Title: STUDENT DATA


1
STUDENT DATA
  • Now on K Fulltime/MsProject2005/IT_Management/Uni
    t_04/Student Data

2
Managing resources
  • Unit objectives
  • Use the Change Working Time dialog box to create
    a base calendar for a project
  • Use the resource sheet to create a resource pool,
    assign resources to tasks, and create a task
    calendar
  • Enter resource costs in Resource Sheet view and
    use the Cost table in Gantt Chart view

3
Topic A
  • Topic A Creating base calendars
  • Topic B Working with resources and calendars
  • Topic C Working with resource costs

4
Base calendars
  • Every project is linked to a base calendar
  • You create a custom base calendar to incorporate
    company holidays and working times into the
    project schedule
  • All tasks are scheduled according to the dates on
    the base calendar to which the project is linked

5
Creating a new base calendar
  • Choose Tools, Change Working Time

6
Change Working Time dialog box
7
Creating a new base calendar
  • Click New and enter the calendar name Company A
  • Select Create New Base Calendar
  • Click OK (now working on Company A Calendar)

8
Creating a new base calendar
  • Company A is on a 4 day workweek. Specify working
    time for the working days Click the column
    heading for Monday (highlights whole column) and
    on the right side, select non-working hours.
    Click OK
  • To double check, Tools, Change Working Hours

9
Creating a new base calendar
  • Choose Project, Project Information
  • Select drop down box for Calendar, and select
    company A. Click OK.
  • Enter new task Lay Foundation, duration 10
    days.
  • Notice it spans 10 working days.

10
Topic B
  • Topic A Creating base calendars
  • Topic B Working with resources and calendars
  • Topic C Working with resource costs

11
The resource pool
  • Is a list of resources needed to complete a
    project
  • Two types
  • Work resources perform work on a task (people and
    equipment)
  • Material resources are the things needed to
    perform work on a task (paint, wood, fuel)

12
Creating a resource pool
  • View, Resource Sheet.
  • Name George
  • Type Work
  • Initials GG
  • GroupIT
  • Std Rate 50/hr
  • Overtime Rate75/hour
  • Calendarstandard

13
Creating a resource pool
  • Name Mary
  • Type Work
  • Initials MB
  • GroupIT
  • Std Rate 50/hr
  • Overtime Rate75/hour
  • Calendarstandard

14
Creating a resource pool
  • Name Cable
  • Type Material
  • Material labelFibre
  • Cost per use150

15
Resource calendar
  • Contains the information that is specific to a
    resource
  • To create a resource calendar
  • Select a resource George
  • Double click or select tool Resource
    information.
  • Activate the Working Time tab
  • George only works Tuesdays, Wednesdays and
    Thursdays.
  • Make the necessary changes in the calendar
    (Hilite non working days).
  • Click OK

16
Assigning resources
  • To assign resources
  • Switch to Gantt Chart view
  • Add a task lay cable for 15 workstations, 15
    days.
  • Choose Tools, Assign Resources or find on toolbar
    (little people).
  • Select cable click Assign. Drop down table
    Units15.
  • Select George, Click Assign, 100
  • Select Mary ,Click Assign, 25
  • Click Close (duration now30 days)

17
Assigning a resource to multiple tasks
  • Enter new tasks Configure server, 5 days
    Configure switch, 5 days.
  • Select both tasks
  • Open the Assign Resources dialog box
  • Select the resource name George
  • (To select multiple resource names to assign to
    multiple tasks, select all resource names (Ctrl
    click))
  • Click Assign

18
Task calendars
  • Used to specify working times that differ from
    the project calendar or resource calendars
  • Define exceptions for scheduling individual tasks
    such as equipment maintenance
  • Take precedence over the project calendar
  • Equal in importance to a resource calendar

19
Task calendars
  • Create new base calendar
  • Tools, Change working time, NEW, name test.
  • Change Saturday morning from 9am-3pm to be
    working hours. (Hilite title for Saturday,
    choose non default working time, change to
    9am-3pm). Click ok.
  • Notice schedule bar for lay Foundation.
  • Double click OR Hilite lay foundation, then
    Project, Task Information.
  • Choose the Advanced Tab. Change drop down list
    for Calendar to Test.
  • Click on Scheduling ignores resource calendars.
    Click OK.

20
Topic C
  • Topic A Creating base calendars
  • Topic B Working with resources and calendars
  • Topic C Working with resource costs

21
Types of costs
  • Fixed costs
  • Remains the same despite adding or removing
    resources
  • Variable costs
  • Varies with the frequency and amount of time a
    resource is used
  • Standard cost
  • Overtime cost
  • Per use cost

22
Types of costs
  • View, Resource Sheet, look at costs
  • Fixed costs
  • None entered yet.
  • Variable costs
  • Varies with the frequency and amount of time a
    resource is used
  • George and Mary
  • Standard cost
  • Overtime cost
  • Cable
  • 150 per use

23
Using the Cost table
  • Switch to Gantt Chart view
  • Choose View, Table, Cost (more views)
  • For lay foundation under Fixed Cost field,
    enter 15000.
  • Notice each task has a cost. If you add a
    project summary line (and adjust format), you can
    see total project cost.

24
Unit summary
  • Created a base calendar for a project
  • Used the resource sheet to create a resource
    pool, assigned resources to tasks, and created a
    task calendar
  • Entered resource costs in Resource Sheet view and
    used the Cost table in Gantt Chart view

25
Independent Practice Activity
  • Exercise is on page of Unit 4-20
  • Use file on K Fulltime/MsProject2005/IT_Managemen
    t/Unit_04/Practice Resources
  • Answer on K, same place Practice Resources
    Answer