Formwork For Concrete - PowerPoint PPT Presentation

1 / 27
About This Presentation
Title:

Formwork For Concrete

Description:

Any means or methods which provide temporary support, access, enhancement, or ... load and side pressure from freshly placed concrete, together with construction ... – PowerPoint PPT presentation

Number of Views:825
Avg rating:3.0/5.0
Slides: 28
Provided by: webDc
Category:

less

Transcript and Presenter's Notes

Title: Formwork For Concrete


1
Formwork For Concrete
  • INTRODUCTION

2
Temporary Structures (TS)
  • Definition
  • Any means or methods which provide temporary
    support, access, enhancement, or otherwise
    facilitate the construction of permanent
    structures.
  • Necessity
  • TS form the interface of design and construction.
    Most permanent structures simply could not be
    built without TS.

3
Temporary Structures (continued)
  • Impact on Schedule, Cost, and Quality
  • Losses in time and money will occur if the TS are
    not planned and coordinated with the same degree
    of thoroughness as the permanent structures.
  • Safety
  • Failure of TS have been responsible for hundreds
    of deaths on construction sites. Safety should be
    the overriding priority of contractors and
    designers responsible for implementing TS.

4
Categorizing Temporary Structures
  • Several common types of work which occur on
    construction sites are
  • Formwork
  • Falsework
  • falsework generally serves to support massive
    structural members until such time as these have
    attained sufficient load-bearing capacity and to
    sustain the loads which occur in the course of
    the erection or removal of structures, as imposed
    by structural members, construction and handling
    equipment, and by temporary storage of building
    materials, components and equipment.
  • Rigging
  • Scaffolding
  • Excavation support

5
Responsibility
  • The norm in the construction industry is to place
    the responsibility for TS solely on the general
    contractor. However, architects and engineers
    must at least have formulated their own method of
    construction.
  • Cast in-place
  • Precast
  • Tilt-up
  • Coordinating the design of permanent structure
    with the TS that will be required can lead to
    more efficient and cost effective construction.

6
Design Consideration
  • Safety
  • Designers must place the first priority on
    safety. OSHA codes, as well as other codes in the
    industry, provide stringent performance
    specifications (how the system should work)
    regarding TS.
  • Cost
  • TS can be the most expensive part of some
    construction projects. Designing cost-effective
    solutions to TS problems could easily be the
    competitive advantage of a contractor over
    others. The designer must have a thorough
    knowledge of all the options which will
    sufficiently solve the TS problem.

7
Design Consideration (continued)
  • Unique Design Challenges
  • TS are subject to unique loading conditions which
    do not apply to a permanent structure
    (fluctuating or dynamic loads, impact loads,
    loads which change position).
  • Working within spatial constraints- Cramped sites
    require the most efficient TS so that workers
    still have room to maneuver safely.
  • Uncertainty of soil conditions- It is always
    possible that an unforeseen condition could arise
    during an excavation. Designers must include an
    appropriate factor of safety in their
    calculations or they may consider contingency
    plans for changing soil conditions.

8
The Contractor
  • In many cases the contractor is the only member
    of the construction team with considerable
    experience and practical knowledge of TS.
  • The contractor must hire his or her own engineer,
    if the specifications or building codes require
    one, or self perform the design of TS.
  • The most complex TS are often handled on a
    design-build basis. The design-build situation is
    optimal because it guarantees coordination
    between design and construction.

9
Concrete Formwork (FW)
  • Forms are TS that provide containment for the
    fresh concrete and support it until it can
    support itself.
  • Forms must be designed to support loads of the
    fresh concrete, equipment, workers, impact of
    various kinds, or sometimes wind without collapse
    or excessive deflection.
  • The cost of FW is between 40 to 60 of the cost
    of concrete structure. Design of a good forming
    system could both expedite a project as well as
    reduce costs.

10
Formwork Requirements - 1
  • Safety FW must be
  • Strong ( to carry the full load and side pressure
    from freshly placed concrete, together with
    construction traffic and equipment).
  • Sound (made of good quality, durable materials).

11
Formwork Requirements - 2
  • Quality FW must be
  • Accurate (within specified tolerances for form
    dimension)
  • Rigid (adequately braced and tied to prevent
    movement, bulging, or sagging during
    construction).
  • Tight Jointed (to prevent cement paste leakage
    which disfigures the surface of concrete).
  • Properly Finished (to provide a concrete surface
    of good appearance).

12
Formwork Requirements - 3
  • Economy FW must be
  • Simple (simple to erect and dismantle)
  • Easily handled (the sizes of units should not be
    too heavy to handle)
  • Standardized (ease of assembly and possibility of
    reuse)

13
Causes of Failures
  • Improper stripping and shore removal
  • Inadequate bracing
  • Vibration
  • Unstable soil under mudsill, shoring not plumb
  • Inadequate control of concrete placement.
  • Rate of vertical placement of concrete can
    develop excessive lateral pressure????

14
(No Transcript)
15
(No Transcript)
16
(No Transcript)
17
(No Transcript)
18
Planning for Formwork
  • The contractor should plan FW at the time of
    making bid considering the following factors
  • Placing schedule and stripping time requirements
  • Capacity of equipment available to handle form
    sections and materials
  • Capacity of mixing and placing equipment
  • Construction joints
  • Reuse of forms as affected by stripping time
  • Relative merits of job-built, shop-built and
    ready-made forms.
  • Weather (protection requirements and stripping
    time)
  • Compare alternative methods to determine the most
    efficient plan.

19
Key area of Cost Reduction - 1
  • Planning for maximum reuse
  • A form designed for max reuse is stronger and
    more expensive, but it can save on the total form
    cost.
  • Economical form construction
  • Shop-built (greatest efficiency in working
    conditions and in the purchase and use of
    materials and tools)
  • Shop area on the site (form sections too large or
    transportation cost too high)
  • Job-built (for small jobs, or where forms must be
    fitted to terrain)

20
Key areas of Cost Reduction - 2
  • Buying prefabricated forms(large number of
    reuses)
  • Renting prefab forms(better flexibility in
    regulating volume of work)
  • Setting and stripping
  • Repetition of the same functions to increase the
    crew efficiency as the job progresses
  • Use of metal clamp or special wedge pin
    connections that are secure, yet easy to assemble
    and dismantle
  • Add extra features that make handling, erection,
    and stripping easier (handles, lifting eyes)

21
Other costs affected by FW - 1
  • Cranes and Hoists
  • Size of form sections should be limited to the
    capacity of the largest crane planned for the
    job.
  • Stair towers may be completed early in the
    schedule to be used for moving men and materials.
  • Leave one bay open to permit mobile crane and
    concrete truck movement.
  • Bar Setting
  • Form design can permit the rebar to be pre
    assembled before installation (more favorable
    condition)

22
Other Costs affected by FW - 2
  • Concrete Placement
  • High lifts in wall construction make placing and
    vibration difficult.
  • Placing rate is limited by form design.
  • Other Trades
  • The plan should permit other trades to perform
    their work efficiently and minimize interruptions
    in placing.

23
Loads and Pressures on Forms
  • Lateral pressure exerted by plastic liquid
    concrete
  • Rate of Placement
  • Temperature of concrete
  • Low temperatures produce delayed set, greater
    lateral pressure at base of form
  • Placement height
  • Hydrostatic pressure
  • Vibration increases lateral pressure

24
  • Maximum lateral pressure at any elevation
  • Walls rate of pour less than or equal to 7 ft
    per hour
  • P 150 9000R/T
  • Walls rate of pour greater than to 7 ft per
    hour
  • P 150 43,400/T 2800R?T
  • Maximum P lesser of 2000 psf or 150h
  • P max lateral pressure, psf
  • R rate of placement, ft/hr
  • T temp. of concrete in forms, F
  • h max. ht. of fresh concrete in form, ft

25
Column Forms
  • Maximum lateral pressure at any elevation
  • Columns
  • P 150 9000R/T
  • Maximum P of 3000 psf, a minimum of 600 psf, but
    in no case greater than 150h.
  • P max lateral pressure, psf
  • R rate of placement, ft/hr
  • T temp. of concrete in forms, F
  • h max. ht. of fresh concrete in form, ft
  • Maximum ht. Of a single lift recommended for a
    column pour is 18 ft. within a two-hour period.

26
Example- Rate of Placement
  • Calculate the rate of pour for a section of shear
    wall on the 12th floor of a high rise building.
    Assume the distance from the ground to the top of
    the wall is 168 ft. A tower crane using two
    buckets, each with a capacity of 1.5 cy, has a
    rate of travel of 90 ft/min up and 120 ft/min
    down. Assume a pick-up time of 20 sec. and a
    dump time of 5 minutes
  • Wall height is 14 ft, wall thickness is 10-in.
    and wall length is 60 ft.

27
Example- Concrete Pressure Calculation
  • The shear wall of height 14 ft, wall thickness of
    10-in. and wall length of 60 ft. is poured at a
    rate of 5.65 ft/hr. Calculate the maximum
    pressure developed in the concrete form assuming
    a concrete temperature of 55F.
  • Determine the height to which this maximum
    pressure will extend.
Write a Comment
User Comments (0)
About PowerShow.com