NCHRP Project 1904 A Review of DOT Compliance with GASB 34 Requirements Interim Report - PowerPoint PPT Presentation

1 / 26
About This Presentation
Title:

NCHRP Project 1904 A Review of DOT Compliance with GASB 34 Requirements Interim Report

Description:

Idaho. Depreciation: Bridges, Rest Area Buildings. Modified: Roads. 11 ... 'Historical Cost' was the most commonly used method for calculating the beginning ... – PowerPoint PPT presentation

Number of Views:29
Avg rating:3.0/5.0
Slides: 27
Provided by: karen231
Category:

less

Transcript and Presenter's Notes

Title: NCHRP Project 1904 A Review of DOT Compliance with GASB 34 Requirements Interim Report


1
NCHRP Project 19-04A Review of DOT Compliance
with GASB 34 RequirementsInterim Report
  • Presentation to AASHTO
  • June 9, 2003

2
Consultant Team
  • PBConsult - prime contractor
  • PricewaterhouseCoopers LLP - accounting
  • NuStats survey administration
  • Cambridge Systematics technical review

3
Survey Methodology
  • Review of prior surveys Tennessee DOT, NASACT,
    Georgia DOT
  • Phone interviews with 11 DOTs
  • Draft survey prepared
  • Survey pre-test with Louisiana and Texas
  • Revised survey submitted to NCHRP Panel
  • Further revisions based on Panel comments
  • Revised survey approved by Panel
  • Survey administered by NuStats

4
Survey Conclusions (1)
  • Higher percentage of States selected depreciation
    approach than previously indicated, probably due
    to difficulties in implementing modified approach
  • Underlying consideration in selection of approach
    was potential impact on department funding
  • States selecting depreciation approach had wide
    range of reasons, mostly reasons for not
    selecting modified approach
  • States selecting modified approach cited useful
    information and Department philosophy
  • A majority of states (75-80) believed that the
    GASB 34 exercise generated useful information

5
Survey Conclusions (2)
  • In general, more certainty of purpose on
    mechanics of reporting requirements than on asset
    management aspects
  • For example, difficulty reported in estimating
    expenditures necessary to achieve targeted
    conditions
  • Number of asset classes varied widely from one
    up to ten perhaps more than GASB anticipated?
  • Implementation costs were reasonable - generally
    under 500K for those states reporting an
    estimate

6
Survey Conclusions (3)
  • Modified approach states more likely to start the
    process earlier
  • Modified approach states more likely to believe
    that exercise improved communications
  • Great diversity of approach in calculating
    historical cost, cost allocation among capital,
    preservation and maintenance categories, and
    capitalization procedures
  • Many states expressed interest in receiving
    survey findings

7
  • Section 1 Overview Questions
  • Section 2 Depreciation
  • Section 3 Modified Approach
  • Section 4 Organization and Decision Making
  • Section 5 Costing Methodology
  • Section 6 Condition Assessment

8
Reporting Methods Used
  • A majority of states selected the depreciation
    approach, but only by a relatively small margin.

9
Reporting Methods Used
10
Combined Approach DOTs
  • Texas
  • Depreciation Bridges, Buildings, Rail Systems,
    Equipment
  • Modified Entire Road Network
  • Idaho
  • Depreciation Bridges, Rest Area Buildings
  • Modified Roads

11
Were alternate approaches seriously considered?
  • 13 states chose the depreciation approach without
    considering different perspectives on the
    reporting method
  • 14 states chose the modified approach without
    considering different perspectives on the
    reporting method

12
Which method is more helpful for making finance
and management decisions?
  • States that chose the modified approach tend to
    view the modified approach as the more helpful
    one (18/22), while states using the depreciation
    approach are more split on this issue
  • 10 states indicated that neither method was
    helpful for decision-making

13
Regardless of which method your agency uses,
which method do you feel is more challenging to
implement and report?
  • States that chose the depreciation approach tend
    to view the modified approach as more challenging
    to use (19/28), while states using modified are
    more split on this issue

14
The Single Most Challenging GASB 34
Implementation Issue for DOTs
15
Selecting Depreciation Approach
  • There were broad range of reasons provided for
    selecting the depreciation approach, but most
    were reasons for not selecting modified

16
GASB publications provide specific guidance for
allocating costs among capital, preservation and
maintenance categories. Survey responses suggest
that not all states are following these
guidelines.
Cost Allocation Policies
  • (73) If the expenditure increases the capacity
    or efficiency of an asset, it is treated as a
    capital asset.
  • (70) If the expenditure extends the useful life
    of an asset, it is treated as a capital asset.
  • (63) If the expenditure neither increases
    capacity/efficiency nor extends the useful life
    of the asset, it is a maintenance cost.
  • ( of states reporting that they follow this
    guideline)

17
Historical Cost was the most commonly used
method for calculating the beginning value of
assets for the depreciation calculation
Historical Cost Favorite Method
18
Modified Approach
  • Unlike with depreciation states, most of the
    reasons supplied for the approach selected were
    reasons for doing modified, not reasons for not
    doing depreciation. The most important reasons
    were more useful information and consistency with
    department philosophy.
  • Interestingly, modified states reported little
    difficulty in convincing others that this
    approach would provide better information.

19
GASB publications provide specific guidance for
allocating costs among capital, preservation and
maintenance categories. Survey responses suggest
that not all states are following these
guidelines.
Reported Policies
  • (95) If the expenditure increases the capacity
    or efficiency of an asset, it is treated as a
    capital asset
  • (50) If the expenditure extends the useful life
    of an asset, it is treated as a preservation cost
  • (82) If the expenditure neither increases
    capacity/efficiency nor extends the useful life
    of the asset, it is a maintenance cost
  • ( of states reporting that they follow this
    guideline)

20
Historical Cost Calculation
21
The Decision-Makers
  • 66 of all DOTs used committees for major
    decision making and policy development

22
When asked if implementing GASB 34 improved lines
of communication among the engineering, finance
and maintenance departments,
Communication Issues
23
Those who agreed that GASB 34 improved lines of
communication (25 states) were then asked if they
thought the communication improvement would
result in improved funding allocations between
expansion and preservation
Improved Communication Improved Allocation?
24
There is an apparent lack of standardization of
policies for when to capitalize project costs
Lack of Uniform Approach
25
New Ways in Which DOTs Plan to Use Information
From Their Condition Assessments
  • (24 states) No new plans to use the information,
    other than to comply with GASB 34.
  • (17 states) Aid in budgeting and funding
    requests.
  • (16) Strategically allocate dollars to parts of
    the system with the greatest need.
  • (15) Development of long range plans.

26
DOTs View of Overall Usefulness of Information
From GASB 34 Reporting
  • A majority of DOTs report that the additional
    information required by GASB 34 will be useful
    for a variety of purposes.
  • A minority (13) indicate that it will not be
    useful.
Write a Comment
User Comments (0)
About PowerShow.com