Title: WATER QUALITY PROGRAM
1WATER QUALITY PROGRAM
- RECIPIENT GRANT AND LOAN TRAINING 2009
2Agenda
- Loan Boilerplate Review
- Bid Process
- Progress Reports
- Payment Requests
3Important Things to Know
- American Recovery and Reinvestment Act (ARRA)
recipients will be given the opportunity to meet
with Ecology staff one on one to discuss any ARRA
specific requirement and to answer any questions. - If you are an ARRA recipient and wish to set up a
one on one meeting please contact Tammie McClure
or Dave Dunn.
4Important Dates
- Agreements must be signed by both parties no
later than 6 months after the publication date of
the combined Final Offer and Applicant List. - Work on the project must begin no later than 10
months after the publication date of the combined
Final Offer and Applicant List. - The project must be completed within 5 years of
the publication date of the combined Final Offer
and Applicant List.
5Grant Loan Agreements
6Loan Boilerplate Review
- General Information
- Project Budget
- Scope of Work
- Special Terms and Conditions
- Interest Rate Terms
- Attachments 1-8
- Amendments
- Closeout
7General Information
- Quick Reference to all General Information
- Project Name
- Loan Number
- Terms
- Contact Information
- Funding Type
- Increased Oversight
- Loan Security
- Project Dates (Start, IofO, Completion, Prior
Authorization, Interim Refinance, etc.)
8Project Budget
- Costs broken down by task
- Preferred method of tracking the budget
9Scope of Work
- Specific details of work
- Should closely follow proposal
- Timelines
- Must be able to measure progress
- Deliverables
- Plans and Specifications
- As-Builts
Yellow Book pg. 12
10Special Terms and Conditions/Interest Rate and
Terms
- Special Terms and Conditions would be anything
that is not already covered under the agreement
that one or both parties think important enough
to include as part of the agreement. - Interest Rates and Terms are determined and
provided for in the Final Intended Use Plan and
the Final Offer and Applicant List.
11Attachments
- Attachment 1 Opinion of Recipients Legal
Counsel - Attachment 2 Authorizing Ordinance or
Resolution - Attachment 3 Pre-award Compliance Review Report
for All Applicants Requesting Federal Assistance - Attachment 4 General Project Management
Requirements
12Attachments (cont.)
- Attachment 5 Agreement Definitions
- Attachment 6 - Loan General Terms and Conditions
- Attachment 7 Post Project Assessment Survey
- Attachment 8 Estimated Loan Repayment Schedule
(Amortization Schedule)
13Amendments
- Formal Process (requires both Ecology and
Recipients sign off) - Extensions submit request 3 months prior to
expiration date - Scope of work and budget modifications that
effect deliverables - Project close-out
- Informal Process
-
Yellow Book, pg. 13-14, 2010 Guidelines pg. 28-29
14Project Close-out
- Ecology will withhold the last 10 of a grant or
loan until all deliverables have been approved. - The recipient must submit final voucher and all
required financial, performance, and other
reports within 45 days after the
expiration/completion date of the agreement. - A final amendment and a final amortization
schedule including accrued interest will be
completed to officially close out the project.
Yellow Book, pp. 71-72
15Questions?
16Responsibilities during Bid, Award, and Pre -
construction
17Bid process
- Specification Inserts
- follow State Procurement Laws.
- Evidence of advertisement (submit to Ecology
Engineer)
18Award
- Bid Tabulations (submit to Ecology Engineer)
- Bid Proposal from the successful low bidder
(submit to Ecology Engineer) - Acknowledgement of receipt of all addenda
- Bid Bond
- Performance and Payment Bonds
- Certifications of Insurance
- Notice of Award (submit to Ecology Engineer)
- Executed contract agreement (submit to Ecology
Engineer)
19Start of Work
- Pre-construction meeting (invite Ecology Staff)
- Construction Quality Assurance Plan (submit to
Ecology Engineer) - Notice to Proceed (submit to Ecology Engineer)
- Construction schedule (submit to Ecology
Engineer)
20Construction
- Three copies of all change orders
- Copies of issued change orders
- Significant change orders must be approved
- Substantial Completion by owner
- Operation and Maintenance Manual
- Final Acceptance by owner
- Declaration of Construction Completion.
- As build drawings.
21PROGRESS REPORTS and Payment Requests
22Progress Reports
- The Progress report is
- An important tool - ensures that the progress is
consistent with spending. - Required at least quarterly.
- Due Jan 15, Apr 15, Jul 15, Oct 15
- Standard form is available.
- Payment requests will be held until the most
recent progress report has been submitted.
Yellow Book, pg. 18, 2010 Guidelines pg. 33
23Progress Reports
- A progress report must contain
- Actual accomplishments compared to the objectives
established for the period - Any delays and reasons for the delay
- Any cost overruns and reasons for the cost
overruns - Measurable deliverables and
- Any additional information that may be of
interest.
Yellow Book, pg. 18, 2010 Guidelines pg. 33
24Progress Reports
- You will find information regarding progress
reporting in the Yellow Book and your funding
guidelines. - A copy of the progress report form can be found
on our website http//www.ecy.wa.gov/programs/wq
/funding/GrantLoanMgmtTools.html
25Payment Requests
- Required forms with all vouchers
- Signed, original A-19
- B2 and C2 forms
- Form D Contractor Participation report
(regardless of contractor participation) - These forms and others can be found
http//www.ecy.wa.gov/programs/wq/funding/GrantLoa
nMgmtTools.html
Yellow Book Appendix A, 2010 Guidelines pg. 32
26Other Forms
- Form E Monthly Time Sheet
- Form F Record of Meeting Attendance
- Form G Sales and Use Tax Report (required at
project completion) - Form H Conversion to Composite Hourly Billing
Rate for Employee - Form I Valuation of Donated Property
Yellow Book, Appendix D
27How to Fill Out a Voucher
- Start from the back and work your way forward
beginning with the C form! - Form C itemization for current charges
28How to Fill Out a Voucher
Dont forget to calculate the totals of each
column
29How to Fill Out a Voucher
30Questions?