Flat Space Frame Structure - PowerPoint PPT Presentation

About This Presentation
Title:

Flat Space Frame Structure

Description:

The capital airport hangar can hold four Boeing 747 large passenger planes for maintenance at the same time. Due to the special function of the hangar and the special requirements for space, the layout adopts the layout of the large space on one side and the auxiliary room on the other side of the hangar, so that the large space of the hangar is made up. – PowerPoint PPT presentation

Number of Views:12
Slides: 21
Provided by: LFBJMB
Category:
Tags:

less

Transcript and Presenter's Notes

Title: Flat Space Frame Structure


1
Analysis Of Engineering Examples Of Flat Space
Frame Structure
  • Capital Airport A380 Hangar

2
Overview
  • The A380 hangar is located on the north side of
    Terminal 3 of the Capital Airport. The total
    construction area of the project is 64,000 m2,
    with 3 floors above ground and 1 underground
    floor. 176.3m, depth 110m, roof elevation
    39.800m. After completion, it can accommodate 4
    A380 Airbuses or 2 A380 and 4 B747 large
    passenger aircrafts at the same time. It is
    currently the world's largest aircraft
    maintenance warehouse. The roof structure is a
    three-layer welded spherical steel space frame
    with a total area of 39,000 m2 and a total mass
    of about 7,000 tons. It adopts a construction
    plan of ground assembly and an overall lifting in
    place, and its one-time lifting area and weight
    can be called the world's largest . The overall
    improvement of the roof structure in the
    construction of the hangar is undoubtedly the
    biggest technical difficulty.

3
Floor plan
The capital airport hangar can hold four Boeing
747 large passenger planes for maintenance at the
same time. Due to the special function of the
hangar and the special requirements for space,
the layout adopts the layout of the large space
on one side and the auxiliary room on the other
side of the hangar, so that the large space of
the hangar is made up.
4
Internal space
The main space inside the hangar is a large space
for airplanes to dock, and its height and span
are larger than those of ordinary buildings, and
it is required that there are no obstacles such
as pillar nets inside.
5
Facade modeling
The overall shape of the hangar is square, and
the facade is made of transparent glass. With
structural features, the whole building appears
light and simple.
6
Structural analysis
  • The roof structure design is the key to the
    design of a large-span hangar. The formulation of
    the plan must meet the following requirements
    According to the height of the airport airspace,
    the highest point of the hangar roof should not
    exceed 40m the layout and size of the roof
    structure should meet the technical use and
    setting The requirements of the suspension crane,
    the deformation of the roof structure does not
    affect the normal operation of the suspension
    crane and the hangar gate the hangar can meet
    the seismic fortification requirements of an 8
    degree earthquake at the same time, it is also
    necessary to consider the reasonable and reliable
    roof structure production, transportation, and
    hoisting. Speed up the construction cycle.
    According to the above principles, after
    comparing various schemes, a spatial structure
    system combining multi-layer quadrangular pyramid
    space frame and bolt-welded steel bridge was
    selected.

7
(No Transcript)
8
Structural plan and elevation
The structure plan and elevation of the hangar
are shown in the figure. The space frame side
beams at the gate of the hangar are designed as a
box-shaped space truss with two-span continuous
steel beams with a width of 9.5m and a height of
11.5m.
Structure plan
Structural elevation
9
(No Transcript)
10
Engineering difficulties
  • 1. The steel structure has a large span and area,
    which is the largest at home and abroad the
    steel structure of this project has a span of
    352.60m, a depth of 114.5m, and a roof elevation
    of 39.800m. The roof structure adopts
    three-layer obliquely placed quadrangular pyramid
    steel space frame frame, supported by the lower
    chord, and the roof of the hangar gate adopts a
    welded box-shaped steel truss, with a width of
    9.5m and a height of 11.5m. For the construction
    of such a large-span structure, there is no
    domestic precedent and mature construction
    experience that can be used for reference. The
    scientific construction plan is selected to
    ensure the quality of the project, ensure the
    safety of the structure itself and the
    construction safety, effectively control the
    construction progress, and reasonably reduce the
    construction cost. The top priority of this
    project and similar projects must be in-depth and
    detailed research.

11
Engineering difficulties
  • 2. High quality requirements for structural
    assembly The steel structure of this project
    adopts a three-layer obliquely placed
    quadrangular pyramid steel space frame structure
    combined with a steel truss, with a span of
    352.60m, a depth of 114.5m, and a complex
    structure. The measurement of the plane control
    network during construction The accuracy
    requirements are very high how to take the
    correct assembly method, assembly accuracy
    control measures according to the characteristics
    of the structure itself, and how to ensure the
    final closure of the overall structure after
    assembly requires careful study. In addition, the
    project has a huge number of components and
    various on-site node forms. How to combine
    structural span, depth, height and structural
    form characteristics, take effective welding
    process and welding quality control measures to
    ensure welding quality and overall structural
    assembly quality is the difficulty of this
    project .

12
Engineering difficulties
  • 3. Heavy tasks and tight schedule
  • The total construction period for the four seats
    of the Capital Airport is three years. In order
    to meet the needs of putting into use before the
    Olympic Games, this project shortened the
    conventional 36-month construction period to 20
    months.

13
Selection of construction plan
  • The existing construction schemes include
    high-altitude bulk assembly, segmented hoisting
    and overall lifting, but considering their
    respective advantages and disadvantages, manpower
    and material resources, safety management and
    other conditions, the overall lifting
    construction technology was finally selected. The
    advantage is that a large amount of work can be
    completed on the ground, reducing the amount of
    tooling scaffolding, avoiding high-altitude
    operations, and reducing the difficulty of
    project safety management. Due to the large site
    area, multi-point and multi-face flow operations
    can be formed, which speeds up the progress of
    ground assembly and facilitates the control of
    engineering installation accuracy.

14
Overall promotion technology
  • In order to meet the boundary conditions of the
    structural design to the greatest extent and
    ensure the quality of the project speed up the
    progress of the project construction and create
    conditions for the follow-up work reduce the
    cost of the project and ensure the safety of the
    construction. For this project, a one-time
    overall lifting construction technique is
    adopted. The one-time overall lifting structure
    has the following advantages the weight of the
    lifting structure can reach more than 10,000
    tons the size, area and volume of the lifting
    structure are large computer control, high
    degree of automation reducing the amount of
    high-altitude work, the construction is safe,
    reliable, and lower Construction risk shorten
    the construction period and reduce the
    construction cost. Based on the above analysis,
    we decided to adopt the scheme of simultaneous
    lifting of the net frame and the truss.

15
Multi-point and multi-face ground assembly work
at the construction site
16
Improve the assembled spaceframe at one time
17
(No Transcript)
18
(No Transcript)
19
(No Transcript)
20
Summarize
  • Large span and high height have become the key to
    the structure design of the hangar
  • Select the space structure system combining
    multi-layer quadrangular pyramid space frame
    frame and bolt-welded steel bridge
  • Capital Airport A380 hangar uses one-time overall
    lifting technology to assemble the flat space
    frame structure
  • The shape is simple and light
Write a Comment
User Comments (0)
About PowerShow.com