Spring 2006 Quarter Plan Presentation - PowerPoint PPT Presentation

1 / 23
About This Presentation
Title:

Spring 2006 Quarter Plan Presentation

Description:

Run a test collection of sensor data. Structural Development. Scott Maghy ... Finalize the approvals needed to put up a fence and bolt into the wall at Lakeside ... – PowerPoint PPT presentation

Number of Views:24
Avg rating:3.0/5.0
Slides: 24
Provided by: Jayn
Category:

less

Transcript and Presenter's Notes

Title: Spring 2006 Quarter Plan Presentation


1
Spring 2006 Quarter Plan Presentation
  • UCSD TIES
  • Lakeside Environmental Monitoring Team
  • April 25, 2006
  • Team Lead Stephen Bak

2
Agenda
  • Water Quality
  • Hardware Development
  • Structural Development
  • User-Interface
  • Overall Goals

3
Water Quality Monitoring and Assessment
  • Evan Sharbrough (lead)
  • Meng Wei Chou
  • Sam Hwang

4
WQ Quarter Progress
  • New phosphate kit for improved accuracy
  • Established site visit days and field tests.
  • Initialized planning for integrating WQ team in
    user-interface development.
  • Assisted with sensor calibration.
  • Tested at sites 1-5 on April 16th.

5
Whats To Come
  • At least 3 remaining site visits for testing
  • April 29th - Coinciding with prototype field test
  • May 13th
  • May 20th
  • Periodic Testing at HaHana (Site 6) and El
    Capitan Reservoir (Site 8).
  • Contribution to user-interface layout and
    displays.
  • Evaluation of statistical analysis software.

6
Current Issues and Obstacles
  • Preliminary site 6 and 8 evaluation
  • Site 6
  • Generally higher TDS and EC than site 2.
  • Consistently lower temperature
  • Higher than desired levels for other parameters
  • Site 8
  • No definitive link to sites in town yet, but also
    outside of desired ranges for many parameters.
  • Recommendation
  • Continue testing both sites but less frequently
    than original 5 sites.
  • Continue searching for source from San Vicente
    Reservoir?

7
Hardware Development Team
  • Software
  • Tony Aung (lead)
  • Nick True
  • Hardware Testing
  • Daniel Su

8
Progress in Programming
  • Began coding wireless transmission algorithms.
  • Debugging local data storage code.
  • Developed possible design for the wireless
    communication within multiple sensor node
    network.

9
Hardware Testing Accomplishments
  • Sensor calibration
  • EC first calibration
  • DO recalibration with correct method
  • Charge regulator study and testing
  • Tested power consumption characteristics
  • Encountered problem with charge regulator.
  • In contact with Morningstar for solutions

10
Hardware Development Goals
  • Independent execution of code within the
    datalogger
  • Wireless Communications Issues
  • Range testing of modem
  • Complete transmission programming
  • Power system characteristics
  • Battery drain duration.
  • Battery charge time.
  • Rooftop simulations with solar panel
  • Recalibrate remaining sensors

11
User Interface Design Team
  • Jason Najarro

12
Quarter Plan
  • Deliver Working Lakeside Office Interface
  • Start Developing Server Database

13
Office Interface
  • Based on Stephen Frosts interface designs, UI
    team will select important features to include in
    prototype interface
  • Collaborate with Chemical team to program
    interface in LabVIEW 8
  • Present working prototype by end of quarter

14
Lakeside Database
  • Obtain donated copy of SQL Toolkit for LabVIEW
    from National Instruments
  • Begin implementing database on team laptop
  • Database can later be transferred to server once
    it is ready
  • Run a test collection of sensor data

15
Structural Development
  • Scott Maghy (lead)
  • Tim Chow
  • Jeanie Kwok

16
Structural DevelopmentWinter Quarter
Accomplishments
  • Relocated placement of the system along the 2nd
    to 3rd step joint from the Channel Road Bridge
  • Completed finished, detailed models for the
    conduits
  • Initiated the process of approvals with the city
    of Lakeside

17
The Enclosure
  • 0.75 thick reinforced fiberglass walls
  • lockable steel hasp
  • humidity/dust resistant seals
  • brackets for wall mounting
  • Cost 195

Campbell Scientific enclosure model ENC 12/14
with components
18
The Approval Process
  • System needs approval from SD County Land
    Development Section
  • Currently in contact with county workers
  • Approval will include system installation, the
    wall, and the safety fence
  • Approval process about two weeks
  • Submission of approval to SD County within next
    two weeks

19
Important Issues
  • Fence details
  • Placement of the solar panel
  • Who will install the system?

20
Structural Goals
  • Purchase and modify the enclosure
  • Further develop solar panel mount design
  • Finalize the approvals needed to put up a fence
    and bolt into the wall at Lakeside
  • System installation

21
Recap
  • Greater integration of WQ team into design as
    well as continued testing
  • High emphasis on programming and system testing
  • LabVIEW representation of User-Interface
  • Obtain approval and all materials to install
    structural system

22
Overall Goals and Dates
  • Tentative Field Test April 29th
  • Pre-Deployment Field Test Mid-May
  • Deliver a functioning prototype by end of quarter
  • Initial target date Mid-to-late May

23
Questions?
Write a Comment
User Comments (0)
About PowerShow.com