Title: Background
1Role of Private Sector in EIA The RTNMC/CBNC
Experience
- Background
- Roads Taken
- Lessons Learned
- Role of RTNMC/CBNC in EIA
- EIA Outcome
- Recommendations
2The RTNMC Operation
Since 1977, RTNMC has been mining saprolitic
nickel ores selling them to ferro-nickel smelters
abroad. The mine is located in Barangay Rio
Tuba, Bataraza, Palawan. In 1996, an EIA was
conducted for the renewal of its 990-Ha Ni Mining
Claims and the conversion of its MLC to MPSA.
ECC was granted the following year.
3In its more than 25 years of operation, RTNMC
accumulated 20 million dry tonnes of laterite and
low-grade Ni ore. Then considered as waste,
these were stockpiled at the site.
4The HPP Project of CBNC
Extensive metallurgical tests were carried out to
extract Ni and Co from the low-grade ore. The
production of a mixed Ni and Co sulfide through a
hydrometallurgical process called HPAL was found
possible. Later developments by Sumitomo Metals
and Mining Co. Ltd. justified the feasibility of
the HPP Project.
5The project is located inside the mining facility
of RTNMC.In Oct. 2000, an EIA was conducted and
the ECC was granted in July,2002.While
construction proceeded, the ECC was challenged in
the senate, in the courts, and at the PCSD.In
Aug.- Sept, 2004, the MPP and EPEP were obtained.
MPSA will be released this month.
6 The HPP Complex
7Roads Taken... (The RTNMC/CBNC Experience with
the HPP Project)
8(No Transcript)
9623 days
10-
- ECC took 617 days (102500-071002)
- Project Scoping , 115 days
(102500-021901) - EIS Preparation , 157 days
(021901-072401) -
- EIS public acceptance took
- Bataraza Sanggunian , 26 days
(072401-082001) - Bgy Rio Tuba Sanggunian, 32 days
(072401-082601) - Palawan Sanggunian , 47 days
(072401-091101) - 30 Different Organizations, 110 days
(072401-111201) - 5 IP Councils , 154 days
(072401-122601) - 10 Brgy Capts Manifesto , 206 days
(072401-021902) - EIS technical report acceptance took
- PCSD , 127 days
(072401-112901)
11Reasons for Long EIA Process
- Wide latitude given to all stakeholders LGUs,
NGOs, POs, IPs, Church - Two separate reviews to contend with PCSD and
EMB
12(No Transcript)
13- NCIP - CPC took 1148 days(062501-092404)
- Application for 1st FBI by NCIP Provl
, 101 days - Moratorium on FPIC processing
, 300 days - Reapplication for 1st FBI by NCIP IV
, 150 days - Notification to FPIC Conduct by NCIP IV
, 65 days - Application for CPC/Denial by NCIP IV
, 30 days - Conduct of 2nd FBI by NCIP IV
, 36 days - Reapplication for CPC/Denial of NCIP IV
, 139 days - Appeal to NCIP CO to 3rd FBI and
- Conduct of FPIC by NCIP CO Legal
, 90 days - Submission of FPIC / MOA and
- Approval by NCIP CO
, 237 days - NCIP Issuance
- CPC
, 1148 days
(062501-082404) - MOA
, 1175 days
(062501-092104)
14Reasons for Long FPIC Process
- Moratorium while NCIPs A.O. of 1998 was reviewed
and revised to A.O. of 2002 - Questionable legal interpretation of A.O. of 2002
and apparent bias at the NCIP IV level. - Influence of some NGOs on the IPs.
15(No Transcript)
16- NGO Case took 547 days(121602-062304)
- Petition for Certiorari, Manila Court of Appeals
- (Dismissed, 121602 093003)
, 284 days - Motion for Reconsideration, Manila Court of
Appeals - (Denied, 093003 120803)
, 68 days - Petition for Review on Certiorari, Supreme Court
- (Denied, 120803 022304)
, 75 days - Motion for Reconsideration, Supreme Court
- (Denied with Finality, 022304 062304)
, 120days
17Issues and Rulings
- NGO Issue
- Grave abuse of authority and discretion by the
DENR Secretary in issuing the ECC - Supreme Courts Ruling
- Courts will not interfere in matters which are
addressed to the sound discretion of government
agency entrusted with regulations or activities
coming under the special and technical training
and knowledge of such agency. - Courts respect rulings of quasi-judicial bodies
with finality if these are supported with
substantial evidence. - Administrative agencies are given wide latitude
in the evaluation of evidence and in the exercise
of its adjudicative functions. - Petitioners failed to present compelling reason
to warrant the deviation by this court from the
foregoing salutatory principles.
18(No Transcript)
19- PCSD RECALL took 305 days(100903 - 081304)
- Explanation of 13 old / recyled issues raised
- by NGO (100903 112103)
, 43 days - Discussion of Inspection/Investigation Report
- of PCSDs TWG (112103 030804)
, 107 days - Discussion of Inspection/Investigation Report
- of PCSDs CENR (030804 081304)
, 155 days - Decision Uphold the earlier clearance granted on
- November 29, 2001.
20(No Transcript)
21Causes of the Delays
- MPP took 623 days (120902-082704)
-
- NCIPs late issuance of CPC
- EPEP took 686 days(103002-092104)
- NGO Petition for Certiorari
- PCSD Recall of HPP Clearance
- MPSA will be obtained this month.
22Roads Taken...
...were Bumpy but Passable!
23LESSONS LEARNED
- The EIA exercise was costly and time-consuming,
but - The comprehensive discussions and dialogues
resulted in increased information flow to the
stakeholders which enhanced their high level of
awareness. - On the part of the proponent, it made them
realized the importance of becoming pro-active in
addressing social and environmental issues. - The exercise gave the assurance of the eventual
realization of a balance of interests between
development and environment. - The experience was educational to the foreign
investors and the business sector as well because
of its far-reaching implications on doing
business in our country. - The judiciarys impartiality and high respect to
administrative agencies was once again manifested.
24Role of RTNMC/CBNC in EIA
- Must be active participants, not just
fence-sitters or behind the EIS preparers - Shoulder financial responsibility during the EIA
conduct and reviews - Explain thoroughly the plans and coordinate
credibly with all sectors - Be responsible for administrative and
coordination works - Work very hard to get public acceptance
25EIA/EIS ensures a balance of interests on
- Economic Viability stated in the FS
- Environmental Protection thru the EPEP
- Social Responsibility thru the SDMP
26RTNMC ACCOMPLISHMENTS
- Infrastructures for Community Service (Php 100
million, at the start of operations) for
construction of hospital with pharmacy, schools,
recreational facilities, markets, a catholic
church, a muslim mosque, airstrip and port
facilities. - Environmental/Social Concerns (1991-2004)
- Environmental Protection (Php 135 million) for
soil erosion control measures, dust suppression
system, and mine rehabilitation/reforestation
programs (203 Has. Mined Out areas and 132 Has.
Outside). Recipient of 2002 PMIEA and other
Environmental Awards, and 6 Safety Awards. - Social Responsibility (Php 50 million) - for
social development such as for school subsidies
and scholarships, free medical /dental services,
free transportation and water supply, free power
to selected public places, sanitation (communal
latrines), construction and maintenance of 51 kms
farm to markets roads, and skills development
programs. -
- Generated jobs for 700 direct and indirect
labor force. Stimulated local business and
improved trade and commerce in the locality and
province of Palawan,
27CBNC ACCOMPLISHMENT/PROGRAM
- Environmental Protection (Php 910 million
capital, Php 230 million/yr operating) for
wastewater treatment plants, tailings disposal
system, air pollution control facilities, solid
waste management system, and safety / health
programs. Recipient of 2004 Safety Award for 3
million manhours without LTA during the
construction of the project facilities. - Combined CBNC/RTNMC Social Responsibility (Php 90
million for 5 years for 10 barangays) - for
social development such as construction of
classrooms, day-care centers, tribal halls,
recreational facilities, 80 kms of main and
feeder roads. Extends scholarships and free
medical/dental services. Gives assistance to
livelihood projects in the form of capital for
cooperatives, farm tractors, improved irrigation
systems, seeds and pesticides, and animal
husbandry. Improves mobility with provision of
multicabs and tricycles with sidecars in each
barangay and communications with radios and
cellfones, training/literacy programs. - Generated jobs for an average of 1000 workers
during construction and 500 employees when in
operation. Stimulated local business and improved
trade and commerce in the locality and province
of Palawan.
28RECOMMENDATIONS
- Proponents should be true to its commitments and
transparent in all transactions. - The IEC should be pursued and continuously
improved to be more effective in ensuring faster
and accurate flow of information. - Recognizing the NGOs steadfast dedication to
protect the environment, they are encourage to
get better technical advice to enable them to
understand and better appreciate genuine efforts
at explaining issues hence, give more merit to
their work. - Tap third party consultants to enable access to
impartial and technically sound project
assessment and recommendations.
29Thank You!
Happy Valentine