Title: PAST
1PAST
PRESENT
FUTURE
2byFady P. Bassily General Manager
Presentation for
- 36th E.C.C.E. Meeting
- 13 September 2002
3POPULATION GROWTH CAR USE
Population evolution in Attica region 1961 2.1
million 1996 4.1 million (100) Private
Car Ownership 1961 39,000 units 1996
1,200,000 units (3,000 ) Daily
transportation 1996 7,000,000 trips/day
Evolution of trips by mode (Public vs
Private) 1973 65 vs 35 1996 42 vs 58
4PAST
5(No Transcript)
6PRESENT
7BASE PROJECT
Tunnel length 17 Km (Sepolia -
Dafni Syntagma-E. Amyna) 1 Km under
construction Stations 19 in operation 1
under construction Depot 120.000
sq.m. Rolling Stock 28 trains
8 FUNDING
2,047 BILLION EURO Cost of Base Project or (697
BILLION GDR at Historical prices) 50 - EUROPEAN
UNION - Grants 50 - GREEK STATE 40
EUROPEAN INVEST. BANK - LOANS 10 STATEs
BUDGET
9KIFISSIA
METRO BASE PROJECT
Line 1 - ISAP
Line 2 ATTIKO METRO
Line 3 ATTIKO METRO
OMONIA
PIREAS
10ARCHAEOLOGICAL EXCAVATIONS
Joint Effort Attiko Metro, Olympic Metro,
Ministry of Culture The biggest Excavation
Project ever in Athens - 70,000 sq.m. of
archaeological investigations - 30 centuries
antiquities found All periods of the city of
Athens history From Neolithic period up to
Modern era Project additional Cost Delay -
75 mil Euro - 2 years
11TUNNEL CONSTRUCTION METHODS
1. Tunnel Boring Machines (TBM) for rocky
ground 2. Open Face Shield (TBM) for softer
ground 3. Micro Tunnel Boring Machine (MTBM)
to support the crown of big vaults 4. New
Austrian Tunneling Method (NATM) in difficult
ground conditions 5. Cut Cover Method for
shallow tunnels
12BASE PROJECT IN NUMBERS
Excavations 2.600.000 c.m. Arch. Excavation
69.000 sq.m. Reinforced concrete 710.000
c.m. Waterproofing Membrane 220.000
sq.m. Steel 62.500 ton. Marbles
20.500 sq.m. Granites 46.500
sq.m. Ceramic Tiles 27.000 sq.m.
13CONNECTING STATIONS
CONNECTIONS Between Lines 1 2 2
stations Between Lines 2 3 1 station To
the National Railway Trains 1
station FACILITIES Bus/trolley transfer
facilities and Park Ride facilities 3
stations Ticket Issuing machines ticket
sellers All stations
14THE STATION FEATURES
Architectural finishing (granite floor,
marble walls) Ticket Issuing machines ticket
sellers (all stations) Fully accessible to
person with special needs 150
escalators 70 elevators Security
Control equipment (closed circuit television,
fire protection, emergency lighting)
Pumping System 102
pumps Ventilation 237 fans
15THE ROLLING STOCK
- 6-car Train sets (with ATP system) 28
-
- Vehicles 168
- Passenger Capacity / Train 1030
- Train Length 106m
- Max Speed (km/h) 80
- Service Locomotives 4
16OPERATION
17SERVICE FACTS FIGURES
Service hours 530 - 2400 Headway 3 min
(peak hours) 5-10 min Max System
Capacity 64,000/hour Daily Passengers 472,000
18OPERATIONAL STANDRARDS
- High standard of passenger's environment
- Zero tolerance for
- Graffiti
- Smoking
- Drinking
- Eating
- Begging
- Solicitation
19OPERATIONAL STANDARDSSecurity
- High level of Security personnel
- Police guards
- Co-ordination by Operation Control Center
- (OCC) in a 24-hour basis
- Over 200 TV cameras
- CCTV monitors (OCC and Station
- Masters rooms)
20ANNUAL RESULTS
85 million trips (1st year of operation) 120
million trips (2nd year of operation) 170
million trips for 2002 (estimation) Tickets vs
Card use 60/40 Customer Satisfaction 97
Service interruptions due to technical
problems minimal Crime zero Operating
cost recovery ratio 108 (with out loan payment
or depreciation allowance)
21OPERATION FINANCIAL DATA
During the second year of Metro operation, the
Metro covered 100 of its operational expenses
(the capital cost excluded) exclusively from
revenues without subsidy. Given that revenue
sources are expected to be added in the immediate
future (such as advertisement), it is anticipated
that the operational revenue will far exceed the
operating costs. As far as the Metro expenses is
concerned, it has to be stressed that its
operation is cost-effective, despite the high
quality of the services it provides (cleanliness,
safety, reliability), whose cost is high. The
structure of the Metro expenses is of particular
interest 46 of the expenses refer to labour
cost (including subcontracting works) and 11
refer to the energy cost.
22EXPENSES CATEGORIES
23BENEFITS
Safety The ATTIKO METRO operation and control
systems ensure maximum safety during
transportation. Speed The Metro reduces travel
time in the city by more that 50 in comparison
to the use of cars, thus ensuring more leisure
time and increased productivity in the life of
citizens. Reliability Metro ensures better
scheduling, flexibility and accuracy in our daily
trips due to the punctuality of train
itineraries, every 3 during peak hours and every
5-10 during the rest of the day. Travel Comfort
Cleanliness ATTIKO METRO ensures easy travel in
the stations through escalators, lifts and a
complete information signs system. Assistance and
services are provided by specialized personnel.
The Metro ensures a well-maintained, complete in
terms of aesthetics and clean environment.
24A PROJECT CONTRIBUTING TO CULTURE
- The Art Program of ATTIKO METRO
- Reveals Ancient Greek Civilization
- The exhibition of the archaeological findings
which came to light through tunneling works,
creates cultural oases in ATTIKO METRO stations. - Presents Modern Greek Art
- The ATTIKO METRO stations accommodate works of
well-known Greek artists - 16 Modern Artwork Exhibits in 11 stations
- Adds to the Project a unique IDENTITY, QUALITY
and AESTHETICS.
25ARCHAEOLOGICAL DISPLAYS
Mini exhibitions in selected stations Most
significant artifacts found exhibited
in Syntagma station Akropolis station Evangelismo
s station Panepistimio station Dafni station
26ARCHAEOLOGICAL DISPLAYS
27ARCHAEOLOGICAL DISPLAYS
28FUTURE
29SYNTAGMA - MONASTIRAKI
30Syntagma - Monastiraki
31CONSTRUCTION OF Syntagma - Monastiraki
- 1,4 km. of tunnel (single, double and triple
track) using the ???? method for Syntagma
Monastiraki Assomaton Thission section. - 1 station MONASTIRAKI, Center Platform 146m.
long to accommodate 8-car trains serving also as
a terminal station. - 4 shafts
- - Fokionos
- - Assomaton
- - Thission
- - Ermou-Arionos
32CHALLENGES HANDLED
- the change in the alignment, under Ermou
instead of Mitropoloeos Street (including
changing of the tunnel construction method) - the
change of the tunnel construction method (NATM
instead of Tunnel Boring Machine) - the
additional measures for the protection of the
Athens Cathedral - the adverse ground conditions
- the extensive archaeological excavations, as
well as - the complete diversion of Keramikos
Archaeological Site
33MONASTIRAKI STATIONStatus
- The works related to the architectural finishes
and the electromechanical installations of the
station have been commenced. - The works related to the installation of tracks
at the tunnel have been completed. The
installation of the E/M equipment in the tunnel
is in progress. - The archaeological excavations have been
completed. - Based on the time schedule, the station will be
in operation on January 2003.
34MONASTIRAKI STATION
35FUNDINGExtensions 2002 - 2006
- 1.643 Million Four extensions
- 138 Million Transfer stations
- 1.781 Million
- 585 Million - EUROPEAN UNION - GRANTS
- 1058 Million
- - GREEK STATE
- - EUROPEAN INVESTMENT BANK - LOANS
- - STATE BUDGET
- 138 Million - Private Participation for
Transfer Stations
36Sepolia Thivon Extension
37SEPOLIA - THIVON EXTENSION
- 2,8 Km of tunnel (OFS NATM)
- 2 stations 1. Agios Antonios under
construction - 2. Thivon under design
- Operation Agios Antonios (June 2004)
- Thivon (December 2005)
- 5 shafts
- Budget 218 million
38SEPOLIA THIVONStatus
- TUNNEL
- The following tunnel excavations (830 meters)
have been completed - - the single track tunnel with Sepolia Depot
- - the double track tunnel under Kifissos
- - the triple track tunnel next to Oikonomidou
Shaft - The construction of Fleming, Ravine and
Papandreou shafts is in advance stage of
progress. - Open Face Shield (OFS) Boring of Tunnel
250 meters - AGIOS ANTONIOS STATION
- The works for the diversion of the public utility
networks and the archaeological investigation
have been completed. - The pilling works (installation of 440 piles)
have been completed. - The excavation works are in progress at the main
section of the station.
39SEPOLIA - THIVON EXTENSION
40SEPOLIA - THIVON EXTENSION
41SEPOLIA - THIVON EXTENSION
42SEPOLIA - THIVON EXTENSION
43Ethniki Amyna D. Plakentias - Airport Extension
44ETHNIKI AMYNA D. PLAKENTIAS EXTENSION
- 5,8 Km of tunnel (EPB, NATM, CC)
- 2 stations (Halandri D. Plakentias)
- 8 shafts
- 1 stabling shed and light repair workshop
(60.000m2) - 1st Operation Phase June 2004 (2 stations)
- 2nd Operation Phase December 2005(2
stations - Nomismatokopio, Holargos)
- 2rd Operation Phase June 2006 (1 station
Ag. Paraskevi) - Budget (of phase 1) 554 million
45E. AMYNA D. PLAKENTIASStatus
- CONSTRUCTION OF HALANDRI STATION
- The works related to the piling, excavation and
concreting of the station raft have been
completed (100). - The concreting works of the platforms slab are
about to be completed, while the concreting of
the slab at concourse level is in progress. - CONSTRUCTION OF TUNNEL SHAFTS
- ???? BORING OF TUNNEL 1500 meters
- NATM 700 meters
- The construction of Metamorfosi, Keas,
- Xanthou, Nomismatokopio shafts is at an advance
stage.
46E. AMYNA D. PLAKENTIASStatus
- STAVROS DEPOT
- The contract with THEMELIODOMI was signed on
February 2002. - The excavation works have been completed.
- The concreting works of the perimeter wall and
the floor slab of the substation are at an
advanced stage. - DOUKISSIS PLAKENTIAS STATION
- The station excavation works are completed, while
the concreting works and the works related to the
installation of the waterproofing system by
ATTIKI ODOS JV are in progress. - The works for the excavation and concreting of
the adjacent tunnels are at an advanced stage.
47ETHNIKI AMYNA D. PLAKENTIAS EXTENSION
48ETHNIKI AMYNA D. PLAKENTIAS EXTENSION
49ETHNIKI AMYNA D. PLAKENTIAS EXTENSION
50ETHNIKI AMYNA D. PLAKENTIAS EXTENSION
51 TO THE AIRPORT
52D. PLAKENTIAS - AIRPORT
- 20,7 Km land-line (?S?) between D.
Plakentias-Airport - 1 station at the Airport (??/?S?)
- Operation June 2004
- Special Metro dual voltage trains will be
operating, with the use of the Suburban Railway
tracks, non-stop itineraries from Doukissis
Plakentias Terminal Station to Spata Airport.
53Dafni A. Panagoulis Extension
54DAFNI A. PANAGOULIS EXTENSION
- 1,2 Km of tunnel (CC, NATM)
- 1 station Alexandros Panagoulis (CC)
- 2 shafts (Papagou Bouboulinas)
- Operation June 2004
- Passengers on daily basis 85,000
- Budget 136 million
55DAFNI A. PANAGOULISStatus
- TUNNEL
- The civil work contract for the extension was
signed on January 2002 with AEGEK/METON
companies. - The construction works for the excavation of the
tunnel are in advance progress (420 m.). - STATION
- The works related to the piling, excavation and
concreting of the station raft have been
completed. - Structural works are in progress.
- The piling works (222 piles) were completed,
while the excavation works in the area to be
configured past the station, for train stabling /
commencement of operation, are at an advanced
stage.
56DAFNI A. PANAGOULIS EXTENSION
57DAFNI A. PANAGOULIS EXTENSION
58DAFNI A. PANAGOULIS EXTENSION
59Monastiraki - Egaleo Extension
60MONASTIRAKI-EGALEO EXTENSION
- ?HE PROJECT
- 4,3 km of tunnel (????)
- 3 stations (2 underground excavated-???? and one
with combined excavation method ????/CC) - 7 shafts
- 1 depot and light repair workshop in Agios Savas
area (85.000 m2) - Operation June 2005
- Budget 539 million
61MONASTIRAKI-EGALEO Status
- CIVIL WORKS
- The relevant contract was signed with the
consortium ACTOR-IMPREGILO in December 2001 - Worksite installation have been completed at the
3 stations (Votanikos, Agios Savas Egaleo) of
the extension. - The works for the construction of the access
shafts in two stations and two shafts are in
progress. - The archaeological excavations have been
completed in two fronts. Today, the
archaeological excavations continue at two
locations where the ventilation shafts of the
line will be constructed. - AGIOS SAVAS DEPOT AND INTERCITY FOR TRANSFER
FACILITIES - The tender for the construction of this project
will be completed on October of 2002.
62MONASTIRAKI-EGALEO EXTENSION
63Extensions Under Construction
64NEW ROLLING STOCK
- Supply of 14 new fully automated trains for the
extensions of Lines 2 3 and of 7 trains (dual
voltage) for the airport service - Train configuration 6 cars per train
- Passenger capacity 204 seats, 840 standees in
DC trains - 156 seats, 840 standees in DV trains
- Maximum speed 80 Km/h for DC trains
- 120 Km/h for DV trains
- Contractor HANWHA/ROTEM, Seoul, Korea
- Budget 198 million
65NEW ROLLING STOCK
66METRO PLANNED EXTENSIONS
67Panormou Maroussi Extension
68PANORMOU MAROUSSI EXTENSION
- First priority is the creation of a new
underground branch of Line 3 from Panormou
Station to Paradissos, in the Amaroussio region,
running along Kifissias Avenue. - Line length 7.5 km
- 5 new stations
- 120,000 passengers/day
- A feasibility study is carried out in respect of
a further 1.2km extension with an additional
station in Maroussi, namely at the site where the
ISAP Maroussi Station is found. - Total cost (up to Maroussi) 810,000,000
(including the rolling stock).
69PANORMOU MAROUSSI EXTENSION
- The preparation of the conceptual design is in
progress, expected to be ready by the end of
2002. -
- The investigation into the possibilities of
getting the projects financed by the private
sector is to begin shortly. -
- This is a first priority extension in respect of
the selection of concessionaires for the
implementation of the project. The companys
objective is to get all these procedures
completed by the end of 2004.
70A. Panagoulis - Elliniko Extension
71A. PANAGOULIS - ELLINIKO EXTENSION
- The Line 2 extension from ALEXANDROS PANAGOULIS
Station to the old Elliniko Airport is to be
underground along Vouliagmenis Avenue, except for
a section which is to be a surface section. - 4.2km length
- 4 new stations
- The creation of a depot in the Elliniko region
is under investigation. - 80,000 passengers/day
- Total cost 280,000,000
- For this specific extension, because of its
construction cost, the possibility of its
implementation by means of public funds (as
public work) within the 3rd Community Support
Framework, is being examined.
72Egaleo - Piraeus Extension
73EGALEO - PIRAEUS EXTENSION
- The Line 3 extension from EGALEO Station to the
region of Piraeus port is to be underground. - 8.2km length
- 6 stations
- 130,000 passengers/day
- Total cost 700,000,000
74Panepistimio - Galatsi Extension
75PANEPISTIMIO - GALATSI EXTENSION
- It concerns the creation of a new branch of Line
2 which will be running from Panepistimio Station
to Galatsi area. - 6.3km length
- 6 new stations
- 110,000 passengers/day
- Total cost 730,000,000
76FUTURE EXTENSIONSProgress of Works
- A procurement procedure is about to begin for
the appointment of a consultant to deal with the
designs of the ELLINIKO, GALATSI and PIRAEUS
extensions. - Also, another procurement procedure is to begin
for the appoint of a financial consultant, who,
assisted by the technical and legal consultants,
will look into the possibilities of getting the
extension projects implemented through concession
contracts and funds coming from the private
sector. The scope of the concessionaires will be
the design, construction, funding and running,
possibly maintenance and operation, of these
lines. - The objective of the company is the completion of
the concession procedures for these extension by
the end of 2004.
77Metro Future Extensions
78TRANSFER PARKING STATIONS
79SYNGROU-FIX Transfer Station
- 660 parking spaces
- Facilities for passengers transferring to bus
lines at the street level - Direct underground connections with the Metro
Station - Shops and commercial activities at level 1
- 2.300 sq.m. park area
- The contract for the construction of the transfer
station was signed in April 2002. The preparatory
works for the construction of the transfer
station are in progress. - Operation May 2004
- BUDGET 12.458.000
80SYNGROU-FIX Transfer Station
81HALANDRI D. PLAKENTIASTransfer Stations
- HALANDRI Transfer Station
- 500 parking spaces
- Transfer facilities from buses
- Provision for the development of commercial
activities - next to the station
- Operation June 2004
- Budget 2 million
- D. PLAKENTIAS Transfer Station
- 630 parking spaces
- Transfer facilities from buses
- Operation June 2004
- Budget 2,3 million
82HALANDRITransfer Station
83D. PLAKENTIASTransfer Station