EMCAL report to Temple - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

EMCAL report to Temple

Description:

Intro definition of 'staged' Project flow. Critical path and schedule ... 7 HV's provided separately (no local voltage divider) daisy chaining 100 of them. ... – PowerPoint PPT presentation

Number of Views:29
Avg rating:3.0/5.0
Slides: 18
Provided by: yuichi5
Category:
Tags: emcal | chain | daisy | report | temple

less

Transcript and Presenter's Notes

Title: EMCAL report to Temple


1
EMCAL report to Temple
  • Y. Kubota
  • 5/27/04

2
Outline
  • Intro definition of staged
  • Project flow
  • Critical path and schedule
  • Staged 50 EMCAL will be ready to be installed
    229 days before it needs to be ready for 2009
    summer shutdown installation.
  • Labor, cost profiles
  • Installation
  • Needs 270 man-years of labor in each of the two
    installation shutdown periods.
  • CD-1 recommendations and responses
  • Risk management
  • and of CMS interference cancel and has little
    effects on our bottom line.

3
Intro
  • 10,100 PWO crystals of 28?28?220 mm3
  • Tyvek wrapped
  • PMT 5-7 stages, gain 3000, requiring 7 HVs
    provided separately (no local voltage divider)
    daisy chaining 100 of them.
  • Signal cable to FEB 2-4m
  • Support structure has cells for individual
    crystals.
  • Light pulser/optical fibers to test system and
    calibrate crystals.

4
Staged
  • 1st stage has half as many crystals (5000)
  • Typical efficiency (compared to the full
    detector) is 60.
  • Fill a range of radii from 40 to 120 cm.
  • Inside of 40 cm is not as useful as this area
    because the background near the beam pipe. Low
    Pt tracks are often rejected in analyses.
  • Outside 120 cm, the rate of photons in this area
    is lower.
  • More crystals will be installed as long as their
    delivery is on schedule.

5
Project Flow
6
Default schedule
229 days float
7
Critical Paths Schedule floats
8
Labor Profile
FY06
FY07
FY09
FY08
FY05
9
Cost
  • Total 12.6M base - 16.8M w/ contingency (33.6)
  • MS 10M base
  • Labor 2M
  • 400k increase from CD-1 (Chinese crystal
    production accelerated)

10
Cost Profile
FY05
FY06
FY07
FY08
FY09
FY08
FY09
FY06
FY07
FY05
11
Change from CD-1
12
OBrowser view of cost
13
Installation in C0
  • Before shutdown 2009
  • Load 5000 crystals (PMTs attached) and test.
  • Shutdown 2009
  • Move the support structure from the Assembly Hall
    to C0.
  • Install light pulsers and front-end electronics
    (FEB) near the detector.
  • Connect optical fibers, signal cables and HV
    cables.
  • Connect FEBs to DAQ.
  • Shutdown 2010
  • Load crystals (PMTs attached) and test.
  • Connect optical fibers, signal cables and HV
    cables.

14
Installation labor
  • Before 2009 shutdown
  • 200 man-days
  • 200 man-days of physicists to install crystals
  • 2009 shutdown 4 months
  • 270 man-days
  • 70 man-days physicists
  • 80 man-days technicians
  • 25 man-days ME
  • 63 man-days EE
  • 2010 shutdown 3 months
  • 275 man-days
  • 200 man-days Physicists
  • 75 man-days technicians

15
CD-1 recommendations
  • Explore ways to arrive at a schedule with
    comfortable float (gt6 months) by working with
    BTeV Management and Installation Integration
    group.
  • Staged installation of EMCAL is our answer to
    this recommendation. We now have a minimum of
    191 business days ( 9 months) of floats.
  • Add an Installation Engineer to the project.
  • More engineering is being added as a shared
    resource to the Project Office.
  • Add US collaborators
  • Yes, we are trying.

16
Risk - mitigation
  • Acquisition of crystals with only a few
    manufacturers can be risky.
  • CMS narrowed the vendor field to one fairly early
    in their process.
  • We plan to keep at least two vendors in the race.

17
If CMS is in our way