Plan - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Plan

Description:

Power for counting rooms supplied from surface transformer. Power to Experimental Area. One transformer will supply power to racks ... – PowerPoint PPT presentation

Number of Views:34
Avg rating:3.0/5.0
Slides: 22
Provided by: pio784
Category:
Tags: plan | transformer

less

Transcript and Presenter's Notes

Title: Plan


1
Services Update
  • Progress on services
  • Detector cabling
  • Gas systems
  • Cooling systems
  • Rack footprint
  • Primary electrical distribution
  • Utilities
  • Principle Priorities
  • For Q4 2003


2
Progress On Services
  • Services on RB26 side
  • Must be installed this year, in order to close
    the doors
  • Complex routing limited space
  • Temporary supports will be required inside the L3
    magnet


Layout at time of last ALICE week
Some gas cooling pipes
Basic Bus Bar layout
Some cables
3
Detector Cabling (1)
  • Inventory well advanced
  • Over 1600 cables to be installed on RB26 side


Rack allocation
Cable type CERN standard or special
Typical inventory for TPC
4
Detector Cabling (2)
Inventory Integrated Ordered Installed
ITS Pixel Drift Strip 75 75 75 20 20 20
Vo 60 20
To 80 20
FMD 20 20
TPC 90 60
TRD 90 60
TOF 90 60
HMPID 90 10
CPV 25 5
PHOS 5 5
MUON Tracking Trigger 80 80 50 60 40
5
Detector Cabling (3)
  • High voltage and signal cables
  • Will be installed using the existing EST/LEA
    industrial support contract
  • Under the direct supervision of the ALICE team
  • Cables will be installed and cut to approximate
    length
  • Cables will be cut to the exact length and
    connectors will be added, when the detectors have
    been put in place
  • Fiber optic cables
  • ALICE team will install the ducts
  • The specialist team from ST/EL will blow the
    fibers at a later date


6
Gas Systems
Preliminary design Final design PRR Construction Installation
TPC Completed Completed Completed In progress
TRD Completed Completed
TOF Completed Completed Completed
HMPID Completed Completed Completed In progress
CPV Completed Completed Completed
PMD Completed Completed Completed
Muon Track Completed Completed Completed In progress
Muon Trig Completed Completed Completed In progress

Status 1st. September 2003
7
Cooling Systems
Preliminary design Final Design PRR Construction Installation
ITS Completed Completed Completed
TPC Completed Completed
TRD Completed Completed
TOF Completed
Bus Bars Completed
HMPID Completed Completed
CPV In progress
PHOS In progress
PMD In progress
MUON Trac. In progress

Status 1st. September 2003
8
Layout of Services (1)

Start off with a clean sheet
9
Layout of Services (2)
Fiber optic cables
Bus Bars
Cooling Gas pipes

ITS services
Gas, Cooling Bus Bars on back frame
10
Layout of Services (3)
Cooling Gas pipes Through doors

Bus Bars
11
Layout of Services (4)

Access passage around Back frame
12
Detector Cabling (5)

Installation schedule for cables on RB26
side Between September December 2003
13
Rack Footprint (1)
  • Standard 52U high racks
  • UX25 cavern
  • 133 racks have been identified
  • Racks allocated to sub-detectors
  • Numbering follows CERN ST/EL standard
  • Grouped into 4 areas (see following slide)
  • PX24 counting rooms
  • Existing racks will be used
  • Allocated as required

UX25 PX24
ITS 12
TPC 9
TRD 12
TOF 13
HMPID 3
PHOS/CPV 3
PMD 2
MUON Trac. 12
MUON Trig. 14
CTP 9
Small detectors 10
Misc. 7
DAQ (P1) 38
HLT (P2) 0
DCS (P3) 20
Detectors (P4) 39
Total 106 97
Reserve 27 0
Grand Total 133 97

14
Rack Footprint (2)
Inside machine

Outside machine
Big block house
Small block house
15
Rack Footprint (3)
  • Crate allocation (UX25)
  • Well advanced
  • 60 out of 132 racks have detailed crate layout


16
Primary Electrical Distribution
  • Now well understood
  • Power for counting rooms supplied from surface
    transformer
  • Power to Experimental Area
  • One transformer will supply power to racks
  • A separate transformer will supply power to
    equipment with pumps etc.

17
Primary Electrical Distribution
1,25MVA Transformer
2MVA Transformer
EXD1/2X
EBD1/2X
EBD5/2X
EBD3/2X
S.G. SX2 et PX24
Eclairage,clim PX24

Niv.1
Niv.2
1,25MVA
1,25MVA
1,25MVA
Niv.3
EXD1/25
EBD1/25
EQD1/25
Niv.4
EBD1/20
EXD-/20
BOUCHON
700KVA Rech. Cryo
Free
EBD3/25
EBD2/29
Alim S.G. UX25 Pont roulant Force 125A-63A,.
ST-CV
EBD4/25
Alim S.G. UX25 Eclairage,petite
force Auxiliaires,.
EBD3/29
18
TPC Lasers

New shielding layout gives better access to TPC
lasers
19
Vo Cable Length

Cable length 25m
20
Utilities
Installed at Point 2 IR1 estimates IR2 estimates
Electrical power supply 3,25MVA 2,62MVA 2,62MVA
Mixed water supply Chilled water supply 172m3/h 72m3/h 161m3/h 66,5m3/h 155m3/h 66m3/h
Cavern ventilation 150kW 134kW 129kW
  • Mixed water supply
  • Rack filling factor of 100
  • Cooling efficiency 90
  • Number of racks reduced
  • From 140 to 133
  • Cavern ventilation
  • 4 reduction

21
Priorities For Last Quarter of 2003
  • Side structures
  • For racks
  • To allow Bus Bar cable installation
  • Services through RB26 doors
  • Bus Bars
  • Cables
  • Gas pipes
  • Cooling pipes

To counting room (P4)

Detector
Cable installation
Modified side structures (UX25)
Rack positions
Write a Comment
User Comments (0)
About PowerShow.com