MAG Arterial Life Cycle Program: Draft Policies and Procedures - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

MAG Arterial Life Cycle Program: Draft Policies and Procedures

Description:

Compliance. Factors considered. The life cycle program must include all of the arterial projects ... with the existing Highway Acceleration Policy with 50 / 50 ... – PowerPoint PPT presentation

Number of Views:23
Avg rating:3.0/5.0
Slides: 19
Provided by: GTy
Category:

less

Transcript and Presenter's Notes

Title: MAG Arterial Life Cycle Program: Draft Policies and Procedures


1
MAG Arterial Life Cycle ProgramDraft Policies
and Procedures
2
RTP Arterial Program (2002 dollars)
  • 62 street projects _at_ 1.3 billion
  • 34 intersection projects _at_ 113 million
  • 50 million for arterial ITS projects
  • 863 million in sales tax funds
  • 105 million in CMAQ
  • 497 million in STP

3
(No Transcript)
4
Life Cycle Budget
  • HB 2456 requires that MAG
  • shall adopt a budget process that ensures the
    estimated cost of the arterial street mode does
    not exceed the total amount of revenue estimated
    to be available for the arterial street mode.

5
Objectives
  • Fiscal Integrity
  • Effective Efficient RTP Implementation
  • Accountability
  • Transparency
  • Compliance

6
Factors considered
  • The life cycle program must include all of the
    arterial projects identified in the RTP.
  • Resources to fund arterial projects must be
    sufficient to build the first projects as well as
    the last projects in the program.
  • Many of the projects have not been fully scoped
    or designed.
  • Funding from third parties should be encouraged.
  • Adequate funding to complete the project must be
    identified before construction begins.
  • Jurisdictions should be able to advance construct
    projects and be reimbursed according to the
    adopted schedule.

7
Overview
  • Designation of lead agency
  • Project agreements
  • Changes approved through MAG
  • Fixed regional budgets
  • Reallocation of unused project funds
  • Reimbursement basis
  • Reporting requirements
  • Audit considerations

8
Sections
  • Program management administration
  • Lead agency and budgets
  • Project requirements
  • Legal agreements
  • Programming

9
I. Program management administration
  • 100 Definitions
  • 110 Objectives
  • 120 Applicability of policies / procedures
  • 130 Coordination with other modes
  • 140 Reporting
  • 150 Committee process
  • 160 Amendment of policies / procedures

10
II. Lead agency and budgets
  • 200 Lead agencies
  • 210 Project budgets
  • 220 Reimbursement process
  • 230 Reallocation of unexpended funds
  • 240 Determination of unexpended funds
  • 250 Reimbursement for prior work

11
III. Project requirements
  • 300 Project eligibility
  • 310 Project approvals
  • 320 Project amendments

12
IV. Legal agreementsV. Programming
  • 400 Project agreements
  • 410 Memoranda of understanding
  • 500 Project priorities and programming

13
Overview of Interim Policy for Advancements
14
Overview of Interim Policy
  • Set forth the guidelines for advancement of RTP
    street projects.
  • Requires jurisdiction to provide funding.
  • Repayments are made according to the Arterial
    Life-cycle program.
  • Generally parallels freeway policy.
  • Priorities maintained
  • No impact on other projects in the program

15
Options
  • 1. No allowance for inflation for advanced
    projects.
  • 2. Full reimbursement Project costs plus
    inflation.
  • Rate would be the same as that used to adjust
    arterial project costs for general inflation, ex
    3.
  • 3. Sharing of the inflation savings between the
    program and jurisdiction.
  • 50 / 50 sharing used for the freeway program
  • Other sharing arrangements

16
Option 1 No Reimbursement
  • Pro
  • Most fiscally conservative for the RTP budget
  • Less risk for the program.
  • Street program primarily limited to sales tax.
  • May be argued that inflation is not incurred or
    limited for the project once advanced.
  • User pay approach Projects can still be
    advanced if the proponent pays the costs
  • Avoids potential negative appearance of windfall
    reimbursements for projects long since
    completed
  • Con
  • Equity Budgets for other projects implemented
    in later years would be adjusted for inflation
  • Lower incentive for early implementation
  • Advancement of some projects may not happen.

17
Option 2 Full Reimbursement
  • Pro
  • More equitable since all projects programmed in
    the same years would receive the same treatment
    for inflation.
  • More incentive for early implementation
  • More likely to be advanced, with corresponding
    benefits to the region for early implementation
  • Con
  • More complex to administer
  • May have negative appearance for windfall
    reimbursements in later years for projects long
    since implemented.

18
Option 3 Partial Reimbursement
  • Pro
  • Addresses equity issue by allowing some
    reimbursement for inflation
  • Less risk than full reimbursement policy
  • Consistent with the existing Highway Acceleration
    Policy with 50 / 50 sharing.
  • Con
  • More complicated to administer
  • May have some negative appearance for windfall
    reimbursements in later years for projects long
    since implemented.
Write a Comment
User Comments (0)
About PowerShow.com