Title: Flat Space Frame Structure
1Analysis Of Engineering Examples Of Flat Space
Frame Structure
- Capital Airport A380 Hangar
2Overview
- The A380 hangar is located on the north side of
Terminal 3 of the Capital Airport. The total
construction area of the project is 64,000 m2,
with 3 floors above ground and 1 underground
floor. 176.3m, depth 110m, roof elevation
39.800m. After completion, it can accommodate 4
A380 Airbuses or 2 A380 and 4 B747 large
passenger aircrafts at the same time. It is
currently the world's largest aircraft
maintenance warehouse. The roof structure is a
three-layer welded spherical steel space frame
with a total area of 39,000 m2 and a total mass
of about 7,000 tons. It adopts a construction
plan of ground assembly and an overall lifting in
place, and its one-time lifting area and weight
can be called the world's largest . The overall
improvement of the roof structure in the
construction of the hangar is undoubtedly the
biggest technical difficulty.
3Floor plan
The capital airport hangar can hold four Boeing
747 large passenger planes for maintenance at the
same time. Due to the special function of the
hangar and the special requirements for space,
the layout adopts the layout of the large space
on one side and the auxiliary room on the other
side of the hangar, so that the large space of
the hangar is made up.
4Internal space
The main space inside the hangar is a large space
for airplanes to dock, and its height and span
are larger than those of ordinary buildings, and
it is required that there are no obstacles such
as pillar nets inside.
5Facade modeling
The overall shape of the hangar is square, and
the facade is made of transparent glass. With
structural features, the whole building appears
light and simple.
6Structural analysis
- The roof structure design is the key to the
design of a large-span hangar. The formulation of
the plan must meet the following requirements
According to the height of the airport airspace,
the highest point of the hangar roof should not
exceed 40m the layout and size of the roof
structure should meet the technical use and
setting The requirements of the suspension crane,
the deformation of the roof structure does not
affect the normal operation of the suspension
crane and the hangar gate the hangar can meet
the seismic fortification requirements of an 8
degree earthquake at the same time, it is also
necessary to consider the reasonable and reliable
roof structure production, transportation, and
hoisting. Speed up the construction cycle.
According to the above principles, after
comparing various schemes, a spatial structure
system combining multi-layer quadrangular pyramid
space frame and bolt-welded steel bridge was
selected.
7(No Transcript)
8Structural plan and elevation
The structure plan and elevation of the hangar
are shown in the figure. The space frame side
beams at the gate of the hangar are designed as a
box-shaped space truss with two-span continuous
steel beams with a width of 9.5m and a height of
11.5m.
Structure plan
Structural elevation
9(No Transcript)
10Engineering difficulties
- 1. The steel structure has a large span and area,
which is the largest at home and abroad the
steel structure of this project has a span of
352.60m, a depth of 114.5m, and a roof elevation
of 39.800m. The roof structure adopts
three-layer obliquely placed quadrangular pyramid
steel space frame frame, supported by the lower
chord, and the roof of the hangar gate adopts a
welded box-shaped steel truss, with a width of
9.5m and a height of 11.5m. For the construction
of such a large-span structure, there is no
domestic precedent and mature construction
experience that can be used for reference. The
scientific construction plan is selected to
ensure the quality of the project, ensure the
safety of the structure itself and the
construction safety, effectively control the
construction progress, and reasonably reduce the
construction cost. The top priority of this
project and similar projects must be in-depth and
detailed research.
11Engineering difficulties
- 2. High quality requirements for structural
assembly The steel structure of this project
adopts a three-layer obliquely placed
quadrangular pyramid steel space frame structure
combined with a steel truss, with a span of
352.60m, a depth of 114.5m, and a complex
structure. The measurement of the plane control
network during construction The accuracy
requirements are very high how to take the
correct assembly method, assembly accuracy
control measures according to the characteristics
of the structure itself, and how to ensure the
final closure of the overall structure after
assembly requires careful study. In addition, the
project has a huge number of components and
various on-site node forms. How to combine
structural span, depth, height and structural
form characteristics, take effective welding
process and welding quality control measures to
ensure welding quality and overall structural
assembly quality is the difficulty of this
project .
12Engineering difficulties
- 3. Heavy tasks and tight schedule
- The total construction period for the four seats
of the Capital Airport is three years. In order
to meet the needs of putting into use before the
Olympic Games, this project shortened the
conventional 36-month construction period to 20
months.
13Selection of construction plan
- The existing construction schemes include
high-altitude bulk assembly, segmented hoisting
and overall lifting, but considering their
respective advantages and disadvantages, manpower
and material resources, safety management and
other conditions, the overall lifting
construction technology was finally selected. The
advantage is that a large amount of work can be
completed on the ground, reducing the amount of
tooling scaffolding, avoiding high-altitude
operations, and reducing the difficulty of
project safety management. Due to the large site
area, multi-point and multi-face flow operations
can be formed, which speeds up the progress of
ground assembly and facilitates the control of
engineering installation accuracy.
14Overall promotion technology
- In order to meet the boundary conditions of the
structural design to the greatest extent and
ensure the quality of the project speed up the
progress of the project construction and create
conditions for the follow-up work reduce the
cost of the project and ensure the safety of the
construction. For this project, a one-time
overall lifting construction technique is
adopted. The one-time overall lifting structure
has the following advantages the weight of the
lifting structure can reach more than 10,000
tons the size, area and volume of the lifting
structure are large computer control, high
degree of automation reducing the amount of
high-altitude work, the construction is safe,
reliable, and lower Construction risk shorten
the construction period and reduce the
construction cost. Based on the above analysis,
we decided to adopt the scheme of simultaneous
lifting of the net frame and the truss.
15Multi-point and multi-face ground assembly work
at the construction site
16Improve the assembled spaceframe at one time
17(No Transcript)
18(No Transcript)
19(No Transcript)
20Summarize
- Large span and high height have become the key to
the structure design of the hangar - Select the space structure system combining
multi-layer quadrangular pyramid space frame
frame and bolt-welded steel bridge - Capital Airport A380 hangar uses one-time overall
lifting technology to assemble the flat space
frame structure - The shape is simple and light