DEVRY BSOP 209 Week 3 Homework Assignment - PowerPoint PPT Presentation

About This Presentation
Title:

DEVRY BSOP 209 Week 3 Homework Assignment

Description:

DEVRY BSOP 209 Week 3 Homework Assignment Check this A+ tutorial guideline at For more classes visit – PowerPoint PPT presentation

Number of Views:3

less

Transcript and Presenter's Notes

Title: DEVRY BSOP 209 Week 3 Homework Assignment


1
DEVRY BSOP 209 Week 3 Homework Assignment
  • Check this A tutorial guideline at
  •  
  • http//www.assignmentcloud.com/bsop-209/bsop-209-w
    eek-3-homework-assignment
  •  
  • For more classes visit
  • http//www.assignmentcloud.com
  •  
  • S7.17
  • Markland Manufacturing intends to increase
    capacity by overcoming a bottleneck operation by
    adding new equipment. Two vendors have presented
    proposals. The fixed costs for proposal A are
    50,000, and for proposal B, 70,000. The
    variable cost for A is 12.00, and for B, 10.00.
    The revenue generated by each unit is 20.00.
  • a)    What is the break-even point in units for
    proposal A?
  • b) What is the break-even point in units for
    proposal B?
  • S7.18