4' Material Requirements Planning - PowerPoint PPT Presentation

1 / 29
About This Presentation
Title:

4' Material Requirements Planning

Description:

Glue. 066. Leg. Supports(4) 533. Ends(2) 411. Sides(2) 622 ... Glue. 066. Figure 4.7 Single-level bills. BILLS OF MATERIAL. MANUFACTURING BILL OF MATERIAL ... – PowerPoint PPT presentation

Number of Views:87
Avg rating:3.0/5.0
Slides: 30
Provided by: iemenHa
Category:

less

Transcript and Presenter's Notes

Title: 4' Material Requirements Planning


1
4. Material Requirements Planning
  • 4? ???
  • ???

2
Material Requirements Planning
INTRODUCTION This chapter will describe bills
of material(the major building block of material
requirements planning), detail the MRP process,
and explain how the material requirements plan is
used. But first, some details about the
environment in which MRP operates. Nature of
Demand There are two types of demand
independent and dependent. Independent demand is
not related to the demand for any other product.
For example, if a company makes wooden tables,
the demand for the tables is independent. Master
production schedule items are independent demand
items. The demand for the sides, ends, legs, and
tops depends on the demand for the tables, and
these are dependent demand items.
3
Material Requirements Planning
  • Objectives of MRP
  • Material requirements planning has two major
    objectives determine requirements and keep
    priorities current.
  • Determine requirements
  • It must determine the following
  • What to order.
  • How much to order.
  • When to order.
  • When to schedule delivery.
  • Linkages to Other MPC Functions
  • The MRP is a priority plan for the components
    needed to make the products in the MPS.
  • Material requirements planning drives, or is
    input to, production activity control (PAC) and
    purchasing. MRP plans the release and receipt
    dates for orders. PAC and purchasing must plan
    and control the performance of the orders to meet
    the due dates.
  • Figure 4.2 shows a diagram of the production
    planning and control system with its inputs and
    outputs.

4
Material Requirements Planning
Independent Demand (Forecast)
Dependent Demand (calculated)
5
Material Requirements Planning
6
Material Requirements Planning
  • Inputs to the Material Requirements planning
    System
  • There are three inputs to MRP systems
  • 1. Master production schedule.
  • 2. Inventory records.
  • 3. Bills of material.
  • Master production schedule
  • The master production schedule is a statement
    of which end items are to be produced the
    quantity of each, and the dates they are to be
    complete.
  • Inventory records
  • A major input to the MRP system is inventory.
    When a calculation is made to find out how many
    are needed, the quantities available must be
    considered.
  • There are two kinds of information needed. The
    first is called planning factors and includes
    information such as order quantities, lead times,
    safety stock, and scrap. This information does
    not change often however, it is needed to plan
    what quantities to order and when to order for
    timely deliveries.
  • The second kind of information necessary is on
    the status of each item. The MRP system needs to
    know how much is available, how much is
    allocated, and how much is available for future
    demand. This type of information is dynamic and
    changes with every transaction that takes place.
  • Bills of material
  • The bill of material is one of the most
    important documents in a manufacturing company.

7
BILLS OF MATERIAL
The American Production and Inventory
Control Society(APICS) defines a bill of
material as a listing of all the subassemblies,
intermediates, parts, and raw materials that go
into making the parent assembly showing the
quantities of each required to make an assembly.
Figure 4.3 shows a simplified bill of material.
There are three important points 1. The
bill of material shows all the parts required to
make one of the item. 2. Each part or item
has only one part number. A specific number is
unique to one part and is not assigned to any
other part. Thus, if a particular number appears
on two different bills of material, the part so
identified is the same. 3. A part is defined
by its form, fit, or function. If any of these
change, then it is not the same part and it must
have a different part number. For example, a part
when painted becomes a different part and must
have a different number. If the part could be
painted in three different colors, then each must
be identified with its unique number.
8
BILLS OF MATERIAL
9
BILLS OF MATERIAL
Bills of material Structure Bills of material
structure refers to the overall design for the
arrangement of bills of material files. Product
tree - Figure 4.4 shows a product tree for the
bill of material shown in Figure 4.3. The product
tree is a convenient way to think about bills of
material, but it is seldom used except for
teaching and testing. In this text, it is used
for that purpose. Parent-component relationship
-The product tree and the bill of material shown
in Figures 4.1 and 4.3 are called single level
structures. Figure 4.4 shows the
parent-component relationship of the table (P/N
100). Unique part numbers have also been assigned
to each part. Multilevel bill - Figure 4.5
shows the same product as the single-level bill
shown in Figures 4.3 and 4.4. However, the
single-level components have been expanded into
their components.
10
BILLS OF MATERIAL
11
BILLS OF MATERIAL
  • Multiple bill - A multiple bill is used when
    companies usually make more than one product, and
    the same components are often used in several
    products. This is particularly true with families
    of products.
  • Figure 4.6 shows the two bills of material.
  • Single-level bill A single-level bill of
    material contains only the parent and its
    immediate components, which is why it is called a
    single-level bill. The tables shown in Figure 4.6
    have six single-level bills, and these are shown
    in Figure 4.7. Note that many components are
    common to both tables.
  • There are several advantages to using
    single-level bills including the following
  • Duplication of records is avoided. For instance,
    base 200 is used in both table 100 and table 150.
    Rather than have two records of base 200--one in
    the bill for table 100 and one in toe bill for
    table 150only one record need be kept.
  • The number of records and, in computer systems,
    the file size is reduced by avoiding duplication
    of records.
  • Maintaining bills of material is simplified. For
    example, if there is a change in base 200, the
    change need be made in only one place.

12
BILLS OF MATERIAL
13
BILLS OF MATERIAL
14
BILLS OF MATERIAL
Indented bill A multilevel bill of material
can also be shown as an indented bill of
material. This bill uses indentations as a way of
identifying parents from components. Figure 4.8
shows an indented bill for the table in Figure
4.5. Summarized parts list The bill of
material shown in Figure 4.3 is called a
summarized parts list. It lists all the parts
needed to make one complete assembly.
15
BILLS OF MATERIAL
Planning bill a major use of bills of material
is to plan production. Planning bills are an
artificial grouping of components for planning
purposes.
16
BILLS OF MATERIAL
Where-Used and Pegging Where-used report
Where-used reports give the same information as a
bill of material, but the where-used report gives
the parents for a component whereas the bill
gives the components for a parent. Pegging
report The pegging report shows the parents
creating the demand for the components, the
quantities needed, and when they are needed,
pegging keeps track of the origin of the demand.
Figure 4.10 shows an example of a product tree in
which part C is used twice and a pegging report.
17
BILLS OF MATERIAL
  • Uses for Bills of Material
  • The bill of material is one of the most widely
    used documents in a manufacturing company. Some
    major uses are as follows
  • Product definition. The bill specifies the
    components needed to make the product.
  • Engineering change control. Product design
    engineers sometimes change the design of a
    product and the components used. These changes
    must be recorded and controlled. The bill
    provides the method for doing so.
  • Service parts. Replacement parts needed to
    repair a broken component are determined from the
    bill of material.
  • Planning. Bills of material define what
    materials have to be scheduled to make the end
    product. They define what components have to be
    purchased or made to satisfy the master
    production schedule.
  • Order entry. When a product has a very large
    number of options, the order-entry system very
    often configures the endproduct bill of
    materials. The bill can also be used to price the
    product.
  • Manufacturing. The bill provides a list of the
    parts needed to make or assemble a product.
  • Costing. Product cost is usually broken down
    into direct material, direct labor, and overhead.
    The bill provides not only a method of
    determining direct material but also a structure
    for recording direct labor and distributing
    overhead.

18
MATERIAL REQUIREMENTS PLANNING PROCESS
  • MATERIAL REQUIREMENTS PLANNING PROCESS
  • The purpose of material requirements planning
    is to determine the components needed,
    quantities, and due dates so items in the master
    production schedule are made on time. This
    section studies the basic MRP techniques for
    doing so. These techniques will be discussed
    under the following headings
  • Exploding and offsetting
  • Gross and net requirements
  • Releasing orders
  • Low-level coding and netting

19
MATERIAL REQUIREMENTS PLANNING PROCESS
Exploding and Offsetting Lead time Lead time
is the span of time needed to perform a process.
In manufacturing it includes time for order
preparation, queuing, processing, moving,
receiving and inspecting, and any expected
delays. Exploding the requirements Exploding
is the process of multiplying the requirements by
the usage quantity and recording the appropriate
requirements throughout the product tree.
Offsetting Offsetting is the process of placing
the exploded requirements in their proper periods
based on lead time. Planned orders If it is
planned to receive 50 of part A in week 5 and the
lead time to assemble an A is one week, the order
will have to be released and production started
no later than week 4.
20
MATERIAL REQUIREMENTS PLANNING PROCESS
21
MATERIAL REQUIREMENTS PLANNING PROCESS
Gross and Net Requirements The previous section
assumed that no inventory was available for the
As or any of the components. Often inventory is
available and must be included when calculating
quantities to be produced. If, for instance,
there are 20 As in stock, only 30 need to be
made. The requirements for component parts would
be reduced accordingly. The calculation is as
follows Gross requirement 50
Inventory available 20 Net requirements
gross requirements available inventory Net
requirements 50 20 30 units Since only 30
As need to be made, the gross requirement for Bs
and Cs is only 30. The planned order release of
the parent becomes the gross requirement of the
component.
22
MATERIAL REQUIREMENTS PLANNING PROCESS
Released Orders Scheduled receipts Scheduled
receipts are orders placed on manufacturing or on
a vendor and represent a commitment to make or
buy. Open orders Scheduled receipts on the MRP
record are open orders on the factory or a vendor
and are the responsibility of purchasing and of
production activity control. Net requirements
The calculation for net requirements can now be
modified to include scheduled receipts. Net
requirements gross requirements - scheduled
receipts - available inventory Basic MRP
Record Figure 4.15 shows a basic MRP record.
There are several points that are important
1. The current time is the beginning of the
first period. 2. The top row shows
periods, called time buckets. These are often a
week but can be any length of time convenient to
the company. Some companies are moving to daily
time buckets. 3. The number of periods in
the record is called the planning horizon, which
shows the number of future periods for which
plans are being made. It should be at least as
long as the cumulative product lead time.
Otherwise, the MRP system is not able to release
planned orders of items at the lower level at the
correct time. 4. An item is considered
available at the beginning of the time bucket in
which it is required. 5. The quantity
shown in the projected on-hand row is the
projected on-hand balance at the end of the
period. 6. The immediate or most current
period is called the action bucket. A quantity in
the action bucket means that some action is
needed now to avoid a future problem.
23
MATERIAL REQUIREMENTS PLANNING PROCESS
Capacity Requirements Planning As occurred in
the previous planning levels, the MRP priority
plan must be checked against available capacity.
At the MRP planning level, the process is called
capacity requirements planning (CRP) . Low-Level
Coding and Netting The process of collecting the
gross requirements and netting can be simplified
by using low-level codes. The low-level code is
the lowest level on which a part resides in all
bills of material. Every part has only one
low-level code. The low-level codes for the parts
in toe product tree shown in Figure 4.16 are
24
MATERIAL REQUIREMENTS PLANNING PROCESS
Part Low-Level Code A 0
B 1 C 2 D
2
25
MATERIAL REQUIREMENTS PLANNING PROCESS
Multiple Bills of Material Most companies make
more than one product and often use the same
components in many of their products. The
material requirements planning system gathers the
planned order releases from all the parents and
creates a schedule of gross requirements for the
components. Figure 4.20 illustrates what happens.
26
USING THE MATERIAL REQUIREMENTS PLAN
USING THE MATERIAL REQUIREMENTS PLAN
The basic responsibilities of a planner are to
1. Launch (release)orders to purchasing or
manufacturing. 2. Reschedule due dates of
open (existing) orders as required. 3.
Reconcile errors and try to find their cause.
4. Solve critical material shortages by
expediting or re-planning. 5. Coordinate
with other planners, master production
schedulers, production activity control, and
purchasing to resolve problems. Planned orders
Released orders. Firm planned orders. Exception
messages. Transaction messages.
27
USING THE MATERIAL REQUIREMENTS PLAN
  • Managing the Material Requirements Plan
  • The planner receives feedback from many sources
    such as
  • Suppliers actions through purchasing.
  • Changes to open orders in the factory such as
    early or late completions or differing
    quantities.
  • Management action such as changing the master
    production schedule.
  • The planner must evaluate this feedback and take
    corrective action if necessary. The planner must
    consider three important factors in managing the
    material requirements plan.
  • Priority Priority refers to maintaining the
    correct due dates by constantly evaluating the
    true due-date need for released orders and, if
    necessary, expediting or de-expediting.
  • Bottom-up replanning Action to correct for
    changed conditions should occur as low in the
    product structure as possible.
  • Reducing system nervousness.

28
SUMMARY
The job of the MRP is to produce the right
components at the right time so that the MPS can
be maintained. The MRP depends on accurate bills
of material and on accurate inventory records.
Bills of material can be created in many ways,
but one department (or individual) must be
responsible for them. Inventory records are
indispensable to the MRP, and the MRP is only as
good as the inventory records. The MRP
exploding and offsetting processes out lined in
this book are largely done by the computer. The
logic used is repetitive and , while error prone
by individuals, can be accomplished by computer.
Good MRP practice is achieved by planners being
able to work with the system.
29
Thank you
Write a Comment
User Comments (0)
About PowerShow.com