Title: Formwork For Concrete
1Formwork For Concrete
2Temporary Structures (TS)
- Definition
- Any means or methods which provide temporary
support, access, enhancement, or otherwise
facilitate the construction of permanent
structures. - Necessity
- TS form the interface of design and construction.
Most permanent structures simply could not be
built without TS.
3Temporary Structures (continued)
- Impact on Schedule, Cost, and Quality
- Losses in time and money will occur if the TS are
not planned and coordinated with the same degree
of thoroughness as the permanent structures. - Safety
- Failure of TS have been responsible for hundreds
of deaths on construction sites. Safety should be
the overriding priority of contractors and
designers responsible for implementing TS.
4Categorizing Temporary Structures
- Several common types of work which occur on
construction sites are - Formwork
- Falsework
- falsework generally serves to support massive
structural members until such time as these have
attained sufficient load-bearing capacity and to
sustain the loads which occur in the course of
the erection or removal of structures, as imposed
by structural members, construction and handling
equipment, and by temporary storage of building
materials, components and equipment. - Rigging
- Scaffolding
- Excavation support
5Responsibility
- The norm in the construction industry is to place
the responsibility for TS solely on the general
contractor. However, architects and engineers
must at least have formulated their own method of
construction. - Cast in-place
- Precast
- Tilt-up
- Coordinating the design of permanent structure
with the TS that will be required can lead to
more efficient and cost effective construction.
6Design Consideration
- Safety
- Designers must place the first priority on
safety. OSHA codes, as well as other codes in the
industry, provide stringent performance
specifications (how the system should work)
regarding TS. - Cost
- TS can be the most expensive part of some
construction projects. Designing cost-effective
solutions to TS problems could easily be the
competitive advantage of a contractor over
others. The designer must have a thorough
knowledge of all the options which will
sufficiently solve the TS problem.
7Design Consideration (continued)
- Unique Design Challenges
- TS are subject to unique loading conditions which
do not apply to a permanent structure
(fluctuating or dynamic loads, impact loads,
loads which change position). - Working within spatial constraints- Cramped sites
require the most efficient TS so that workers
still have room to maneuver safely. - Uncertainty of soil conditions- It is always
possible that an unforeseen condition could arise
during an excavation. Designers must include an
appropriate factor of safety in their
calculations or they may consider contingency
plans for changing soil conditions.
8The Contractor
- In many cases the contractor is the only member
of the construction team with considerable
experience and practical knowledge of TS. - The contractor must hire his or her own engineer,
if the specifications or building codes require
one, or self perform the design of TS. - The most complex TS are often handled on a
design-build basis. The design-build situation is
optimal because it guarantees coordination
between design and construction.
9Concrete Formwork (FW)
- Forms are TS that provide containment for the
fresh concrete and support it until it can
support itself. - Forms must be designed to support loads of the
fresh concrete, equipment, workers, impact of
various kinds, or sometimes wind without collapse
or excessive deflection. - The cost of FW is between 40 to 60 of the cost
of concrete structure. Design of a good forming
system could both expedite a project as well as
reduce costs.
10Formwork Requirements - 1
- Safety FW must be
- Strong ( to carry the full load and side pressure
from freshly placed concrete, together with
construction traffic and equipment). - Sound (made of good quality, durable materials).
11Formwork Requirements - 2
- Quality FW must be
- Accurate (within specified tolerances for form
dimension) - Rigid (adequately braced and tied to prevent
movement, bulging, or sagging during
construction). - Tight Jointed (to prevent cement paste leakage
which disfigures the surface of concrete). - Properly Finished (to provide a concrete surface
of good appearance).
12Formwork Requirements - 3
- Economy FW must be
- Simple (simple to erect and dismantle)
- Easily handled (the sizes of units should not be
too heavy to handle) - Standardized (ease of assembly and possibility of
reuse)
13Causes of Failures
- Improper stripping and shore removal
- Inadequate bracing
- Vibration
- Unstable soil under mudsill, shoring not plumb
- Inadequate control of concrete placement.
- Rate of vertical placement of concrete can
develop excessive lateral pressure????
14(No Transcript)
15(No Transcript)
16(No Transcript)
17(No Transcript)
18Planning for Formwork
- The contractor should plan FW at the time of
making bid considering the following factors - Placing schedule and stripping time requirements
- Capacity of equipment available to handle form
sections and materials - Capacity of mixing and placing equipment
- Construction joints
- Reuse of forms as affected by stripping time
- Relative merits of job-built, shop-built and
ready-made forms. - Weather (protection requirements and stripping
time) - Compare alternative methods to determine the most
efficient plan.
19Key area of Cost Reduction - 1
- Planning for maximum reuse
- A form designed for max reuse is stronger and
more expensive, but it can save on the total form
cost. - Economical form construction
- Shop-built (greatest efficiency in working
conditions and in the purchase and use of
materials and tools) - Shop area on the site (form sections too large or
transportation cost too high) - Job-built (for small jobs, or where forms must be
fitted to terrain)
20Key areas of Cost Reduction - 2
- Buying prefabricated forms(large number of
reuses) - Renting prefab forms(better flexibility in
regulating volume of work) - Setting and stripping
- Repetition of the same functions to increase the
crew efficiency as the job progresses - Use of metal clamp or special wedge pin
connections that are secure, yet easy to assemble
and dismantle - Add extra features that make handling, erection,
and stripping easier (handles, lifting eyes)
21Other costs affected by FW - 1
- Cranes and Hoists
- Size of form sections should be limited to the
capacity of the largest crane planned for the
job. - Stair towers may be completed early in the
schedule to be used for moving men and materials. - Leave one bay open to permit mobile crane and
concrete truck movement. - Bar Setting
- Form design can permit the rebar to be pre
assembled before installation (more favorable
condition)
22Other Costs affected by FW - 2
- Concrete Placement
- High lifts in wall construction make placing and
vibration difficult. - Placing rate is limited by form design.
- Other Trades
- The plan should permit other trades to perform
their work efficiently and minimize interruptions
in placing.
23Loads and Pressures on Forms
- Lateral pressure exerted by plastic liquid
concrete - Rate of Placement
- Temperature of concrete
- Low temperatures produce delayed set, greater
lateral pressure at base of form - Placement height
- Hydrostatic pressure
- Vibration increases lateral pressure
24- Maximum lateral pressure at any elevation
- Walls rate of pour less than or equal to 7 ft
per hour - P 150 9000R/T
- Walls rate of pour greater than to 7 ft per
hour - P 150 43,400/T 2800R?T
- Maximum P lesser of 2000 psf or 150h
- P max lateral pressure, psf
- R rate of placement, ft/hr
- T temp. of concrete in forms, F
- h max. ht. of fresh concrete in form, ft
25Column Forms
- Maximum lateral pressure at any elevation
- Columns
- P 150 9000R/T
- Maximum P of 3000 psf, a minimum of 600 psf, but
in no case greater than 150h. - P max lateral pressure, psf
- R rate of placement, ft/hr
- T temp. of concrete in forms, F
- h max. ht. of fresh concrete in form, ft
- Maximum ht. Of a single lift recommended for a
column pour is 18 ft. within a two-hour period.
26Example- Rate of Placement
- Calculate the rate of pour for a section of shear
wall on the 12th floor of a high rise building.
Assume the distance from the ground to the top of
the wall is 168 ft. A tower crane using two
buckets, each with a capacity of 1.5 cy, has a
rate of travel of 90 ft/min up and 120 ft/min
down. Assume a pick-up time of 20 sec. and a
dump time of 5 minutes - Wall height is 14 ft, wall thickness is 10-in.
and wall length is 60 ft.
27Example- Concrete Pressure Calculation
- The shear wall of height 14 ft, wall thickness of
10-in. and wall length of 60 ft. is poured at a
rate of 5.65 ft/hr. Calculate the maximum
pressure developed in the concrete form assuming
a concrete temperature of 55F. - Determine the height to which this maximum
pressure will extend.