apophis with a 500 kg
    spacecraft, 1381 kg of chemical fuel is required
  • Mass at launch (to Earth escape) is 1881 kg

33
AAA System Design Review
December 9, 2008
34
Engine Selection
Trajectory, Propulsion, and ACS
  • Aerojet 445
  • Chemical Rocket used for transfer to Apophis and
    rendezvous
  • Busek BHT-200 (x2)
  • Electric Engine used to perform gravity tractor
    operation
  • Each engine is installed at a 38º canting angle
    to avoid exhaust impingement on Apophis

35
Aerojet 445 Hi-PAT Specifications
Trajectory, Propulsion, and ACS
  • Specific Impulse 329 s
  • Thrust/Steady State 445 N
  • Mass 5.44 kg
  • Propellant Type Hydrazine/NTO
  • Propellant Mass 1381 kg
  • Flow Rate 141 g/s
  • Currently in use

36
Busek BHT-200 Specifications
Trajectory, Propulsion, and ACS
  • Input Power 50W-300W, 200Wnominal
  • Voltage 250V
  • Current 800 mA
  • Propellant Flowrate 0.94 mg/sec
  • Xenon Propellant Mass 250 kg
  • Thrust 4-17 mN, 12 mNnominal
  • Specific Impulse 1390 sec
  • Efficiency 43.5
  • Successfully used by the TacSat-2 experimental
    satellite launched on December 16, 2006

Source http//www.busek.com/index.html
37
Attitude Determination
Trajectory, Propulsion, and ACS
  • 2 Star Trackers
  • For improved accuracy and redundancy
  • 8 Sun Sensors
  • Adcole coarse 1-axis
  • 1 Inertial Measurement Unit
  • Northrop Grumman LN-200

37
AAA System Design Review
December 9, 2008
38
Attitude Control and Manuevering
Trajectory, Propulsion, and ACS
  • 4 Reaction Wheels
  • Teldix RSI 02 0.2-1.6 Nms momentum capacity
  • For stability and slewing
  • Pyramid formation
  • Hydrazine Thrusters
  • 8 MR-103C 1 N (0.2-lbf) by Aerojet
  • Pointing and momentum dumping
  • 4 MR-106E 22 N (5-lbf) by Aerojet
  • Thrust vector control

39
ggies gainst pophis
A
A
A
  • System Design Review
  • Structure, Thermal, and Power
  • December 9, 2008

40
Design Requirements
Structure, Thermal, and Power
  • Structures
  • Structure should withstand launch loads,
    frequencies, and pressures
  • Satellite bus should provide support for all
    instruments
  • Thermal
  • Maintain all instruments and components within
    survivable temperatures
  • Power
  • Provide enough power to operate necessary systems
    through all phases of the mission

41
Design Assumptions
Structure, Thermal, and Power
  • Spacecraft mass at Apophis 500 kg
  • Optimal angle of Hall thrusters 38
  • Assume worst case hot and cold are at periapse
    and apoapse of Apophis orbit, respectively
  • Spacecraft modeled as a conductive sphere for
    thermal analysis

42
Conceptual Bus Design
Structure, Thermal, and Power
  • Utilize body mounted solar arrays
  • All fuel tanks and components housed internally
    for thermal control
  • Material of main structure 6061T6 Al

43
Thermal
Structure, Thermal, and Power
Approximate spacecraft as a sphere of equivalent
surface area.
Model does not identify hot/cold spots Internal
satellite configuration currently unknown
44
Thermal
Structure, Thermal, and Power
45
Power Requirements
Structure, Thermal, and Power
  • Provide enough power and storage to operate the
    spacecraft in all modes throughout the mission
  • Provide power switching and power regulation
  • Redundancy as necessary
  • Solar array is primary power source

46
Power Assumptions
Structure, Thermal, and Power
  • Battery Assumptions
  • Rechargeable batteries will be used for secondary
    power
  • Battery will provide high A-h per unit mass
  • Bus voltage of at least 28 Volts
  • Array Assumptions
  • Array is large enough to charge the batteries
    while supplying power to spacecraft
  • Array must provide 1100 Watts

47
UTJ GaAs Solar Array
Structure, Thermal, and Power
  • Array Rationale
  • Gallium Arsenide has a high absorptivity
  • Requires few microns of thickness to absorb
    sunlight
  • GaAs cells are relatively insensitive to heat
  • Gallium arsenide is very resistant to radiation
    damage

48
Lithium Ion Battery
Structure, Thermal, and Power
  • Battery Rationale
  • Li-ion batteries are lighter than other
    equivalent batteries
  • They have a higher energy density than most
    batteries
  • They operate at higher voltages compared to most
    batteries
  • They have a lower self discharge rate (Retain
    charge for long time)

49
ggies gainst pophis
A
A
A
  • System Design Review
  • Budget and Scheduling
  • December 9, 2008

50
Timeline
Budget and Scheduling
2010 Finalize preliminary design
2022 Rendezvous complete. Begin mitigation
2011 Begin prelim. testing analysis
2027 Mission Ends
2022 LAUNCH
2012 Begin major testing analysis


2018 Make adjustments, Continue testing
2015 Prototypes assembled for testing
Albedo Mitigation Study
AAA System Design Review
51
Work Breakdown Example
Budget and Scheduling
from Space Mission Analysis Design
52
Key Funding Assumptions
Budget and Scheduling
  • For the purposes of this study, it should be
    assumed that the total funding available for
    development of a 2022 Apophis deflection mission
    will be
  • Between 100-200 million dollars
  • Excluding Launch vehicle, mission operations
    system, technology development, flight validation
    demonstrations, mission operations

53
Cost Estimation Method
Budget and Scheduling
  • Parametric Estimating- Use math relations between
    design parameters and cost that are compiled from
    statistics of previous programs. These relations
    are called CERs (Cost Estimating
    Relationships).
  • CERs only applicable to the range of historical
    data
  • Parametric estimating unsatisfactory for items
    involving major technological advancements or
    fundamental paradigm shifts. The current mission
    does not fall into this category so this
    estimation method is sufficient.

Space Mission Analysis Design
54
Terms
Budget and Scheduling
from Space Mission Analysis Design
55
Breakdown of Small Satellite Costs
Budget and Scheduling
from Space Mission Analysis Design
43 contingency , then multiply by factor of 3
56
Comm CDH Subsystems
Budget and Scheduling
57
Sensors and Telecom
Budget and Scheduling
58
ACS Subsystem
Budget and Scheduling
59
Structures and Mechanisms
Budget and Scheduling
60
Thermal Management Subsystem
Budget and Scheduling
61
Power Subsystem
Budget and Scheduling
62
Propulsion Subsystem
Budget and Scheduling
63
Educational Outreach
Budget and Scheduling
  • Target audience
  • Educational institutions
  • Classroom presentations
  • Introduce students to
  • space technology
  • Design competition
  • Opportunities for students to do research
  • Development of creative solutions for the mission
  • Opportunities for interested parties to
    participate in modification of albedo studies

64
Trajectory, Propulsion
Structures, Thermal, Power
  • Launch Window 1/28/22-3/16/22
  • Flight Time 144 Days
  • Total Delta V 4.28 km/s
  • Launch Vehicle Atlas V class
  • BUSEK BHT 200 4-17 mN
  • Chemical transfer, EP for mitigation
  • Dry Mass 250 kg
  • Primary Material 6061-T6 Al
  • Worst Case Hot 61 C
  • Worst Case Cold -25 C
  • Array GaAs to supply 1100 Watts, 4.8 m2
  • Batteries Saft Li-Ion

Mitigation, Payload, Telecom
Budget and Scheduling
  • Gravity Tractor Duration 4 Years (total)
  • Standoff 385 m
  • Albedo treatment experiment
  • Overall Budget 100-200 million
  • Initial Projected Cost - 80.2 million
  • Preliminary Design Complete 2010
  • Testing and Analysis 2010-2018
  • Launch 2022

AAA System Design Review
Write a Comment
User Comments (0)
About PowerShow.com